ANDHRA
PRADESH ELECTRICITY REGULATORY COMMISSION
Hyderabad
Sri.
K.Sreerama Murthy, Member
Sri Surinder Pal, Member
O. P. No. 8 of 2005
and
11-5-423/1/A, 1st Floor,
Singareni Colleries Bhavan, Hyderabad.
Upstairs, Hero Honda Showroom, Renigunta
Road, Tirupati.
1-7-668, Postal Colony, Hanumakonda,
Warangal.
Sai Shakti, Opp: Saraswathi Park, Daba
Gardens, Visakhaptnam.
(Respondents No.2 to 5
impleaded as per orders dated 27-07-2005 of the Commission in I.A No. 36 of 2005)
………
Respondents
This petition coming on for hearing on 17-08-2005 and
23-09-2005 in the presence of Sri C.Kodanda Ram, Advocate, for the petitioner
and Sri N. Jayasurya, Advocate, for the respondents and having stood over for
consideration to this day, the Commission delivered the following:
O R D E R
1. This petition is about the mode of
calculation of Plant Load Factor (PLF) of the bagasse-based cogeneration unit
of the petitioner. The contention of the
petitioner is that the PLF has to be calculated on annual basis, even according
to the order of the Commission dated 20.03.2004 in R.P. No.84 of 2003 in O.P.
No.1075/2000 and subsequent order dated 11-08-2004 in R.P. Nos.1, 2 and 11 of
2004. The petitioner has, therefore,
questioned the computation of PLF by the respondents on monthly basis (billing
period).
2. All the respondents filed counters and
took up a preliminary objection with regard to maintainability of the petition
in view of the pendency of appeal filed by South Indian Sugar Mills Association
(SISMA), of which the petitioner is a member, challenging the order of the
Commission dated 20.03.2004 referred to above, on several grounds, including
the quantum of PLF fixed by the Commission for arriving at the tariff fixed for
sale of per unit of electrical energy (for brief, ‘the Tariff’) to the licensee. It is further
submitted by the learned counsel for the respondents that the appeals filed by SISMA
and others are posted for hearing finally on 19-10-2005 before the Appellate
Tribunal for Electricity.
3. The Commission heard arguments on the
preliminary objection raised by the respondents.
4. The respondents contended that in the
writ petition filed before the High Court, and later in the appeal filed before
the Appellate Tribunal for Electricity consequent upon the constitution of the
Tribunal, challenging the correctness of
the Tariff, including the quantum of PLF
fixed by the Commission, is also pending decision. Therefore, it is contended that this petition
before the Commission is not maintainable.
5.
The learned
counsel for the petitioner on the other hand stated that the relief sought by
the petitioner in this petition is altogether different from the issues
involved in the appeal pending consideration before the Appellate Tribunal.
6. The present petition though filed for
directions to respondents to implement the aforementioned orders as passed by
this Commission in R.P.No.84 of 2003 in O.P.No.1075/2000 and R.P.Nos.1, 2 and
11, is in essence a petition seeking adjudication of a dispute with the
respondents.
7. In the Appeal No. 21 of 2005 filed
before the Appellate Tribunal by the SISMA (the petitioner is one of its
members) challenging the order dated 20.03.2004 of the Commission mentioned
above including the orders on Review Petitions thereon, impleading this
Commission in addition to the respondents herein, the appellant in ‘Detail of
Appeal’ has specifically contended that the calculation should be on annual
basis. Relevant paragraphs are as extracted below:
“ 5.50 The respondent Commission ought to have seen,
that should it desire to adopt two part tariff system in the case of bagasse
based co-generation units, having seasonal nature of operations, the capacity
on 55% PLF should be calculated on annualized basis and not on settlement
period (billing period) basis, apart from directing APTRANSCO / DISCOMS to
purchase power and pay both fixed and variable costs till such time the
aggregate units in a financial year reach the threshold level of PLF.
5.51
The respondent Commission ought to have seen that in
case the first option i.e. single part tariff is not acceptable, the respondent
commission ought to direct APTRANSCO / DISCOMS to pay both fixed costs and
variable costs upto 100% capacity utilization during any month subject to
overall annualized threshold limit of PLF.”
8. When an appeal is pending before the Appellate Tribunal for Electricity for consideration of the validity and enforcement of the Order dated 20.03.2004 of the Commission involving all incidental aspects like percentage of PLF, its calculation on annual basis etc, taking up of adjudication proceedings by the Commission in respect of PLF would be tantamount to taking up a matter which is sub-judice. Therefore, the objection raised by the respondents is well taken and hence further proceedings in the matter are stayed till the disposal of appeal filed by SISMA by the Appellate Tribunal for Electricity.
The order is corrected and signed on this 1st day of
October, 2005
Sd/- Sd/- Sd/-
Surinder
Pal K.Sreerama Murthy K.Swaminathan
MEMBER MEMBER
CHAIRMAN