ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION

Hyderabad.

 

Dated  11-08-2004

 

Present

K. Sreerama Murthy, Member

Surinder Pal, Member

 

R.P.No. 1 / 2004

R.P.No. 2 / 2004

  R.P.No. 11 / 2004

In RP. No. 84 / 2004 in OP No. 1075 / 2000

 

Between

 

1.Transmission Corporation of Andhra Pradesh Limited RP.No. 1/2004

2. M. Venugopala Rao, Correspondent, Prajashakthi        RP.No. 2/2004

3. Peoples Monitoring Group on Electricity Regulation    RP.No. 11/2004         

…. Petitioners

AND

Non-Conventional Energy Developers’ of AP                                      ….Respondent

O R D E R

 

1.                  Andhra Pradesh Electricity Regulatory Commission (hereinafter the Commission) initiated suo-motu proceedings for determination of tariff applicable to Non-Conventional Energy (NCE) projects of Andhra Pradesh to take effect from 01-04-2004 onwards.

 

2.         The Commission passed the order dated 20-03-2004 in R.P.No.84 / 2003 in O.P. No. 1075/2000, wherein the Commission determined the tariff, terms and conditions for purchase of energy by Transmission Corporation of Andhra Pradesh (hereinafter APTRANSCO) from the following categories of              NCE based power projects :

i)                    Biomass-based energy and  Biomass-based co-generation plants

ii)                  Bagasse-based Co-generation plants

iii)                Mini-Hydel power projects

iv)                Wind electricity generators

v)                  Industrial Waste-based energy projects

vi)                Municipal Waste-based energy projects.

 

3.         While deciding the purchase price and other terms in respect of different categories of NCE based projects, the Commission adopted a “Cost plus” approach and allowed a fair amount of return instead of the adhoc price earlier fixed in OP No 1075 / 2000 based on the guidelines of Ministry of        Non-Conventional Energy Sources (MNES).  The Commission computed the tariffs based on realistic costs that NCE developers would incur from year to year based on normative parameters, while APTRANSCO adopted levelised tariff methodology to compute tariffs for NCE projects.  The tariffs based on levelisation proposed by APTRANSCO will not provide realistic tariff compensation.  The Commission therefore adopted the “Cost plus” approach.

                        Subsequent to the issue of Commission’s order dated 20-03-2004, APTRANSCO filed a review petition (RP No 1 / 2004) seeking the following:

a)                 ROE to be at 14% instead of 16% allowed by the Commission.

b)                 PLF for bagasse-based plants to be 62% against 55% adopted by the Commission.

c)                  Correction to the provision of depreciation allowance.

d)                 Incentive payment to be based on annual basis.  

e)                 Downward revision of incentive rate.

f)                    Providing for certainty of continuation of operation of the plants after their loans are repaid. 

Further to the review petition, APTRANSCO sought Commission’s directions on the following:

g)                 Adjudication of grievances by the Commission.

h)                  Non-allowance of incentive for generation based on fossil fuels.

i)                    Filing of annual reports and affidavits on usage of coal in generation.

j)                    Exemption from providing generation terminal meters for biomass and hydel projects.

k)                  Directions in respect of year of operation.

4.         Sri. M. Venugopala Rao, Correspondent, Prajashakthi, and Peoples Monitoring Group on Electricity Regulation, have also filed review petitions, (R.P No 2 and R.P No 11), seeking downward revision of the tariffs on following grounds:

a)                 The capital costs allowed are high and should be determined after studying the market trends through an independent agency. Peoples Monitoring Group has suggested that the capital cost be decided based on the specific project instead of adopting benchmark capital cost.

b)                 The Plant Load Factors (PLFs) adopted by the Commission are low and provide super profits to the developers.

c)                  The Return On Equity (ROE) shall be only 14% and not 16%.  Peoples Monitoring Group have stated that the Commission having recognised ROE of 12.5% in case of Krishna Godavari Power Utilities, allowing 16% of ROE is illogical.

d)                 The fuel costs allowed, especially for biomass, are high.

e)                 The Municipal waste to energy and Wind electricity generators must be allowed third party sales in view of the high costs.

 

5.         All these three petitioners have sought for downward revision of tariff fixed by the Commission in its orders dated 20-03-2004 mainly on common grounds, and, therefore, all these three petitions are being disposed of by this common order. 

 

6.         The following developers of NCE projects, who are aggrieved by some of the provisions of the Commission’s Order dated 20-03-2004, filed writ petitions in the Hon’ble High Court of Andhra Pradesh and following the directions of the Hon’ble High Court, filed petitions before the Commission for review of the Commission’s Order dated 20-03-2004 seeking upward revision of the tariffs : 

i)                    M/s. Biomass Energy Developers’ Association

ii)                  M/s. Small Hydro Power Developers’ Association

iii)                M/s. Sree Rayalaseema Hi-Strength Hypo Ltd (Bio-mass Developer)

iv)                M/s. Vensa Biotek Limited

v)                  M/s. Active Power Corporation

vi)                M/s. South India Sugar Mills Association

vii)              M/s. Raus Power Pvt. Ltd

viii)            M/s. Sai Renewable Power Pvt. Ltd.

 

The Commission conducted hearing on 8th, 10th and 11th of June 2004 and invited developers and petitioners, to present their case on the review petitions filed before the Commission.  M/s NEDCAP had also been directed to present their views in the hearing as intervenor.

 

After going through the submissions of various parties, the Commission passed the following separate orders on the review petitions filed by the developers : 

RP Nos.

Petitioners

Date of Commission’s Order

 

3 / 2004

 

 

4 / 2004

M/s Biomass Energy Developers Association

 

M/s Sree Rayalaseema Hi-Strength Hypo Limited

 

05-07-2004

5 / 2004

 

 

12 /2004

M/s Small Hydro Power Developers Association      

 

M/s Active Power Corporation Pvt., Ltd.

 

07-07-2004

7/ 2004

 

9 / 2004

 

13/ 2004

M/s Sai Renewable Power Pvt., Ltd.

 

M/s Vensa Biotek Pvt., Ltd.

 

M/s Raus Power Private Limited

 

10-07-2004

8 /2004

M/s South India Sugar Mills Association

 

10-07-2004

The issues raised by the petitioners herein, in RP.No.1/2004, 2/2004 and 11/2004 for review of the Order dated 20-03-2004 and the decision of the Commission thereon are as under:

 

7.         Issue: Return on equity (ROE):

APTRANSCO submitted that it had proposed ROE of 14% and 11% for the existing and the new projects respectively in its tariff proposal for NCE projects due to declining rates of interest and market trends. The Commission however, APTRANSCO submitted, had allowed ROE at 16% leading to higher tariffs.  APTRANSCO in its review petition submitted the following:

a)                 NCE generators are must-buy for APTRANSCO as per the directions of the Commission.

b)                 Payments are made regularly without delay / default.

c)                  The Central Electricity Regulatory Commission (hereinafter CERC) in its tariff regulations for Central generating stations has fixed ROE at 14%.

d)                 The task force  (N.K Singh Committee) set up by Ministry of Power Government of India (GOI) also proposed ROE of 14%.

e)                 The Commission earlier approved ROE of 12.5% in case of  M/s Krishna Godavari Power Utilities’ coal-based power plant.

f)                    Karnataka Electricity Regulatory Commission has fixed ROE of 12% for bagasse-based plants and Mini Hydel power plants.

 

Considering the risk-free operations of NCE projects, APTRANSCO submitted, the Commission may review this rate and determine appropriate rate based on the submissions made above.

 

Sri. M. Venugopala Rao, one of the other petitioners submitted that 16% ROE allowed by the Commission is high as 16% ROE was indicated by GOI in early 1990s when the rates of interest ranged between 16% and 20%.  The task force headed by Sri. N.K Singh also recommended 14% ROE.  The petitioner, further referring to the Krishna Godavari Power Utilities’ coal-based project where the Commission allowed ROE at 12.5%, pleaded that 16% ROE allowed by the Commission is too high and be reviewed.  He also submitted that ROE can be fixed at 11%.  M/s. Peoples Monitoring Group expressing similar views, sought reduction in ROE.

 

Commission’s Analysis:

The Commission in its Order dated 20-03-2004 specifically stated that it recognized that NCE projects are environmentally benign and help conserve fossil fuels.  Further, they are fraught with uncertainties and risks.  Hence these NCE projects cannot be equated with conventional projects.  In order to provide encouragement to these projects in the overall national interest in general and keeping in view the responsibility of the Commission to promote renewable / co-generation energy under section 86 (1) (e) of the Electricity Act 2003, the Commission allowed ROE of 16%.  The contentions of the petitioners do not alter these basic premises and accordingly do not provide legal basis for review of the Commission’s Order dated 20-03-2004 on this ground. 

 

8.         Issue: Plant Load Factor (PLF):

The petitioner, Sri. M. Venugopala Rao, submitted that the PLFs adopted by the Commission in respect of mini-hydel and bagasse-based                         co-generation plants are very low.  M/s Peoples Monitoring Group on Electricity Regulation too submitted that the PLFs adopted by the Commission are low and cast huge burden on the consumers.  M/s NEDCAP requested for adoption of 50% PLF in case of bagasse-based power projects and 35% in case of mini-hydel power projects.  APTRANSCO, while accepting the PLFs adopted by the Commission except in case of bagasse-based co-generation plants, submitted that 62% PLF ought to be adopted in case of these plants taking into consideration the plant operation for 150 days during crushing season and 100 days during non-crushing season.

 

Commission’s analysis:

The Commission has adopted the PLFs based on the historical data furnished by APTRANSCO and NEDCAP.  While considering the above the Commission discarded the extremes where a plant in a particular category achieved very high / very low PLF as consideration of such data tends to distort the process of evaluation.

 

In respect of bagasse-based co-generation plants, the Commission considered the operation of co-generation plants for 130 days during crushing season based on 10 years’ average as submitted by South India Sugar Mills Association and 100 days during non-crushing season.  The PLF of 55% adopted by the Commission is therefore based on valid data and needs no consideration for review.  There are therefore, no grounds for review of the order in respect of the above.

 

9.         Issue: Capital cost:

The petitioner, Sri. M. Venugopala Rao, contended that the capital costs allowed for NCE projects are high and need to be determined based on the study of market trends through an independent agency.  M/s Peoples Monitoring Group submitted that the capital cost be fixed for each project instead of adopting normative benchmark parameters.

 

Commission’s Analysis:

The Commission adopted benchmark parameters for the capital cost, as determination of capital cost for NCE projects on a case-to-case basis would be impractical in the absence of a bidding process.  Moreover, these projects have been commissioned at different points of time under difference market situations.  While arriving at the costs for different NCE projects, the Commission placed reliance on the Detailed Project Reports, and the data provided by APTRANSCO and NEDCAP, to arrive at the benchmark capital cost.   The Commission therefore is of the opinion that there is no error apparent on the face of it and the contentions of the petitioners have no grounds.

 

However, where it was brought to the notice of the Commission in respect of mini-hydel plants that the capital subsidy adopted by the Commission was at variance to the subsidy actually provided by MNES, the Commission has reviewed and revised the capital cost accordingly.  This has been provided in paragraph 30 of the Order dated 07-07-2004 passed in the review petitions No. 5 / 2004 and 12 / 2004.

 

 

10.       Issue: Rate of Incentive:

APTRANSCO in its review petition submitted two alternate methodologies for fixing the incentives as detailed below:

a)                 Incentive equivalent to savings in transmission costs on account of “localised supply”.

b)                 Incentive equivalent to 50% of O & M cost per unit.

Based on the above methodology, APTRANSCO proposed incentive of            10 paise per unit.

The petitioner, Sri. M.Venugopala Rao, submitted that the incentive shall be as per CERC guidelines. 

 

Commission’s Analysis:

The Commission in its Order dated 20-03-2004 provided incentive of          21.5 paise per unit for the energy delivered beyond the threshold PLF based on the guidelines of CERC for coal-fired boilers.  The Commission having taken note of CERC notification dated 26-03-2004 issued subsequent to that Order of the Commission, has applied the same in its orders issued on review petitions filed by the developers.  For the NCE projects, the Commission is of the view that the incentive should be at the level allowed for conventional projects.  Therefore, there is no justifiable ground for review of its Order dated 20-03-2004 on this count.

 

11.       Issue: Incentive to be on annual basis:

APTRANSCO as well as other developers requested that the PLF should be worked on annual basis and incentive be allowed accordingly, construing that the Commission had indicated in its Order dated 20-03-2004 that PLF shall be computed on the basis of billing month.

 

Commission’s Analysis:

It was not the intention of the Commission that PLF and incentives should be worked on a monthly basis.  The Commission, therefore, while issuing orders on the review petitions filed by the NCE developers clarified that the PLF shall be computed on annual basis, and re-iterates that clarification herein too.

 

12.       Issue: Continuation of the operation of the plants after loans are repaid:

APTRANSCO in its review petition submitted that the Commission may issue necessary regulations so that the plants continue to operate and supply electricity to APTRANSCO even after the loans are repaid.

 

Commission’s Analysis:

The Power Purchase Agreements (PPAs) provide that the duration of the PPA is 20 years from the date of commercial operation.  Even when the power purchase price is subject to revision by the Commission on completion of 10 years after date of commissioning, the developers would still receive O & M charges, variable charges and residual depreciation representing 20% of the capital cost besides ROE.  Therefore, the apprehension of the APTRANSCO that the developers will not operate the plants after the loans are repaid is misplaced and no direction is required to that effect, nor can it be effective, if given.

 

13.       Issue : Correction to the provision of depreciation:

APTRANSCO submitted that the Commission in its Order has stated that APTRANSCO has assumed a depreciation rate of 7.84% for biomass and Bagasse-based plants and of 6.7% for Mini-Hydel plants, whereas it (APTRANSCO) had instead considered a depreciation rate of 7% p.a. for providing repayment of loan over a 10-year period.   It requested the Commission to consider the depreciation rate of 7% as adopted in its tariff proposals.

 

Commission’s Analysis:

The Commission did not fix the rate of depreciation on the basis of APTRANSCO’s submissions alone and observed in its Order dated                   20-03-2004 as follows:

 

“The depreciation rate of 7.84% is as per the rates approved for Independent Power Producers (IPPs) so that this amount can be used for repayment of loans.   The Commission while approving uniform rate of depreciation both for existing as well as new projects, allows depreciation at the rate of 7.84% per annum from the date of commissioning till the depreciation allowed accumulates to 70% of the project cost. The balance depreciation of 20% of the project cost will be allowed every year equally for the balance period of the PPA so that the total depreciation allowed for the project does not exceed 90% of the project cost”.

Hence there are no grounds to review this component

 

 

 

14.       Issue : Year of Operation:

APTRANSCO sought for a direction from the Commission regarding year of operation. Some of the developers stated that the year of operation shall be reckoned from commercial operation date and not on the basis of financial year. 

 

Commission’s Analysis:

The Commission hereby clarifies that the year of operation shall be reckoned from the date of commercial operation to arrive at the appropriate fixed charges for each year.  The variable charge shall however be as indicated in the Order based on the corresponding financial year.

 

15.       Issue : Exemption from installation of generator terminal meters for biomass and hydel projects:

APTRANSCO sought exemption from installing meters at the generator terminals in respect of biomass and hydel projects.

 

Commission’s Analysis:

The Commission in its Order dated 20-03-2004 (paragraph 81) directed that where the developers are having captive consumption and supply energy to APTRANSCO after meeting their internal consumption, APTRANSCO should make arrangements for meter reading at generator terminals for proper implementation of the two-tier tariff.

 

In this connection, the Commission hereby clarifies that where there is no captive consumption the energy recorded at the interface point may be grossed up by adopting normative auxiliary consumption to arrive at the PLF at generator terminals.  However, where captive consumption is involved, metering at generator terminals shall be provided, to ascertain the actual PLF at the generator terminals. With this clarification, no further review of the Commission’s Order is called for.

 

16.       Issue :  Fuel Cost

The petitioner, M/s. Peoples Monitoring Group, has submitted that the fuel cost allowed, especially for biomass projects is on the high side. 

 

Commission’s Analysis:

The Commission deputed a team of its officers to some biomass and bagasse-based projects to ascertain the type of fuels used and the mix and to ascertain the price obtaining for the fuels. The rates of fuel for biomass and bagasse have been fixed by the Commission, based on the report by the study team and various other facts and data, as detailed in paragraph 54 of the Commission Order dated 20-03-2004.  No other data has been produced contradicting it.  Hence no review is required.

 

17.       Issue :  Non-allowance of incentive for generation based on fossil fuels

APTRANSCO submitted that no incentive should be allowed for generation based on fossil fuels as it defeats the very purpose of generation of power from non-conventional energy sources. 

 

Commission’s Analysis:

The Commission is of the view that when MNES has permitted usage of up to 30% conventional fuels, the developers cannot be barred from the use of fossil fuels to the extent permitted.  Hence, no grounds for review.

 

18.       Issue : Developers to submit annual reports and affidavits for usage coal

APTRANSCO submitted that the Commission may issue directions that the developers should submit annual reports and affidavits about the usage of coal. 

 

Commission’s Analysis:

The Commission is of the view that if APTRANSCO considers it necessary, it may itself seek such reports / data from the developers.  No such directions are required from the Commission.  If the developers refuse or fail to give the reports, APTRANSCO may then file an application.  The Commission will consider the application on merits and pass appropriate orders.

 

19.       Issue : Adjudication of grievances by the Commission

The Commission in its Order dated 20-03-2004 directed that if any developer is aggrieved by any of the provisions of that Order, he may approach APTRANSCO with sufficient data for initial examination and forwarding to the Commission. APTRANSCO, in its affidavit, requested that the Commission may adjudicate upon the matter as provided in the Andhra Pradesh Electricity Reform Act, 1998. Sri. M. Venugopala Rao submitted that this provision should be withdrawn as it leads to the distortion of judicial process, the Commission being a quasi-judicial authority.

 

Commission’s Analysis:

The issue involves a lot of technical data, required to be verified initially with records available with the Licensee before the Commission takes up matter for adjudication.  APTRANSCO itself admitted that the issues involved are technical and do not permit easy and simple adjudication. The suggestion of APTRANSCO and apprehensions of other petitioners are therefore not appropriate.

 

20.       Issue: Third-party sales:

Sri. M. Venugopala Rao submitted that the developers of Wind energy and Municipal waste to energy must be allowed to sell power to third parties in view of the high cost.

 

Commission’s Analysis:

The developers have entered into long-term agreements (20 years) with APTRANSCO.

In view of the Commission’s analysis above, on the various submissions made by the petitioners, there are no grounds to review the Order of the Commission dated 20-03-2004.

 

The petitions are accordingly dismissed.

 

This order is signed by Andhra Pradesh Electricity Regulatory Commission on 11th  August, 2004.

 

 

Sd/-                                                    Sd/-

SURINDER PAL                     K. SREERAMA MURTHY

(MEMBER)                                      (MEMBER)

 

 

CERTIFIED COPY