ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION

11-4-660, 4th & 5th Floors, Singareni Bhavan, Red Hills, Hyderabad.

 

O R D E R

 

R.P.No.   5 / 2004

R.P.No. 12 / 2004

 

Dated  07-07-2004

Between

1. Small Hydro Power Developers Association – R.P 5/2004                                 

2. M/s Active Power Corporation Pvt. Limited – R.P 12/2004     ….Petitioners

 

AND

Transmission Corporation of Andhra Pradesh                            …. Respondent

 

 

1)         Andhra Pradesh Electricity Regulatory Commission (Commission) initiated        suo-motu proceedings for determination of tariff in  R.P. No. 84 / 2003 in         O.P. No. 1075 / 2000 applicable to  Non-Conventional Energy (NCE) Projects of Andhra Pradesh to take effect from 01-04-2004 onwards.

 

2)         The Commission passed the order dated 20-03-2004, wherein the Commission determined the tariff, terms and conditions for purchase of power by Transmission Corporation of Andhra Pradesh (hereinafter APTRANSCO) from the following categories of Non-Conventional Energy based Power Projects:

 

i)                    Biomass-based energy and Biomass-based  Co-generation Plants

ii)                  Bagasse- based Co-generation plants

iii)                Mini-Hydel Power Projects

iv)                Wind Electricity Generators

v)                  Industrial Waste based Energy Projects

vi)                Municipal Waste based Energy Projects.

 

3)         While deciding on the purchase price and other terms in respect of different categories of Non-Conventional Energy based projects, the Commission adopted a “Cost plus” approach and allowed a fair amount of return compared to the adhoc price earlier fixed based on the guidelines of Ministry of         Non-Conventional Energy Sources (MNES) issued in 1993. While rationalizing the tariffs and adopting the cost plus approach, the tariff for some categories of NCE Developers underwent a revision leading to reduction in the tariffs.  Aggrieved by some of the provisions of the said order, the following developers of NCE projects filed writ petitions in the Hon’ble High Court of Andhra Pradesh:

 

i)                    M/s. Biomass Energy Developers Association

ii)                  M/s. Small-Hydro Power Developers Association

iii)                M/s. Sree Rayalaseema Hi-Strength Hypo Ltd (Bio-mass Developer)

iv)                M/s. Vensa Bio-Tek Limited

v)                  M/s. Active Power Corporation Pvt. Limited

vi)                M/s. South India Sugar Mills Association

vii)              M/s. Raus Power Pvt. Ltd

viii)            M/s. Sai Renewable Power Pvt. Ltd.

 

Out of the above, the present order deals with non-conventional energy from Mini Hydel plants namely those listed at serial numbers (ii) and (v) above. The Commission is passing separate orders on the review petitions filed by other categories of non-conventional energy developers.

 

4)         The Hon’ble High Court by order dated 27-04-2004 has directed as under:

 

            The Developers Association is permitted to file review petition against the impugned orders dated 20-03-2004 before APERC as contemplated under section 94 (1) (f) of the Electricity Act, 2003 within a period of ten days from the date of issue of the order and on such filing, the respondent.  Regulatory Commission is directed to dispose of the same within a period of eight weeks thereafter.  Till passing of such order, as per the interim orders passed by the Court on 01-04-2004 the existing tariffs shall continue in force”.

 

5)                 Pursuant to the directions of the Hon’ble High Court, the petitioners filed petitions No. 5 / 2004 and 12 / 2004 before the Commission for review of the order dated 20-03-2004 passed by the Commission.  The APTRANSCO,
Sri M.Venugopala Rao, Correspondent, Prajashakthi and Peoples Monitoring Group on Electricity Regulation also filed petitions for review of the order dated 20.3.2004 passed by the Commission, for downward revision of the tariffs. The other parties were given opportunities to file replies to the review petitions by NCE developers or APTRANSCO, etc., as the case may be.  The copies of the review petition of APTRANSCO were also served on NCE Developers who had earlier participated in the proceedings for determination of the tariffs, terms and conditions leading to the passing of the Order dated
20th March 2004 by the Commission.  The Commission conducted a hearing on 11-06-2004 and invited the developers, APTRANSCO, Sri. M.Venugopala Rao, Correspondent, Prajashakthi, and Peoples Monitoring Group on Electricity Regulation to present their case on the review petitions filed before the Commission.  Non-conventional Energy Development Corporation of Andhra Pradesh Limited (hereinafter NEDCAP) had also been directed to present their views as intervenor.

 

6)                 Besides the issues on merits, the petitioners raised a number of legal issues on the maintainability of the proceedings before the Commission as well as the jurisdiction of the Commission to pass the impugned order. The gist of the contentions raised by the petitioners is as under:

 

(a)       The Commission on maintainability and jurisdiction could not have lawfully initiated the proceedings under or in pursuance of its earlier order dated 20-06-2001 in O.P. No. 1075 / 2000 when that order had been suspended by the Hon’ble High court, even in case of                 non-conventional generating companies who had agreed, or would agree, in the future to sell their entire generation to APTRANSCO.

 

(b)       From 10-06-2003, the functions of the Commission are only those that are specifically provided for by the Electricity Act, 2003 and the Commission cannot act in pursuance of anything other than under the said Act, such as, any consensus or private reference or any contract or agreement. The Electricity Act 2003 contemplates and provides only for the determination of tariff by the Commission for generating companies for sales to distribution licensees (as defined in section          2 (17) of the Electricity Act 2003) and only in the manner provided in Part VII of the Electricity Act 2003.  The Commission could not have exercised jurisdiction under section 21 (4) of the Andhra Pradesh Electricity Reform Act 1998 and determine the price at which NCE developers shall sell electricity to APTRANSCO.

 

(c)    The Commission omitted to consider the specific provisions of sections 62 and 64 of the Electricity Act, 2003 which clearly provide for the manner in which the determination of tariff of generating companies shall be carried out.  Section 62 (1) (a) of the Electricity Act, 2003 provides that the State Commission shall determine the tariff in accordance with the provisions of the Electricity Act, 2003 for the supply of electricity by a generating company to a distribution licensee.  Section 64 of the Electricity Act, 2003 provides for the procedure for tariff order.  Section 64 (1) provides that an application for determination of tariff under section 62 shall be made by a generating company in such manner and accompanied by such fee as may be determined by the regulations.  The function of determination of tariff for generation within the State, referred to in Section 86 (1) (a), is to be performed only to the extent and in the manner expressly provided by the said Act. The jurisdiction of the Commission to determine the tariff in respect of the sales of electricity generated by a generating company is only in respect of sales to distribution licensees.   The Commission could not  lawfully undertake proceedings for determination of the tariff of generating companies in respect of sales to any one other than distribution licensees, such as the APTRANSCO.

 

(d)       Even if it is assumed that the provisions of section 21 (4) of  Andhra Pradesh Electricity  Reform Act would apply to the respondent in respect of its purchases made during the transitional period, the Commission  exceeded its jurisdiction and scope in making the order under review as the APTRANSCO  is allowed to undertake trading  only for a maximum period of one year from the date of commencement of the  Electricity Act, 2003 and consequently could purchase electricity as a bulk supply licensee under the Reform Act only till 09-06-2004.  Effective from 10-06-2004, APTRANSCO is prohibited from purchasing electricity or trading in electricity and therefore the question of any tariff for the purchase of electricity by the respondent after that date cannot at all arise.  Accordingly, the fixation of tariff for 10 years by the impugned order is not correct.

 

(e)              Section 21 (4) of the Reform Act does not provide for the determination of tariff of a generating company by the Commission. Section 21(4) contemplates only consent to be given by the Commission to an agreement between the respondent and a generating company for the purchase of electricity by the respondent. The scope of the said section 21 (4) is only in respect of evaluating an agreement for the purchase of electricity by a licensee and the scope of the said section cannot be expanded to undertake determining the tariff binding on both the generating company and the licensee; and neither the licensee can be compelled to purchase at the price determined by the Commission nor the generating company can be compelled to sell at the determined price.

 

(f)                 The Commission ought not to have considered the hypothetical possibility of the so-called segregation of the respondent’s activities into transmission activities and trading activities.  The Commission  ought to have seen that the Electricity Act does not speak of such segregation. The Electricity Act, 2003 prohibits the respondent, a State Transmission Utility, from trading in electricity. The Commission could neither lawfully bind a yet unborn and yet unconceived trading entity by its order, nor could it lawfully bind a generating company to sell to a yet unborn and yet unconceived trading entity at prices determined in the manner set out in the Commission’s order.

 

(g)              Even if the Government creates another entity in future for engaging in trading activities, such an entity will have to obtain a trading licence under the Electricity Act, 2003 and be bound by the terms of such licence and the provisions of the Act.  It is not permissible for any trading licensee to be granted any kind of monopoly in the purchase or sale of electricity.  The change from a Single Buyer Model to Multi Buyer Model is one of the essential features of the Electricity Act, 2003.  A distribution licensee cannot be compelled to purchase electricity from only a single specified trading licensee.

 

(h)               The mandatory requirement of the section 86 (1) (e) of the Electricity
Act 2003 cannot be said to have been complied with by merely stating the total quantum of purchase from NCE sources in the tariff order for the year 2004-05 issued separately issued by the Commission, as stated by the Commission in the order dated 20.03.2004.  It is not the total quantum that is required to be specified by the Commission. The provision requires the Commission to specify the percentage of the total consumption in the area of a distribution licensee that shall be purchased from renewable sources of energy.

 

(i)                 Section 64 (1) of the Electricity Act, 2003 contemplates that the generating company would make an application to the State Commission for the determination of the tariff for sale to distribution licensees.  A plain reading of section 64 makes it abundantly clear that the application is to be made by the generating company.  The proceedings initiated by the Commission and the Commission’s order under review have the effect of unlawfully pre-empting and precluding an application to be made under section 64 (1) by a generating company for sale to a distribution licensee.

 

(j)                 The order S.O. 672 (E) dated 09-06-2004, issued by the Central Government under section 183 of the Electricity Act, 2003 authorising the State Transmission Utilities to engage in the activity of bulk purchase and sale of electricity to distribution companies for a further period of one year is not legal and valid.

 

(k)               Section 39(1) of the Electricity Act 2003 provides that the State Transmission Utility shall not engage in the business of trading in electricity.  The said provision was effective immediately on the date of commencement of the Electricity Act 2003.  This provision did not, by itself, provide for any transitional relaxation.  All State Transmission Utilities were prohibited from engaging in trading in electricity from the date of commencement of the Act, i.e. 10-06-2003.

 

(l)                 The transactions between generating companies and electricity traders are not to be regulated by the Commission under the Electricity
Act 2003.  Except for licensing under section 14 and fixing of trading margins under section 86 (1) (j), there is no regulatory function, power or jurisdiction of the Commission over the activities of electricity traders, more particularly in respect of tariffs.  There is no provision in the Electricity Act, which provides for the determination of any tariff by the Commission of the purchases by an electricity trader or for the determination of the tariff of any generating company for sale to an electricity trader.

 

Commission’s Analysis on the issue of maintainability of the proceedings initiated by the Commission and the jurisdiction of the Commission:

 

7)                 Before dealing with the contentions of the petitioners, it will be necessary to set out the developments in the electricity laws relevant to the present proceedings. The Andhra Pradesh Electricity Reforms Act, 1998 (hereinafter for brevity referred to as the Andhra Pradesh Act) came into force on 1.2.1999.  The Andhra Pradesh Act was enacted by the Legislature of the State of Andhra Pradesh and the assent of the President was taken under Article 254 of the Constitution of India for the Andhra Pradesh Act. The Andhra Pradesh Act therefore prevailed over the provisions of the Central Laws which were then in existence namely the India Electricity Act, 1910, the Electricity (Supply) Act, 1948 and the Electricity Regulatory Commissions Act, 1998. The Commission was constituted under the Andhra Pradesh Act on    03-04-1999.

 

8)        Section 21 (4) and (5) of the Andhra Pradesh Act, amongst others, dealt with the purchase of electricity by licensees from generating companies and it reads as under:

(4) A holder of a supply or transmission licence may, unless expressly, prohibited by the terms of its licence, enter into arrangements for the purchase of electricity from,-

 

(a)        the holder of a supply licence which permits the holder of such licence to supply energy to other licensees for distribution by them; and

 

(b)                any person or Generating Company with the consent of the Commission.

 

            (5) Any agreement relating to any transaction of the nature described in sub-sections (1), (2), (3) or (4) unless made with, or subject to such consent as aforesaid, shall be void”.

 

9)         The Andhra Pradesh Act enabled the reorganization of the erstwhile Andhra Pradesh State Electricity Board (APSEB). In exercise of the powers under the Andhra Pradesh Act, the APSEB was reorganized with effect from 1.2.1999.  Under the reorganization, APTRANSCO was initially the licensee for transmission, bulk supply, distribution and retail supply of electricity in the State.  Thereafter, effective 1.4.2001, the functions of distribution and retail supply of electricity in the State were transferred from APTRANSCO and vested in four distribution companies. The APTRANSCO continues to undertake the transmission and bulk supply functions including the purchase of electricity from generating companies in bulk and sale and supply of electricity in bulk to the four distribution companies.

 

10)       By order dated 20.6.2001 passed in O.P. 1075 of 2000, the Commission directed the NCE developers to sell the electricity generated in their projects to APTRANSCO only and not to third parties. This order of the Commission was challenged by some of the NCE developers in appeals filed before the Hon’ble High Court on the ground that the Commission has no jurisdiction to compel the NCE developers to sell the electricity to APTRANSCO. The Hon’ble High Court vide order dated 16-07-2001 passed in CMA 1753 of 2001 was pleased to suspend the order passed by the Commission.  In view of the above, the direction given by the Commission to NCE Developers to sell electricity only to APTRANSCO and not to third parties was not implemented in that the developers were not mandated to sell electricity to APTRANSCO pending the decision of the Hon’ble High Court. However, some of the developers on their own agreed to sell the electricity to APTRANSCO on the tariff, terms and conditions determined by the Commission in OP No.1075 of 2000 vide order dated 20.6.2001.  Thus those NCE developers including of Mini Hydel Power projects who had agreed to sell electricity to APTRANSCO duly accepted the tariff and other terms and conditions for such sale contained in the order dated 20-06-2001 and signed and implemented the agreements with APTRANSCO. There was an agreement between such NCE Developers and APTRANSCO consistent with the provisions of section 21(4) of the Act, which was approved by the Commission.  The tariff and other terms and conditions and other stipulations contained in the order dated 20.6.2001 therefore became binding on such developers.

 

11)      The Order dated 20-06-2001 specifically stated that the tariff, terms and conditions for sale of electricity by the NCE developers to APTRANSCO shall be subject to review and the reviewed tariff, terms and conditions shall be effective from 01-04-2004. As mentioned above, while accepting to sell electricity from their projects, the developers also agreed to the review of the tariff terms and conditions by the Commission for sale of electricity by them to APTRANSCO.  The proceedings leading to the order dated 20.3.2004 were pursuant to the above stipulation contained in the order dated 20.6.2001 which were accepted by such of the NCE developers who had agreed to sell electricity to APTRANSCO on the tariff and other terms and conditions contained in the said order.

 

12)      In accordance with the above, the Commission initiated the proceedings for review of the tariff, and other terms and conditions for sale of electricity by NCE developers to APTRANSCO and has passed the order dated                  20-03-2004. It is relevant to clarify that by the order dated 20-03-2004, the Commission is not mandating in any manner those NCE developers who have not accepted the earlier order dated 20-06-2001 passed by the Commission, while their challenge to the order is pending the decision by the Hon’ble Court. However, such of the NCE developers who had accepted the earlier order dated 20-06-2001 and have been selling electricity generated by them to APTRANSCO cannot challenge the jurisdiction of the Commission to review the terms as per the stipulation contained in the order dated 20.6.2001. In the circumstances mentioned above, the contention of the petitioners that in view of the fact that the Commission’s order dated 20-06-2001 in
O.P.No.1075/2000 had been suspended by the Hon’ble High Court and the Commission therefore cannot initiate review proceedings as stipulated in the order dated 20-06-2001 even for such developers who had voluntarily agreed to sell electricity to APTRANSCO accepting the said order, is without any merit.

 

13)      The Electricity Act, 2003 came into force on 10.6.2003.  As mentioned above, the issue whether the NCE developers can sell electricity to third parties or not during the period from 1.4.2001 till the coming into force of the Electricity  Act, 2003 is pending for decision by the Hon’ble Court. After the coming into force of the Electricity Act, 2003, the generating companies are entitled to sell electricity to the persons of their choice subject to the provisions of sections 38 to 42 of the Electricity Act, 2003.   The above change brought about by the Electricity Act, 2003, allowing the generating companies to sell electricity to consumers cannot be interpreted to mean that the generating companies who had earlier agreed to sell electricity to APTRANSCO under a valid contract can now resile out of the agreement and sell the electricity generated by them to others. The NCE developers will continue to be bound by the agreement solemnly entered into by them. The Electricity Act does not provide that such agreements shall terminate or shall otherwise be void or voidable.

 

14)      The Electricity Act, 2003 makes certain transitional provisions. Section 14 and proviso 1 to it read as under:

 

“The Appropriate Commission may, on application made to it under section 15,  grant a licence to any person –

 

(a)                to transmit electricity  as a transmission licensee; or

(b)                to distribute electricity  as a distribution licensee; or

(c)                to undertake  trading  in electricity as an electricity trader, in any area which may be specified  in the licence:

 

Provided that any person engaged in the business of  transmission or supply of electricity under the provisions of the repealed laws  or any Act  specified in the Schedule on or before the  appointed date shall be  deemed to be  a licensee under this Act  for such period  as may be stipulated in the  licence, clearance or approval granted to him under the repealed  laws  or such Act  specified in  the Schedule, and the provisions of the repealed laws or such Act    specified  in  the  Schedule  in respect of such  licence shall apply  for a period of one year from the date of commencement of this Act  or such  earlier period  as may be  specified, at the request of the licensee, by  the Appropriate  Commission  and thereafter  the provisions of this Act  shall apply to such  business”:

 

15)             Thus in terms of the above provisions, the APTRANSCO as a licensee shall continue to be governed by the provisions of the Andhra Pradesh Act and the applicable provisions of the previous Central Laws for a period of one year in regard to its licences. The licence of APTRANSCO shall be governed by the provisions of the Electricity Act, 2003 after the period of said one year.   Accordingly the restrictions contained in sections 39 and 41 of the Electricity Act, 2003 prohibiting the State Transmission utility and the Transmission Company from engaging in trading were not to be applicable to APTRANSCO till 09-06-2004.  When the order dated 20.3.2004 was passed by the Commission, the prohibition contained in sections 39 and 41 of the Electricity Act was not therefore applicable to APTRANSCO. There was then no restriction on APTRANSCO purchasing the electricity from the generating companies for resale to the distribution companies.  The validity of the order passed by the Commission needs to be judged based on the law applicable as on the date of the order and not with reference any subsequent events.  There is therefore no illegality or invalidity in the order dated 20-03-2004 passed by the Commission as per the law applicable at the relevant time. 

 

16)             The next issue arises as to whether the order dated 20-03-2004 which sanctions the purchase of electricity by APTRANSCO from the NCE developers and its resale to the distribution companies can be continued to be maintained even after 9.6.2004 when the transitional period of one year envisaged under the Electricity Act, 2003 comes to an end and section 39 of the Electricity Act prohibiting the State Transmission Utility from engaging in trading activity should apply.  In terms of section 39 read with sections 131, 132, 133 and 172 of the Electricity Act, 2003 what is required to be implemented is the segregation of the trading functions of the State Transmission Utilities and not the termination of the any agreement for purchase and sale of the electricity as sought to be contended by the petitioners. The Electricity Act allows APTRANSCO to transfer either the trading activity or the transmission utility to another company to fulfill the requirement of sections 39 and 41 of the Electricity Act. Such a transfer of the function can be done through a transfer scheme notified under sections 131, 132, 133 etc. of the Electricity Act and also read with sections 23 and 24 of the Andhra Pradesh Act.

 

17)             As and when APTRANSCO transfers the above function of purchase of electricity to the distribution companies and/or entities as per the requirement under the Electricity Act, 2003, the rights and obligations under the existing agreements including the purchase of electricity from the developers on the tariff terms and conditions determined by the Commission under the impugned order shall stand assigned and transferred to such transferee(s).  The agreements with NCE developers will not therefore come to an end because of the prohibition contained in section 39 of the Electricity Act, 2003 on the State Transmission Utility from engaging in trading.  The NCE developers will be bound to honour the agreements with the assignees or transferees under the above statutory transfer scheme.  In this regard, the following specific provisions of the Electricity Act, 2003 and the Andhra Pradesh Electricity Reform Act, 1998, are relevant:

 

ELECTRICITY ACT, 2003:

“39.         (1)       The State Government may notify the Board or a Government company  as the State Transmission Utility:

        

Provided that the State Transmission Utility shall not engage in the business of trading in electricity:

 

Provided further that the State Government may transfer, and vest any property, interest in property, rights and liabilities connected with, and personnel involved in transmission of electricity, of such State Transmission Utility, to a company or companies to be incorporated under the Companies Act, 1956 (1 of 1956) to function as transmission licensee through a transfer scheme to be effected in the manner specified under Part XIII and such company or companies shall be deemed to be transmission licensees under this Act.

 

131  (4)   The State Government may, after consulting the Government company or company or companies being  State Transmission Utility or generating  company or transmission licensee or distribution licensee, referred  to in sub-section (2)  (hereinafter referred to as the transferor),  require  such transferor to  draw up a transfer scheme to  vest  in a transferee being any  other  generating  company or transmission licensee or distribution licensee, the property, interest in property, rights and liabilities which have been vested in the transferor under  this section, and publish  such scheme as statutory transfer scheme under  this Act.

 

                  131 (5)      A transfer scheme under this  section may-

(a)       provide for the formation of subsidiaries, joint venture companies or other schemes of division, amalgamation, merger, reconstruction or arrangements which shall promote the profitability and viability of the resulting entity, ensure economic efficiency, encourage competition and protect consumer interests;

 

(b)        define the property, interest in property, rights and liabilities to be allocated -

 

(i)      by  specifying  or describing the property, rights and liabilities in question;  or

 

(ii)          by referring to all the property, interest in property, rights and liabilities comprised in a described part of the transferor's undertaking; or

 

(iii)         partly in one way and partly in the other;

 

(c)         provide that any rights or liabilities stipulated or described in the scheme shall be enforceable by or against the transferor or the transferee; 

 

(d)        impose on the transferor  an obligation to enter into such written agreements with or execute such other instruments in favour of any other subsequent transferee as may be stipulated in the scheme;

 

(e)     mention the functions and duties of the transferee;

 

(f)     make such supplemental, incidental and consequential provisions as the transferor considers appropriate including provision stipulating the order as taking effect; and

 

(g)        provide that the transfer shall be provisional for a stipulated period.

 

131   (6)       All debts and obligations incurred, all contracts entered into and all matters and things engaged to be done by the Board, with the Board or for the Board, or the State Transmission Utility or generating company  or transmission licensee or distribution licensee, before a transfer scheme becomes effective shall, to the extent specified in the relevant transfer scheme, be deemed to have been incurred, entered into or done by the Board, with the Board or for the State Government or the transferee and all suits or other legal proceedings instituted by or against the Board or transferor, as the case may be, may be continued or instituted by or against the State Government or concerned transferee, as the case may be.

 

ANDHRA  PRADESH  ACT, 1998:

 

23 (5) The State Government may, after consulting the APTRANSCO (the "transferor licensee"), or generating company or companies, as the case may be, require them to draw up a transfer scheme to vest in a further licensee (the "transferee licensee") or any generating companies,  any of the functions including distribution function, property, interest in property, rights and liabilities which have been vested in the transferor licensee or generating companies, as the case may be under this section and publish the same as Statutory Transfer Scheme under this Act.  The Transfer Scheme to be notified under this sub-section shall have the same effect as the Transfer Scheme under sub-section(2).

 

23 (6) A transfer scheme may,-

(a)               provide for the formation of subsidiaries, joint venture companies or other schemes of division, amalgamation, merger, reconstruction or arrangements;

 

(b)               define the property, interest in property, rights and liabilities to be allocated:-

 

(i)                  by specifying or describing the property, rights and liabilities in question;

 

(ii)                by referring to all the property, interest in property, rights and liabilities comprised in a specified part of the transferor's undertaking; or

 

(iii)              partly in the one way and partly in the other;

(c)                provide that any rights or liabilities specified or described in the scheme shall be enforceable by or against the transferor or the transferee;

 

(d)               impose on the licensee an obligation to enter into such written agreements with or execute such other instruments in favour of, any other subsequent licensee as may be specified in the scheme;

 

(e)               make such supplemental, incidental and consequential provisions as the transferor licensee considers appropriate including provision specifying the order in which any transfer or transaction is to be regarded as taking effect; and

 

(f)                  provide that the transfer shall be provisional for a specified period.

 

23        (7) All debts and obligations incurred, all contracts entered into and all matters and things engaged to be done by the Board, with the Board or for the Board, or the APTRANSCO or generating company or companies before a transfer scheme becomes effective shall, to the extent specified in the relevant transfer scheme, be deemed to have been incurred, entered into or done by the Board, with the Board or for the State Government or the transferee and all suits or other legal proceedings instituted by or against the Board or transferor, as the case may be, may be continued or instituted by or against the State Government or concerned transferee, as the case may be.

 

23 (8) In the event that a licensee is required to vest any part of its undertaking in another licensee pursuant to sub-section (5), the Commission shall amend the transferee’s license in accordance with section 19 or revoke its licence in accordance with section 18.”

 

18)        In accordance with the above provisions, the rights, obligations, responsibilities etc. assumed by APTRANSCO under the existing agreements and arrangements with the generating companies including those with NCE developers in terms of the stipulation contained in the Commission’s orders dated 20.6.2001 and 20.3.2004 shall vest in the successor entity and there shall be no vacuum in this regard. The Commission is therefore entitled to proceed on the basis that there shall be some entity / entities to succeed to the rights and interests as well as the obligations of APTRANSCO to comply with the requirements of the Electricity Act, 2003.

 

19)        The provisions of the Andhra Pradesh Act do not cease to apply after the coming into force of the Electricity Act, 2003 on 10.6.2003 and even after the transition period of one year specified in the said Act.  Section 185 (3) of the Electricity Act, 2003 read as under:

“185    (3)       The provisions of the enactments specified in the  Schedule, not inconsistent with the provisions  of this Act, shall  apply to the States in which such enactments  are applicable”.

 

The Schedule to the Electricity Act lists the Andhra Pradesh Act as one of the specified enactments.  Accordingly, except where a provision in the Andhra Pradesh Act is inconsistent with the Electricity Act, 2003, the provisions of the Andhra Pradesh Act will continue to apply. The Commission can therefore continue to exercise functions and powers under the provisions of the Andhra Pradesh Act which are not inconsistent with the Electricity
Act, 2003. 

 

20)      The Electricity Act, 2003, does not prohibit the determination of the tariff terms and conditions for purchase of electricity by a trading licensee from a generating company.

 

           Section 86 of the Electricity Act, 2003, inter alia, read as under:

“86.     (1)      The State Commission shall discharge the following  functions,  namely: -

 

(a)       determine  the tariff for  generation, supply, transmission  and wheeling of electricity,  wholesale,  bulk or retail,  as the case may be, within the State:

 

Provided  that where  open access  has been permitted to a category  of consumers under section 42,  the State Commission  shall determine only the  wheeling charges and surcharge thereon,  if any, for the said category of  consumers;

 

   (b)          regulate  electricity purchase and procurement process of distribution licensees including  the price at which electricity shall be procured  from the generating  companies  or licensees or from other sources through agreements for purchase of  power for  distribution  and supply within the State”;

 

21)      It can be seen from the above that sub-clause (b) of clause (1) of section 86 of the Electricity Act, 2003 deals specifically with the Commission’s function to regulate the purchase and procurement process of electricity by the distribution companies from the generating companies and also from others including from trading licensees.   Sub-clause (a) of clause (1) section 86 of the Electricity Act is however wider and it deals with the determination of generation tariff without any qualification or condition that such determination of tariff can be restricted only to circumstances when the generating companies sell electricity to a distribution licensee.  Accordingly, the contention of the petitioners that the Commission can determine the tariff only for the purchase of electricity by the distribution companies from the generating companies and not generally for the sale by the generating companies is without merit.  There is also no inconsistency in the provisions of the Andhra Pradesh Act and the Electricity Act 2003, in this regard.  Further, as mentioned above, the order of the Commission was passed on
20-03-2004 i.e. during the transition period of one year when section 21(4) of the Andhra Pradesh Act was applicable by virtue of first proviso to
Section 14.  Therefore, even assuming for the sake of argument that there was any inconsistency between the Andhra Pradesh Act and the Electricity Act 2003, it will have no bearing.  Further, such tariff is being determined by the Commission as envisaged in the order dated
20-06-2001 earlier passed by the Commission. There is a specific provision in the Power Purchase Agreements (hereinafter PPAs) entered into by the members of the Petitioner-Association who had agreed to sell the electricity to APTRANSCO that the purchase price and incentives effective from 01-04-2004 can be reviewed by the Commission and a further review will take place on completion of 10 years after commercial operation date.  The members of the Petitioner-Association were therefore aware that the prices are subject to revision effective from
01-04-2004.  The NCE developers who had accepted the earlier order and has been selling electricity to APTRANSCO cannot raise any issue on the validity of the determination of the tariff by the Commission in terms of the stipulations contained in the said order dated 20-06-2001. 

 

22)      The petitioners have urged that the combined reading of sections 61, 62 and 86 of the Electricity Act, 2003, shows that the Commission has no jurisdiction to compel a generating company to sell electricity to a trading company and the Commission cannot determine the tariff, terms and conditions of such sale. According to the petitioners, section 86(1)(a) of the Electricity Act cannot be interpreted in isolation. The petitioners have urged that the Commission omitted to consider the specific provisions of sections 62 and 64 of the Electricity Act, 2003 which clearly provide for the manner in which the determination of tariff of generating companies shall be carried out. According to the petitioners, in the absence of an application as per the provisions of section 64, the Commission cannot proceed to determine or revise or review the tariff suo-motu.  

 

23)      The above contentions of the petitioners have no merits in the facts and circumstances of the present case. The Commission has not and will not compel any NCE developers to enter into agreements with either APTRANSCO or any other person including a distribution company.  Prior to the Electricity Act, 2003, the Commission exercised its functions under the Andhra Pradesh Act, and refused the permission sought by NCE developers to sell electricity generated by them to the consumers directly and provided that such NCE developers may sell the electricity to APTRANSCO on the terms and conditions contained in the order dated 20.6.2001.  The order of the Commission dated 20.6.2001 was suspended by the Hon’ble High Court on filing of the writ petitions by some of the NCE developers in the context of the Commission not permitting the sale of electricity to consumers and directing such developers to sell electricity to APTRANSCO.  However, some NCE developers voluntarily accepted the order dated 20.6.2001 passed by the Commission and entered into PPAs with APTRANSCO. In the proceedings leading to the order dated 20-03-2004, the Commission has considered and determined the tariff, terms and conditions for the supply of electricity by such NCE developers who had agreed to accept the earlier order dated 20-06-2001 passed by the Commission.  The Commission has jurisdiction to decide on the tariff, terms and conditions for such NCE developers for the period from 01-04-2001 for the reasons that:

 

a.      It relates to existing agreements between APTRANSCO and the NCE developers at the time when APTRANSCO was the Bulk Supply Licensee and was entitled to purchase and sell electricity in the State and as a licensee, APTRANSCO has been under the regulatory control of the Commission including in regard to tariff at which the electricity shall be purchased or procured;

b.      The order dated 20-06-2001 clearly provided for such review of the tariff, terms and conditions by the Commission effective 01-04-2001 and the concerned NCE developers have accepted the same and have been supplying electricity generated by them to APTRANSCO based on the above.

c.      APTRANSCO as on the date of the passing of the order dated                 20-03-2004 was the deemed trading licensee in terms of section 14 proviso 1 of the Electricity Act, 2003. As a licensee, APTRANSCO is under the regulatory control of the Commission and the Commission can review the tariff terms and conditions at which APTRANSCO procures electricity for resale to the distribution licensees;

d.      Section 86 (1) (f) of the Electricity Act, 2003, empowers the Commission to adjudicate on the issues related to the agreement between the generation company and the licensees.

e.      Section 86(1)(a) of the Electricity Act, 2003, empowers the Commission to determine tariff in the case of generating companies which have entered into agreements for sale of electricity generated by them;

f.        Whatever has been decided by the Commission in the orders dated 20.6.2001 and 20.3.2004 on the sale and purchase of electricity between the NCE developers and APTRANSCO will enure to the benefit of the company which will succeed to the trading functions presently being undertaken by APTRANSCO. The agreements will not become void or voidable merely because the Electricity Act requires that as the State Transmission Utility APTRANSCO should not carry on trading in electricity after the transition period.   

 

24)      The next contention of the petitioners is that the Commission should not have proceeded to determine tariff terms and conditions for the sale of electricity beyond the transition period of one year. The petitioners have contended that the Commission has been aware that with the coming into force of the Electricity Act, 2003, APTRANSCO has to cease to undertake trading function after the transition period and there is therefore no question of deciding on the tariff for the post-transition period on the sale of electricity by the NCE developers.  As mentioned above, the Electricity Act, 2003, does not render void the existing agreements between the APTRANSCO and NCE developers after the transition period.  The Act only requires the segregation of the transmission and trading functions. On such segregation, the entity which will succeed to the trading function will assume all the rights and obligations of APTRANSCO for the remaining period of the PPAs.  The Commission has the power to determine tariff of the generating companies (NCE developers) and has also the function to regulate the trading licensee.  There is therefore no merit in the contention of the petitioners on the lack of jurisdiction of the Commission to determine tariff for the NCE Developers for the period beyond the transition period.  

 

25)      The Government of India vide notification dated 09-06-2004 has extended the transition period for the State Transmission Utility to continue the trading for a further period of one year.  This order is passed by the Government of India under section 181 of the Electricity Act. The petitioners have urged that the Government of India has no authority to extend the transition period in exercise of the powers to remove difficulties. The Notification issued by the Government of India is specific and clear and it has reference to representations filed by States and also to section 172 of the Electricity Act. The Commission cannot examine the statutory validity or invalidity of the notification issued by the Government of India under the Electricity Act, 2003. In any event, for the reasons mentioned hereinabove, the order passed by the Commission on 20-03-2004 was valid and in accordance with the law applicable as on the date of the order.  The effect of the provisions of the Electricity Act requiring APTRANSCO as a State Transmission Utility to transfer the Trading function after the transition period and the implication of any non-compliance thereof are independent issues.  In the above context, there is no error or mistake in the order dated 20-03-2004 passed by the Commission calling for any review. 

 

26)      The petitioners contended that the Commission has to fix a percentage of the total consumption in the areas of distribution licensees that shall be purchased from renewable sources of energy.  This is an independent issue and is not relevant for the present case.  By the order dated 20-03-2004, the Commission has determined the tariff in respect of the projects for which the members of the Petitioner-Association have entered into PPAs and those developers who may be interested to sell power to APTRANSCO in future.  The Commission will decide the percentage at the appropriate time and the fixation of percentage of energy has no bearing on tariff determination.

 

            ON MERITS OF THE ORDER

            The issues on merits raised by the petitioners and the Commission’s analysis are as under:

 

27)      Study team Report:

           

The petitioners have contended that the report of the study team appointed by the Commission to visit some of NCE projects is not made available to the petitioners.  In this connection, it is stated that the report of the study team is in respect of biomass and bagasse-based projects and not related to             Mini-Hydel Plants.

 

28)      Tariff determination procedure:

            The Petitioner-Association contend that the law contemplates the determination of tariff upon an application from the generating company.  The Commission’s conclusion that a two-part tariff will be difficult to implement in view of large number of projects of small capacity is unreasoned.  According to the Petitioner-Association, in the computer era and age of information technology, such reasoning is not understandable. The respondent stated that the Order dated 20-03-2004 virtually means tariff for individual projects, linked as it is to their date of implementation.  The respondent contemplates to put in place necessary system to implement orders of the Commission.

 

The Commission has already discussed the rationale for not adopting the conventional two-part tariff at paragraph (30) of the Commission’s order which reads as under:

“The Commission recognises the fact that two part tariff will be difficult to implement in view of the large number of the plants of low capacity.  But at the same time, the Commission considers that beyond the threshold level of generation, the developers should get only variable cost (if any) and incentives and not the fixed charges.  The Commission would also like to determine the tariff for all the projects of one category based on the year of commissioning of each project”.

 

The two-tier tariff contemplated by the Commission based on the benchmark performance level (Plant Load Factor, or PLF) would distinguish those plants, which are operating at varying operating conditions.  This would virtually mean a two-part tariff, modified to suit the non-conventional projects.  This methodology is based on scientific principles and applied in respect of tariff for the power plants across the country.  In view of the above, the contention of the petitioners seeking the adoption of a two-part tariff as in case of conventional projects is not warranted and merits no consideration.

 

29)      Two-tier tariff:

 

The other Petitioner, M/s. Active Power Corporation Private Ltd., contends that the two-tier tariff fixed by the Commission with 35% threshold PLF would result in closure of NCE projects, in particular in case of the Petitioner’s own project.  As per the petitioner, it has to pay term loan of Rs. 30 lakhs (inclusive of interest) every quarter apart from meeting operational costs.  The Petitioner contends that full cost recovery up to 100% PLF must be allowed to meet O & M expenses.

 

APTRANSCO submitted that the contention of the petitioner neither reflects the correct position with regard to petitioner’s profitability in the past nor does it take into account any normative parameters for the future operations.  Hence the case does not warrant specific consideration.

 

As explained earlier in this Order, the developers can recover full fixed cost at 35% PLF.  A developer cannot expect the same tariff, also inclusive of the fixed costs component, even after covering his fixed costs in full as this will unduly burden the consumers apart from deviating from the practice generally followed in the power industry.  Hence the Commission does not accept the petitioner’s submission.

 

30)      Capital Cost:

The Petitioner-Association submitted that the Commission has arbitrarily taken the project cost as Rs. 4.5 Crs. per MW.

 

It has further stated that the Commission, having agreed that the cost of smaller projects is more than that of the larger projects due to economies of scale,  should have given effect to the reality.

 

It has also stated that as per the information submitted by the Petitioner-Association, the actual project cost lies between Rs. 4.18 Crs.,  and Rs. 7.14 Crs / MW for various projects with capacity ranging from 7.5 MW to 0.75 MW.  Considering the above, the petitioner stated that adoption of        Rs. 4.5 Crs. per MW merely on the basis of undetailed indications given by APTRANSCO and NEDCAP is not proper.

 

The Petitioner-Association has also contended that this Commission has stated that the MNES, has been providing more capital subsidy for new smaller projects and less for bigger projects and that the said consideration is not correct and, in any case, is not relevant for the facts of the case.  The MNES has categorically confirmed in letter dated 05-04-2004 to the                     Petitioner-Association that it has been providing interest subsidy for small hydro power projects and that no capital subsidy was given to projects which had taken first disbursement from financial institutions by 31-03-2003.  It was further submitted by the Petitioner that even in the case of those projects which receive first disbursement after 01-04-2003, as per the capital subsidy scheme, the first MW is given a capital subsidy for Rs.75 lakhs, with each additional MW being given capital subsidy @ Rs.12.5 lakhs per MW, and not a capital subsidy of Rs.87.5 lakhs per MW as stated in the Commission’s order dated 20-03-2004.  In view of this factual position, the Commission’s taking into consideration a capital subsidy of 0.875 Crs, by which the already arbitrary rate of Rs. 4.5 Crs. / MW was further reduced, is not justified or warranted. 

 

The other Petitioner, M/s. Active Power Corporation Private Limited, has also contended that the Commission should have considered actual project costs of individual projects, and submitted that its project cost was       Rs. 7.91 Crs for a capacity of 1.4 MW.

 

APTRANSCO stated that the MNES guidelines for the interest subsidy, which were existing prior to the capital subsidy regime, had stipulated maximum eligibility ceilings of capital cost at Rs.4 Crs. (for capacity of above 1 MW) and Rs.5 Crs. (for capacity of less than 1 MW).  It contended that these  ceilings are a sort of benchmark for capital cost.  Also that, going forward for the capital subsidy regime, though MNES has not stipulated the capital cost, it relied on the benchmarks already established for providing capital subsidy.  Therefore, once a norm (indicated through the subsidy regime) is in place, any higher cost of project for any capacity cannot become a specific case for consideration. 

 

APTRANSCO further submitted the project cost of the mini-hydel stations installed by APGENCO as follows :

 

S.No.

Name of the Station

Capacity

Project Cost

1.

D-83 Kakatiya Canal Peddapally

9th Mile

 

2 x 500 KW

 

249 lakhs

2.

10th Mile

3 x 220 KW

140 lakhs

3.

14th Mile

2 x 500 KW

307.38 lakhs

4.

16th Mile

2 x 500 KW

276.22 lakhs

5.

18th Mile

3 x 220 KW

150 lakhs

6.

19th Mile

3 x 230 KW

165 lakhs

7.

Palair

2 x 1000 KW

375 lakhs

 8.

Chettipeta

2 x 500 KW

388.17 lakhs

 

It also highlighted that as per the Indian Renewable Energy Development Agency (hereinafter IREDA) norms for financing of the          mini-hydro schemes, the projects should satisfy three conditions, namely (a) technical soundness, (b) least cost design, and (c) should have a financial return of 12%.  The guidelines clearly stress for minimization of project cost, thereby calling for efficiencies in project planning and execution. 

In this background, keeping the norms of MNES as well as requirement of IREDA (being one of the financiers to the sector) in view, there is no justification for considering any higher ‘actual’ costs of the projects for tariff determination.

 

With regard to categorisation of projects below 1 MW capacity and projects above 1 MW capacity, APTRANSCO stated that there are only 4 projects operating below 1 MW (totaling up to 2.5 MW) out of the entire capacity of 84 MW set up by 25 developers.  Given this scenario, the installed capacity is more skewed towards developers with more than 1 MW.  The Commission has considered base cost of Rs.4.5 Crs./ MW for hydro projects, which favours majority of the capacity installed in the State.

 

APTRANSCO also contended that the structure of the subsidy scheme, either on account of interest subsidy or on account of capital subsidy tends to factor in economies of scale. For example, during the interest subsidy regime, there was a maximum support ceiling, which was progressively decreasing for larger projects.  In case of the capital subsidy, similar subsidies are provided for first MW and reduced subsidies for subsequent MWs.  The phenomena of economies of scale are also observed from the actual projects provided by the Petitioner-Association (though not to be considered as benchmarks for tariff determination). Given the above, the Commission’s benchmarking of the project cost, after accounting for subsidy, is therefore appropriate for tariff determination.

 

APTRANSCO, while responding to M/s. Active Power Corporation Ltd.,  submitted that the Petitioner’s contention of higher capital cost (Rs. 5.65 Crs/ MW) is without any basis and reasoning and as such does not make any ground for revising the benchmarks. The Petitioner has already earned Rs.13.58 Crores i.e., twice the estimated project cost and 1.7 times the project completion cost as submitted by the petitioner during the last 4 years of the project operation. 

 

The objectors, Sri. M.Venugopala Rao and Peoples Monitoring Group  on Electricity Regulation, pleaded that higher cost should not be considered.  Peoples Monitoring Group also submitted that some of the projects had already recovered their full capital cost or near-full cost, so the payments already made for such projects be also considered while fixing the tariff. 

 

The Commission notes that the project costs of APGENCO’s
mini-hydel projects – none exceeding 1 MW capacity – as tabulated above range from Rs.1.80 crs. to Rs.3.88 crs. / MW. The Commission, however, adopted the project cost of Rs. 4.5 Crs / MW for the reasons already stated in its Order dated 20-03-2004. The preceding submissions fail to make out any case for review of the project cost.  However,  it is relevant that the Commission had adjusted the capital subsidy of Rs. 87.5 lakhs / MW based on the information filed by NEDCAP with its  letter No. NEDCAP / PD / APERC/2004, dated: 24-02-2004. Now the Petitioner-Association has provided a clarification obtained from MNES vide MNES letter No. 2(13)
2000-SHP dated: 05-04-2004, to the effect that the subsidy for the first 1 MW is only Rs.75 lakhs and thereafter @ Rs. 12.5 lakhs per MW. The Commission takes note of this clarification that capital subsidy progressively decreases with the increase in capacity.   The Commission  also recognises the fact that the capital cost too tends to decrease with the increase in  capacity due to economies of scale. Hence, the Commission revises the last 3 lines of paragraph 65 of its Order dated March 20, 2004 to read as follows:

 

“The Commission therefore considers that a uniform capital cost of   Rs. 3.75 Crs/MW (Rs. 4.5 crs less capital subsidy of Rs. 0.75 crs) would be reasonable for mini-hydel projects, whether small or large”.

 

Similarly, the Table in para 76  of the order is also revised as follows:

Year of operation

(nth year)

Tariff

Rs / Unit

1st

2.69

2nd

2.60

3rd

2.52

4th

2.43

5th

2.34

6th

2.26

7th

2.17

8th

2.09

9th

2.00

10th

1.92

 

 

31)      Plant Load Factor:

The Petitioner-Association contends that the Commission ought not to have determined a PLF of 35% without considering compensation for those years in which actually realized PLF is less than 35%.  The detailed information from which the proposed averages have been computed has not been made available to the Petitioner-Association.  Mere arithmetical average is non-conclusive of anything. Further, the Commission is to be concerned with the future; the trends of change are more relevant than the changes themselves.  The Commission ought to have made projections for the future taking into consideration the relevant circumstances.  It has further stated that the statement of Chief Engineer / Nagarjuna Sagar is so general and bereft of any supporting information or details that it cannot be considered anything more than an unreasoned ipse dixit.   It is neither evidence nor relevant to the facts of the case.  The Petitioner contends that the declining and alarming positions of the years 2001-2004 are known and not disputed and the Commission ignored this aspect and fixed the benchmark at 35%. 

 

APTRANSCO submitted that while determining the PLF for a long term, long-term trends hold relevance rather than the short-term trends.  It further submitted that the average PLF for these plants for the period prior to              FY 2000 is above 40% for which the data has already been submitted to the Commission.  Most of the capacity additions in the State had taken place by the year 2000 when the total capacity of Mini-Hydel Plants had reached    more than 50% of the present capacity.  The average PLF during FY 2000 and FY 2001 was more than 40%.  The PLFs considered are, therefore, achievable.  The generation was affected during 2003 primarily due to reduced monsoon in Karnataka.  The projects are based on long term hydrology studies conducted before determining capacities.  The contention of the Petitioner-Association is therefore baseless.

 

One of the objectors, Sri. M. Venugopala Rao, opined that the benchmark parameter of 35% PLF is too low and would cast huge burden on the consumers.  He suggested that inefficient projects that are unable to achieve even this level of performance, should not be encouraged.

 

The Commission discussed in detail the views of the developers, NEDCAP, APTRANSCO, Irrigation department and the average PLF of the seven years from 1996 in paragraph 66 of its Order dated:20.03.2004 and determined the threshold PLF as 35%. In addition to the above, the Commission observes the following:   

 

a)                 The project planning and capacity determination in respect of hydel projects has necessarily to be based on long term study of hydrological data and possible future scenario.

 

b)                 When the projects were conceived in and around the year 2000, the issues that could possibly arise out of construction and completion of the projects in the upper riparian States (including Alamatti) against the background of “Krishna River Water Tribunal Award” were too well known and must have been taken into consideration.

 

c)                  If the planning is to be based on short term data, large-sized hydel projects could not have been conceived and constructed. 

 

d)                 The sites for the projects have been selected by the developers themselves on their own as submitted by Chief Engineer / Nagarjuna Sagar  at the time of hearing leading to the issue of Commission’s order dated 20-03-2004 (paragraph 66), and if the sites selected are such that they support very low PLF, the APTRANSCO or the consumers at large cannot be expected to shoulder the consequential undue extra burden.

 

e)                 The Commission does not find any reason to dismiss the submission of a responsible officer like Chief Engineer/ Nagarjuna Sagar, made during the course of open hearing in the presence of Petitioner-Association that bad monsoons is not a permanent feature and is cyclic in nature.

f)                    Even the large plants at Nagarjuna Sagar and Srisailam (Right & Left) Power Houses are built on long term forecasts ranging from 25-50 years.

 

g)                 A point raised by the Petitioner-Association in regard to the normative PLF is that the inclusion of the unusually high PLF of a single developer (M/s.Active Power Corporation Pvt. Ltd.,) had unrealistically raised the average PLF.  It suggested that such unusual level of PLF as well as the projects with zero PLF should be excluded before computing the average PLF.  An exercise has been carried out in the Commission on this basis and it is observed that the results are not much different.  It is particularly  seen that in respect of the (calendar) years 1998, 1999 and 2000, the three normal monsoon years in the recent past and the period when the number of small hydro projects in operation was substantial (10 to 27), the average PLF works out to 35.06%.

 

h)                  Further, the normative PLF of 35% has been adopted based on the recommendations of NEDCAP, as they have details of performance of the NCE projects, and are the nodal agency for promotion thereof.

 

i)                    The Commission therefore is of the opinion that the benchmark parameters of 35% PLF is reasonable and achievable.

 

Hence the Commission does not find any justification to review this component.

 

The other petitioner, M/s. Active Power Corporation Private Ltd., raised the issue of reduction in inflows and power generation due to construction of cooling towers at Vijayawada Thermal Power Station.

 

The Petitioner contends that due to proposed construction of cooling towers for three generating units at Vijayawada Thermal Power Station (VTPS), drawal of water by Irrigation Department from Budameru diversion canal and completion of Basavaramatarakam lift irrigation scheme at Vijayawada in 2004-05, the water availability would get reduced substantially and power generation would come down from 12.5 MU to 4 MU.  Regular annual maintenance of bund and electrical machinery may cause further reduction in power generation.  The Commission passed its order dated           20-03-2004 without considering the above.

 

APTRANSCO submitted that the allegations of the Petitioner are baseless.  It further submitted that the Petitioner’s Mini Hydel Power Project was commissioned in April 2000, and from April 2000 to March 2004, the Petitioner’s Mini Hydel Project has delivered 42.69 MU (at about 90% PLF) to the grid for sale to APTRANSCO for which APTRANSCO paid                            Rs. 13.58 Crores to the Petitioner towards cost of power.  It further stated that the Petitioner’s Mini Hydel Project delivered 0.96 MU in March 2004 at a PLF of above 100%.  Even if the assumption that generation comes down due to the factors stated above, the project would safely generate power above the threshold PLF of 35% considered by the Commission.

 

Notwithstanding what is stated by APTRANSCO, the Commission opines that there would indeed be reduction in power generation when the proposed cooling towers are constructed for three of the six generating units of Vijayawada thermal power station and irrigation scheme mentioned above is completed.  However, Commission agrees with the conclusion of APTRANSCO that the PLF of the project is unlikely to fall below 35%.  The Commission, therefore, finds no reason to review the threshold PLF of 35%, as fixed  in its Order dated 20-03-2004.

 

32)      Incentive:

The Petitioner-Association contends that the fixation of incentive at a low level of 21.5 paise per unit for generation above the PLF of 35% is not rational and reasonable.  The criteria for fixing 21.5 paise per unit is not indicated in the Commission’s order.  The Commission did not even consider allowing shortfall to be recouped in the subsequent year when the PLF is above 35% by allowing full-cost tariff for such additional energy in such subsequent year.

            The reasons for introducing incentive beyond threshold level are explained at paragraph (76) of the Commission’s order which reads as under:

 

“As observed earlier, fixation of uniform tariff across all mini hydel power plants with varying operating conditions would lead to unequal tariffs.  The Commission therefore proposes a two tier tariff for the mini hydel power plants distinguishing those operating up to 35% PLF and other operating above 35% PLF.  The Tariff indicated above will be applicable for the Power Plants up to PLF of 35% and where PLF during a settlement period exceeds 35%, only an amount of 21.5 paise per unit  as has been allowed to other categories of NCE developers (in place of the tariff indicated above) shall be paid for every unit delivered in excess of 35% PLF at generator terminals i.e. including captive and auxiliary consumption”.

 

            The incentive scheme has been introduced by the Commission in such a way that while allowing adequate return to the developer and providing necessary motivation to generate beyond the threshold PLF, the consumer is not unduly burdened.  This is based on the provisions made by Central Electricity Regulatory Commission (hereinafter CERC) in respect of conventional projects.   Any business is fraught with risks.  It is, however, not fair to pass on all risks to the consumers.  Therefore, the philosophy of payment of full tariff during surplusing years to compensate for shortfall in other years is not rational and cannot be accepted.

 

Subsequent to the issue of Order dated 20-03-2004, however, CERC in its notification dated 26-03-2004 revised the incentive rate to 25 paise/ unit for ex-bus energy beyond the target PLF.  The Commission, taking note of the above, allows revision of incentive from 21.5 paise/ unit to 25 paise / unit on the same lines as CERC order.  This will however be effective from              01-04-2004.

 

33)      Auxiliary consumption:

The Petitioner-Association pleaded that fixation of Auxiliary Consumption at 1% based on CERC guidelines is not correct as the          Mini-Hydel plants are small in capacity.  It pleads for additional allowance for transformation losses.

 

APTRANSCO submitted that the detailed project reports made available by some of the Small Hydro Developers show Auxiliary Consumption as 1% and it is reasonable.

 

The Commission does not consider that there can be any substantial difference in transformation loss for Mini-Hydel projects in comparison to other hydel projects.  Hence the Commission does not find any reason to review the Auxiliary Consumption fixed at 1% in its Order dated 20-03-2004.

 

34)      O & M expenditure:

The Petitioner-Association contends that allowing for operation and maintenance (O&M) expenditure at 1.5% of capital cost following the Central Electricity Authority (hereinafter CEA) guidelines is an error. It has submitted that CEA guidelines are not applicable to small hydro plants and that the actual expenditure is as high as 4.7%, depending on individual circumstances and location, size, etc. of the projects.

 

The other petitioner, M/s. Active Power Corporation Private Ltd., contends that it has to incur Rs.90 lakhs every year towards O&M expenditure and 1.5% of Capital cost fixed by the Commission is unreasonable.

 

APTRANSCO submitted that the O&M expenditure during the first 4-5 years is almost negligible and 1.5% as provided by APERC is reasonable.

 

APTRANSCO also submitted that Rs.90 lakhs projected for  O&M cost corresponds to 11% which is most unrealistic and not justifiable.

 

The Commission cannot consider an individual case, especially that of a developer which is reported to have earned  revenue of twice its estimated project  cost and 1.7 times the project completion cost in the preceding four years of the operation of the project as referred to in paragraph 30 of this Order, as the basis for laying down a benchmark. As to the contention of the petitioners that CEA guidelines are not applicable to small hydro plants, the Commission observes that allowing the O&M expenditure as a percentage of a capital cost is justifiable and equitable, considering the fact that the capital cost of a project is linked with the capacity of the plant and the economies of scale accrue to bigger projects.  Hence there are no grounds for review of the component of O&M expenditure fixed as per CEA guidelines.

 

35)      Rate of interest:

M/s. Active Power Corporation Pvt. Ltd., contends that adoption of 12% rate of interest on term loan is incorrect stating that it is paying interest at 14%.

APTRANSCO submitted that the nodal agency NEDCAP has proposed interest rate of 8.5% while the Commission has allowed 12%.  The Petitioner may swap the loan if really paying 14% interest rate.  It has further submitted that the contention of the Petitioner that the Commission has ignored the objections raised by the Petitioner and proposals submitted by NEDCAP is incorrect.  Recommendations of NEDCAP have been considered by the Commission on merits.

 

 

The Commission in its order dated 20-03-2004 (paragraph 73) has observed as under:

 

“APTRANSCO has considered the interest on term loans at 13% for the existing and 10% for the new projects. 

 

The developers of mini hydel projects during hearing stated that prevailing interest rates are higher as no interest subsidy is available from MNES.  They requested for a provision of 14%.

 

NEDCAP indicated an interest rate of 8.5% for the existing (after interest subsidy) and 11.75% for the new projects.

 

While determining the project cost, the Commission has adopted same price for both existing and new projects. The capital subsidy or interest subsidy more or less nullifies the higher interest rate for one category vis-à-vis the other one. As the Commission considered the capital cost after adjusting for capital subsidy, interest rate is considered without adjusting for the interest rate subsidy.  Hence Commission considers the interest rate of 12% for both existing and new projects”.

 

As observed in the Order of the Commission dated 20-03-2004, uniform rate of interest has been provided for existing as well as new         Mini-Hydel projects taking into consideration the fact that the capital subsidy available to the new projects is offset by the interest subsidy available to the old projects.  Further the Petitioners can take advantage of the falling interest rates for swapping of loans.  In view of all these considerations, the Commission does not find any justification to review this component.

 

36)      Annual escalation:

 

The Petitioner-Association stated that while determining the annual escalation for operation and maintenance, the Commission has fixed it at 4%, ignoring the IREDA norm of 5% and expressed reservations on relevance of WPI & CPI.

APTRANSCO submitted that as per CEA guidelines, O&M costs are required to be escalated by assigning weightage to both WPI & CPI.  CEA has fixed similar norms for diesel sets having smaller capacities.

 

The Commission observes that determination of escalation based on WPI & CPI is an accepted practice across the country and the escalation as provided in the Order dated 20-03-2004 is accordingly in order and requires no review.

 

37)      Payment of Royalty charges:

The Petitioner-Association stated that the Commission has directed that water royalty charges shall be paid directly by APTRANSCO and the DISCOMs to the Government.  It questioned as to how the DISCOMs have come into the picture.  It is further submitted that it does not appear that the Commission has jurisdiction to make such a stipulation as royalty charges, if any, are to be paid by the developer to the Government and the recovery of the same too is enforceable only against the developers.

 

APTRANSCO submitted that the Petitioner has completely misunderstood the proposition.  The reference to DISCOMs is made with a futuristic view of the emerging sector structure with regard to payment of royalty.  APTRANSCO / DISCOMs are contemplating to evolve certain structure and would propose measures for payment of royalty.

 

The Commission observes that as long as a suitable            mechanism / procedure is evolved for payment of royalty to the State Government, it is immaterial which agency discharges the obligation.  Accordingly, the Commission finds no grounds justifying a review of its impugned Order in regard to this component.

 

38)      Debt-equity ratio :

 

The Petitioner-Association  submitted that while the debt-equity ratio of 70: 30 is relevant in the ordinary circumstances considering the norms of financial institutions, the extraordinary circumstances of the small hydro power developers at present have not been taken into account.  The developers incurred losses over the past three years due to inadequate power generation by reason of extremely poor inflows.  Consequently, the debts had been restructured with interest amounts being converted into term loans to the extent of 45% over and above the original debt.  Under the conditions, the debt service costs have gone up.  The Petitioner stated that these extraordinary circumstances have not been taken into consideration by the Commission.

 

APTRANSCO submitted that neither APTRANSCO nor the consumers in the State are responsible for such debt restructuring and skewed debt equity.  It further stated that though there are PPAs in the country which have skewed debt-equity structure yet the tariff is based on normative parameters; therefore such a consideration is not justifiable.

 

The debt-equity ratio is a norm, which is followed uniformly by the lenders for project financing.  The Commission has adopted the same in its Order dated 20-03-2004 and finds no justification for review thereof. 

 

39)      Income-tax :

 

The Petitioner-Association submitted that the Commission has not appreciated the true position with regard to Minimum Alternate Tax (MAT) and provisions with regard to income-tax.  Further, the tax holiday period in case of some developers is coming to an end and they have to pay income-tax at 35% plus 10% surcharge which should have been allowed as a pass-through.

 

APTRANSCO submitted that the Commission has considered a 16% return which provides necessary margin for meeting MAT obligation.  It has further stated that in case the tax holiday is coming to an end, these projects might be at the threshold of completing 10 years of operation.  As such, as per the Order of the Commission dated 20-06-2001, these projects may come under review of tariff which can be undertaken at the appropriate time.    

 

The Commission has provided return on equity at 16% to all             non-conventional projects including the small-hydro power projects, taking into account the MAT obligation also.  Further, these projects enjoy a 10-year tax holiday.  As per the Commission’s Order, there will be a review of tariff for individual projects on completion of 10 years.  The Commission, while reviewing the tariffs applicable to individual projects on completion of 10 years will take into consideration this aspect also.   Presently, therefore, there is no case for a review.

 

40)      Settlement period:

 

The Petitioner-Association submitted that in case of seasonal operation, such as that of Small Hydro Power Projects, the settlement period of one month for the application of the benchmark 35% PLF is erroneous.  The settlement period for such projects cannot be less than a whole year.

 

APTRANSCO also submitted that the PLF computation should be on annual basis for payment of incentive.

 

The Commission hereby clarifies that PLF computation and payment of incentive beyond threshold PLF shall be on annual basis only.

 

41)      Year of Operation:

 

It is submitted by the Petitioner-Association, without seeking any specific relief,  that the Commission erred in determining the tariff for 10 years and determining that the existing and the new projects shall be entitled to tariff, based on the year of operation in the schedule provided in paragraph 76 of the Commission’s order dated 20-03-2004, and the same is without any rationale.

 

The Commission however, clarifies that the year of operation for the purpose of payment of fixed charges shall be reckoned from the date of commercial operation. The variable charge shall however be related to the financial year as indicated in its Order dated 20-03-2004.

 

42)      Access to records:

 

The Petitioner-Association alleged that the data / records sought from the Commission were not made available.  The allegation is factually wrong. The Petitioner's representative,  Sri. D.G.N.Kumar, was provided access to all the related records on 10-05-2004 and the copies of documents sought by him were delivered vide Commission’s letter dated 20-05-2004.

 

43)      Conclusion:

 

The petitions filed by the Petitioners for review of the Order dated 20.3.2004 do not indicate any error apparent on the face of the record or         non-consideration of any relevant material or document or otherwise  sufficient reason for review of the Order dated 20-03-2004 passed by the Commission except for additional information furnished on capital subsidy by MNES leading to re-determination of the capital cost. The Commission in the order dated 20-03-2004 provided for special treatment of the NCE projects in its endeavour to promote non-conventional energy development. However, such development cannot be open-ended in the sense that the tariff allowed becomes very high. In order for the Commission to direct APTRANSCO to purchase the power generated from such projects, it is necessary that the tariff is also affordable.  There is an optimum level beyond which the project developers cannot expect the Commission to allow the tariff as the direct impact of higher tariff will be unduly burdening the consumers in general to pay higher tariff for the electricity. The Commission has to strike a balance between the interest of promoting non-conventional energy and the interest of the consumers to have an economical tariff for the electricity.

 

Except for the clarifications provided above on the settlement period and the year of operation, re-determination of capital cost due to additional information on capital subsidy by MNES now being made available, and revision of incentive beyond threshold PLF, the Commission hereby rejects the petitions filed by the petitioners.

 

This order is signed by Andhra Pradesh Electricity Regulatory Commission on 7th day of July, 2004.

 

                                                            Sd/-                                                                   Sd/-

SURINDER PAL                                       K.SREERAMA MURTHY

                                                    (MEMBER)                                                (ACTING CHAIRMAN)

 

 

 

 

CERTIFIED COPY