ANDHRA PRADESH
ELECTRICITY REGULATORY COMMISSION
4th & 5th Floors, Singareni Bhavan, Red Hills, Hyderabad-500 004
R.P. (SR) No. 9 of 2007
in
O.P.No.19 of 2006
Dated: 22.03.2007
Sri Surinder Pal, Member
Sri R.Radha Kishen, Member
Between
and
1. Transmission Corporation of Andhra Pradesh Ltd,
2. Eastern Power Distribution Company of A. P. Ltd,
3. Southern Power Distribution Company of A.P. Ltd
4. Central Power Distribution Company of A. P. Ltd,
5. Northern Power Distribution Company of A. P. Ltd. … Respondents
This petition coming on for hearing on 17.03.2007 in the presence of Sri C.Kodanda Ram and Sri Challa Guna Ranjan, Advocates for the petitioner and Sri P. Shiva Rao, Advocate, for the respondents and having stood over for consideration to this day, the Commission delivered the following:
This review petition is filed under Section 10 (4) of the Andhra Pradesh Electricity Reform Act, 1998 (hereinafter “the Reform Act”) r/w Section 94 (1) (f) of the Electricity Act, 2003 (hereinafter “Act 2003”) seeking review of the Commission’s Order dated 30.12. 2006 in O.P. No.19 of 2006 and praying the Commission to (a) permit the petitioner to be impleaded in the proceeding and allow it to address its submissions to this Commission; (b) direct respondents that the proposed amendment to clause 2.1 of the Power Purchase Agreement (hereinafter “PPA”) be restored to ‘Installed Capacity’ or be amended to ‘Installed Capacity of 370 MW’ instead of ‘limited to 370 MW’; and (c) withdraw the Commission’s approval to the proposed amendment to clause 6.2 of the PPA.
2. The following are the averments made in the review petition :
(a) Due to shortage in the supply of Natural Gas and the inability of Gas Authority of India Limited to supply the allocated quantities of Natural Gas to the petitioner, Respondent No.1 (hereinafter, R-1) filed a petition before the Commission for deletion of the alternate fuel clause from the definition of ‘Fuel’ in the PPA between the parties herein entered into in the year 2004.
(b) While the matter was pending, the petitioner submitted proposals to the Government of Andhra Pradesh (hereinafter “GoAP”) for arriving at an amicable solution on the issue of deletion of the alternate fuel provision from the PPA, which were referred by GoAP to a committee for examination in depth on the said issue. Based on the recommendations of the Committee, the respondents submitted certain amendments to the PPA to GoAP for its approval. After examination, GoAP proposed further necessary action, following which all the respondents herein filed O.P.19 of 2006 for grant of consent by this Commission to the proposed amendments. The Commission invited objections and suggestions on the proposed amendments to the PPA from the public and accordingly notification was published on 01.07.2006.
(c) During the pendency of the proceedings before the Commission, APDISCOMs (collectively the respondents No.2 to 5 herein) proposed certain modifications to the proposed amendments as well as certain additional amendments. A.P. Power Coordination Committee (hereinafter “APPCC”) proposed to the petitioner certain additional amendments in clauses 2.1 and 6.2 of the PPA through letters dated 12.10.2006 and 04.10.2006. By letter dated 24.10.2006, the petitioner herein rejected any amendment to the said two clauses of the PPA. The proposed amendments to clauses 2.1 and 6.2 of the PPA did not form part of the public notice published on 01.07.2006 and hence the petitioner at that time did not have any knowledge with regard to approval of the proposed amendments to the above-mentioned clauses.
(d) The
petitioner was not provided any effective opportunity to present its case
before this Commission and the proposed amendments to clauses 2.1 and 6.2 of
the PPA were not consented to by the petitioner. The Commission did not have
jurisdiction to approve the proposed amendments to the terms of the PPA when
such proposed amendments had not received the petitioner’s consent.
(e) Rationale for such proposed amendments were premised on flawed reasoning resulting in an error apparent on the face of the record. Objectors in the public hearings conducted by the Commission did not pray for the specific amendments, as is apparent from the Commission’s Order (dated 30.12.2006 in O.P.No.19 of 2006). The Commission did not take into account specific and categorical rejection of the proposed amendments to clauses 2.1 and 6.2 of the PPA by the petitioner. During the course of the proceedings, the petitioner herein was not given any notice regarding the proposed amendments to clauses 2.1 and 6.2 of the PPA.
(f) Insofar as the proposed amendment to clause 2.1 of the PPA is concerned, such amendment leads to inconsistencies and grounds for misinterpretation in the PPA, leading to possibility of potential disputes in future. APDISCOMs did not provide any cogent reason or rationale for carrying out of such proposed amendments. The impugned order would result in providing legal sanctity to proposed unilateral amendments to concluded contracts between the parties. The words ‘Installed Capacity of the Project’ is replaced by the words ‘370 MW’, as approved by this Commission by its Order, will create conflict between clause 2.1 and other clauses of the PPA and will create confusion and generate grounds for misinterpretation leading to disputes in future.
(g) Approving
proposed amendment to clause 6.2 of the PPA was immaterial and unnecessary to
the issue under this Commission’s consideration. The analysis of the
Commission, of computation of O&M expenses to be incurred over the extended
period of the PPA, as reported in paragraphs 37, 38, 39 and 40 of the Order is
premised on incorrect hypothesis and assumptions. The assumption that O & M
cost of combined cycle power projects will be within the norms approved by CERC
(Central Electricity Regulatory Commission) is not realistic. The basic premise
of the Commission for approving amendment to clause 6.2 of the PPA, i.e., that
the projected loss of the petitioner being only at Rs.14 crores, is based on an
unrealistic estimation of the O & M cost and therefore, the same is
erroneous and severely flawed
(h) There are a catena of judgments of the Hon’ble Supreme Court of India that where a party is denied its right of fair hearing or is not given adequate opportunity to be heard, such actions of the authority will be contrary to the principles of natural justice and are liable to be set aside. This proposition has been affirmed in Swadeshi Cotton Mills Vs. Union of India, AIR 1981 SC 818, Tribhuvandas Bhimji Zaveri and another Vs. Collector of Central Excise (1997) 11 SCC 276, Punjab National Bank and others Vs. Kunj Behari Mishra (1998 (7) SCC 84, Yoginath D.Bagde Vs. State of Maharashtra and another, AIR 1999 SC 3734, M.Chockalingam and another Vs. Commissioner of Income Tax, Madras and another, AIR 1963 SC 1456.
(i) The Commission has the power to give or withhold its consent or approval to what is submitted before it with mutual consent of the parties. It is humbly submitted that this Commission would not have the mandate in law to approve the proposed arrangements of power purchase on the application of the licensees where the other party to the arrangement i.e., the generating company, objects to such proposed terms, since any approval of such unilateral terms may prove to be infructous if the generating company does not consent to the proposed terms.
(j) The Commission u/s 21(4) and (5) of the Reform Act acquires jurisdiction to give its consent to a PPA or to amendments to PPA only if the parties to the PPA mutually agree on the terms of such PPA or amendments to the PPA. The Commission does not have the jurisdiction to reopen the PPA and abrogate to itself, the power to approve the proposed amendments of the terms of the PPA when the other party i.e., the generating company has not consented to such proposed amendments. The Commission exceeded its jurisdiction in approving proposed amendments to clauses 2.1 and 6.2 of the PPA which amendments have not been consented to by the petitioner.
3. Before admitting the petition, notice was ordered to be issued to the parties. On 17.03.2007, the Commission primarily heard the counsel for the petitioner, on the maintainability of the review petition, who reiterated the various averments mentioned in the petition and further submitted that:
(a) the
project of the petitioner was conceived and developed after obtaining
permission to establish the same through competitive bidding process as per the
policy of the Government of India issued in 1995. The project was originally proposed to be a project with Naphtha
as fuel, later on modified to Gas with Naphtha as alternate fuel. However, the respondents, realizing that in
the absence of availability of gas they will be burdened with payment of fixed
costs, due to generation of electricity from Naphtha not being affordable,
being too costly, have filed petition before the Commission in O.P. No. 25 of
2004 on 09-07-2004 for deletion of the alternate fuel clause in the PPA. In the meanwhile, Act 2003 came into force,
which provided for promotion of competition and market development.
(b) In
several appeals, the Appellate Tribunal for Electricity (hereinafter “the
Tribunal”) held that a PPA once entered cannot be amended. However, on the proposals made by the
respondents and keeping in view the non-availability of Natural Gas, it was
agreed to postpone declaration of Commercial Operation Date (hereinafter “COD”)
so as to alleviate the difficulty of payment of fixed cost and declaration of
COD based on Naphtha, the alternate
fuel.
(c ) This
petition is more in the nature of seeking amendment to the order of consent
given to the PPA entered into between the parties in respect of clauses 2.1 and
6.2. However, the respondents
themselves have come forward with regard to allowing clause 2.1 to remain as it
existed prior to the Order of the Commission.
The other clause, i.e. the clause 6.2,
which relates to ‘Buy-Out’ is not important at this stage of the PPA as
it relates to a situation that may arise after the completion of the period of
PPA, when the APDISCOMs may choose to take over the project and not at this
stage.
(d) The
amended PPA as submitted by the respondents herein in O.P.No.19 of 2006 was
agreed upon by the parties as a package, after detailed commercial negotiations
and cannot be disturbed without the consent of the petitioner herein.
(e) Thus the issue of maintainability of the petition is not an
issue. It is prayed that the Commission may admit the petition, since the
petition is maintainable.
4. The point that arises for consideration is :
“Whether the review petition is maintainable”
5. The
counsel for the petitioner laboured hard to contend that the petitioner was not
provided with effective opportunity to present its case and that the amendments
proposed to clauses 2.1 and 6.2 of the PPA were not consented to by it. The
request for proposed amendments to clauses 2.1 and 6.2 of the PPA was filed before
the Commission on 06.11.2006 and it did not form part of the public notice
issued on 01.07.2006 and consequently, the petitioner was unaware of the
proposed approval of these amendments proposed by APDISCOMs. The Commission did
not invite objections from the petitioner with regard to such modified
amendments. The petitioner had no reason to believe that the proposed
amendments to clauses 2.1 and 6.2 of the PPA have been filed before the
Commission for its consent by APDISCOMs since it had specifically and
categorically rejected such proposed amendments by its letter dated 24.10.2006
to APPCC. As a result, adverse consequences of such proposed amendments were
not brought out in its entirety before the Commission and it amounts to
violation of principles of natural justice.
6. The
next contention of the counsel for the petitioner is that the negotiations in
the context of gas shortage and deletion of alternate fuel clause were based on
commercial negotiations and finalized as a package. The draft PPA which was
agreed upon and initialed between the parties does not contain any amendment to
clauses 2.1 and 6.2. Unilateral change of commercial clauses, which formed part
of the ‘negotiated and agreed package’ is inequitable in principle.
7. The
further contention of the counsel for the petitioner is that the Hon’ble
Appellate Tribunal for Electricity in its recent judgment dated 02.06.2006 in
Appeal No. 1 of 2005 and batch, held that the Commission has no authority to
reopen the concluded contract or PPA. It is also held therein that agreements
entered into by the Board (predecessor-in-interest of the respondents
herein) and the developers are
statutory and binding on the respondents herein, as well as on the Commission.
The Commission cannot, therefore, either nullify or modify the concluded
contracts in purported exercise of regulatory powers vested in it. The
rationale of the above judgment is affirmed by the Tribunal in Rithwik Energy
Systems Ltd Vs. APTRANSCO and others in Appeal No. 90 of 2006 and batch and
similar views were expressed by it in several other appeals.
8. Before
adverting to the various contentions raised on behalf of the petitioner, it is
necessary to dwell on the proceedings set in motion which led to passing of the
order dated 30.12.2006 by the Commission in O.P.No.19 of 2006. Grant of consent
to PPA or amendment to PPA is an elaborate exercise. In the case on hand, the
Commission invited objections and suggestions from the public as required under
law on the proposed amendments to the PPA entered into between the petitioner
and the respondents. The circumstances that led to negotiations, submission of
proposals to GoAP on 02.03.2006, constitution of Committee by GoAP, its
recommendations, receiving objections / suggestions by general public, response
of the respondents, holding public hearing on 17.07.2006 and 27.07.2006,
Commission’s analysis on the various issues with regard to the proposed
amendments, etc., have all been discussed in detail in the said Order. As there
is no dispute with regard to the process of grant of consent to the proposed
amendments as such, it is not necessary to go into detail.
9. Suffice
it to say that the entire challenge to Order dated 30.12.2006 passed by the
Commission in O.P.No.19 of 2006 revolves around grant of consent to the
amendments in respect of clauses 2.1 and 6.2 of the PPA which were proposed by
the respondents in its affidavit dated 06.11.2006 in spite of rejection of the
said proposed amendments by the petitioner herein. In this context, it is necessary to state that during public
hearing held on 17.07.2006 and 27.07.2006,
the issue of the buy-out provision after termination of the PPA was
raised and the respondents were asked to clarify the matter. In pursuance
thereof, by letter 04.10.2006 the APPCC (an entity co-ordinating the activities
of all the respondents herein) on behalf of the respondents proposed amendments
to clause 6.2 of the PPA. Subsequently,
by letter dated 12.10.2006, the APPCC on behalf of the respondents also
proposed to amendments to Article 2.1 and paras 1 and 3 of Article 3.2 of the PPA. In response to the said two
communications, the petitioner by its letter 24.10.2006, responded by
intimating APPCC that modifications to Articles 2.1 and 6.2 are not necessary.
With regard to paras 1 and 3 of Article 3.2, however, the petitioner agreed to
the proposed modifications.
10. Even though the petitioner has stated that modification to Articles 2.1 and 6.2 are not necessary, the APPCC, through the Chief General Manager (Comml & RAC) on behalf of R-4 and respondents No.2, 3 and 5 proposed amendments to the said two Articles, requesting the Commission to take a view in the matter and include the proposed amendments while issuing consent to the amendments. The fact that the petitioner was requested to accept the said modifications and its response that modification to Article 2.1 and 6.2 are not necessary would go to show that the petitioner had prior knowledge of the proposed amendments. The Commission after careful consideration of the matter and for the reasons recorded in its Order dated 30.12.2006 (in O.P.No.19 of 2006) granted consent to the amendments proposed, in exercise of regulatory powers vested in the Commission u/s 24(4) of the Reform Act and Section 86 of the Act, 2003.
11. It
is well-settled proposition in law that review jurisdiction cannot be used as
appellate jurisdiction. Mere mistake in appreciation of evidence or an
inference drawn from material placed before the Commission, would not amount to
“mistake” or “error apparent on the face of record” as contended by the counsel
for the petitioner. Where decision was taken by the Commission on appreciation
of oral and documentary evidence, review jurisdiction cannot be invoked on the
said grounds.
12. During
the course of hearing in O.P. No.19 of 2006, the Commission heard the matter at
length on all the issues relating to grant of consent to the proposed
amendments. After careful consideration of the material placed before it,
objections of the general public and other stakeholders on various issues and
concerns expressed during the public hearing as well as the written responses,
the Commission issued its Order dated 30.12.2006 and granted consent to the
amendments proposed to the PPA as mentioned in detail in Annexures I to IV
appended to the said Order. Thus the
Order dated 30.12.2006 was passed by the Commission after consideration of all
relevant facts and on appreciation of evidence, both documentary and oral.
While doing so, the Commission was required to take certain views in the matter
of grant of consent considering different propositions, especially in the light
of apprehensions of general public. In our view, reconsideration of the said
order sought by the petitioner would amount to substituting one view with
another and the same is not permitted under law.
13. No
doubt power of review can be exercised for correcting a mistake, but it should
not be exercised to substitute a view.
In the case of Lily Thomas Vs Union of India reported in (2000) 6 SCC
224 = AIR 2000 SC 1650, the Hon’ble Supreme Court held that the power of review
can be exercised for correcting a mistake but not to substitute a view. The
Hon’ble Supreme Court in the case of M/s. Jain Studios Ltd Vs Shin Satellite
Public Co. Ltd reported in AIR 2006 SC
2686 observed that the power of review can be exercised with extreme care,
caution and circumspection and only in exceptional cases. In Commission’s view,
there is no mistake or error apparent on the face of record requiring review of
the order dated 30.12.2006. The
Commission, therefore, does not agree with the counsel for the petitioner that
because of mistake or error apparent on the face of record or that there exists
other sufficient reason to necessitate this Commission to review the order
dated 30.12.2006 with regard to Articles 2.1 and 6.2 of the PPA. For the said reason there is no necessity
to advert to the different judgments cited by the counsel for the petitioner in
support of various grounds for review of the impugned order. It is not out of place to mention here that
if aggrieved by the Order dated 30.12.2006 passed by the Commission in
O.P.No.19 of 2006, the petitioner is at liberty to seek remedy elsewhere and
not by way of filing the present petition to review the Order passed by the
Commission.
14. For
the reasons mentioned above, the Commission is of the view that the petitioner
has failed to make out a case for the maintainability of the petition. In the
result, the petition is not admitted as not maintainable.
The order is corrected and signed on this 22nd day of March, 2007
|
Sd/- |
Sd/- |
Sd/- |
|
(R.RADHA KISHEN) |
(SURINDER PAL) |
(K.SWAMINATHAN) |
|
MEMBER |
MEMBER |
CHAIRMAN |
CERTIFIED COPY