ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION

HYDERABAD

 

 

Dated: 25.05.2007

 

Present

Sri K. Swaminathan, Chairman

Sri Surinder Pal, Member

Sri. R.Radha Kishen, Member

 

 

 O. P. No. 21 of 2004

 

Between

 

M/s GMR Technologies & Industries Limited

having its Corporate Office at

6-3-866 / 1 / G2, Greenlands,

Begumpet, Hyderabad.                    

Represented by its Managing Director.                                                                                                                                              Petitioner

 

and

 

1.         Chairman and Managing Director,

Transmission Corporation of Andhra Pradesh Limited              

Vidhyut Soudha, Khairatabad, Hyderabad                    

 

2.         Joint Managing Director (HRD, Comml & IT),

Transmission Corporation of Andhra Pradesh Limited              

Vidhyut Soudha, Khairatabad, Hyderabad                    

 

3.         Chief Engineer, (Comml & IT),

Transmission Corporation of Andhra Pradesh Limited              

Vidhyut Soudha, Khairatabad, Hyderabad                    

 

4.         Eastern Power Distribution Company of Andhra Pradesh Limited.

P & T Colony, Seethammadhara,

Visakhapatnam – 500 013.                                                                                                                                                   Respondents

 

(R-1 is added being a party to the appeal before Hon’ble ATE)

(R-4 added in view of Third Transfer Scheme and it being a party

to the appeal before Hon’ble ATE)

 

       

 

This petition on being remanded from the Hon’ble Appellate Tribunal for Electricity (for short, ‘ATE’) coming up for hearing on 05.05.2007, in the presence of Sri.C.Kodanda Ram, Advocate, for the petitioner and Sri.P.Shiva Rao, Advocate, for the respondents, and having stood over for consideration to this day, the Commission delivered the following:

 

O R D E R

 

            Originally the petition was filed on 18.05.2004 by the petitioner herein against respondent Nos. 2 and 3.  The Commission after carefully considering the said petition disposed of the same by its order dated 17.07.2004.

 

2.         The petitioner challenged the said order of the Commission before the Hon’ble Appellate Tribunal for Electricity (for short, ‘the ATE’) in Appeal No.203 of 2005 and the Hon’ble ATE by its order dated 07.03.2007 allowed the appeal in part with certain directions as mentioned below and dismissed the same with regard to other reliefs:

 

“In view of the aforesaid discussion and our observations on the various issues, the appeal is allowed and the order of the Andhra Pradesh Electricity Regulatory Commission dated 17.07.2004 in O.P. No. 21 of 2004 is set aside. The matter is remanded to the Commission with the direction that within eight weeks of the receipt of this judgment, it will re-determine the ‘demand’ of the appellant in accordance with the PPA and authorize adjustment of the amount refundable, if any, against the dues in future”. (emphasis supplied)

 

 

3.         In view of the directions of the ATE, notices were given not only to petitioner and respondent Nos. 2 and 3, but also to respondent Nos. 1 and  4 as arrayed in the appeal before it. 

 

4.         As the matter is remanded to the Commission with a specific direction to re-determine the ‘demand’ of the petitioner in accordance with the Power Purchase Agreement (for short,  ‘PPA’) and authorize adjustment of the amount refundable, if any, against the dues in future, as mentioned above, the scope of present proceedings before the Commission is limited to the extent envisaged in the directions of the ATE. It is not therefore, necessary to delve into the rival pleadings of the parties herein in the original proceedings initiated before the Commission. 

 

5.         After receipt of notices, parties entered appearance.  On the date of hearing, a petition u/s 86 (1) (f) of the Electricity Act, 2003 (for short, ‘the Act’) was filed by the petitioner stating that in terms of the PPA and particulars of the energy consumed by it, it made monthly statement of the consumption vis-à-vis the demand and the consumption charges payable,  and accordingly submitted an annexure containing such particulars along with the petition filed on that day.

 

6.         On the said date of hearing,  written additional submissions were filed by the respondents, inter-alia stating that;

 

a)         the respondents have preferred an appeal before the Hon’ble Supreme Court of India u/s 125 of the Act;

 

b)         section 21 (4) of the A.P. Electricity Reform Act, 1998 (for short, ‘Reform Act’) mandates that a licensee can purchase power from generating companies under agreements only with the consent of the Commission and Section 21 (5) thereof stipulates that any agreement without consent of the Commission is void. Thus all PPA entered into by APTRANSCO, invariably required consent of the Commission u/s 21 (4) of the Reform Act;

 

c)         the Commission approved the PPA formats for Non-conventional Energy (for short, ‘NCE’) projects with captive use in premises and without captive use in premises;

 

d)         it is respectfully submitted that all PPAs entered into by a licensee will fall in one of the above categories and no differentiation is shown in adopting the above clauses for similarly- placed NCE projects;

 

e)         the petitioner sought signing of the PPA with APTRANSCO during July, 2001 and undertook that it is agreeable to the terms and conditions of PPA as may be finalised by APTRANSCO and the Commission;

 

f)          there are about 18 NCE projects having captive use in premises and entered into PPAs with a provision to bill the imported energy and maximum demand as per actual meter recordings. After obtaining confirmation from Non-conventional Energy Development Corporation of AP (for short, ‘NEDCAP’), the nodal agency, and the petitioner about captive use in project premises, APTRANSCO billed the actual recorded MD in lieu of notional MD;

 

g)         the Article 9.2 of the PPA clearly shows that “the amendments to the Agreement as per the respective orders of APERC from time to time shall be carried out”. The petitioner is also forgetting the Article 7 of the PPA, which provides that “any and all incentives / conditions envisaged in the Articles of this Agreement are subject to modifications from time to time as per the directions of APERC, Government of Andhra Pradesh and APTRANSCO”; and

 

h)                  The actual recorded particulars and billing details of the petitioner’s project are submitted below:

Month

Units drawn

(Kwh)

Charges per unit

(Rs)

Energy charges

(Rs)

MD drawn (KVA)

Charges per KVA

(Rs)

Demand charges

(Rs)

Total charges

(Rs)

February

2002

1000

3.76

3760

1800

170

306000

611995*

July

2003

2000

3.60

7200

1400

195

273000

280470

November

2003

2000

3.60

7200

1110

195

216450

328043*

April

2004

1000

3.60

3600

1200

195

234000

469527*

December

2004

1000

3.50

3500

1700

195

331500

335135

 

(*)        The project drawn power at power factor at less than 0.9 (i.e., at 0.5, 0.5 and 0.67 during February 2002, November 2003 and April 2004 respectively). As such, Low Power Factor Surcharge as per HT tariff regulations was charged as in case of all NCE projects.

 

7.         Heard arguments of the parties concerned.

 

8.         The counsel for the petitioner submitted that in view of Commission’s order dated 17.07.2004 having been set aside and the specific direction of ATE to it to re-determine the ‘demand’ of the petitioner in accordance with the PPA, what is now left for consideration by the Commission is the arithmetic calculation of the amounts withheld. The statement filed this day by the petitioner together with the petition referred to above, may be verified and suitable directions may be issued. 

 

9.         The counsel for respondents submitted that       

 

 

a)         The respondents have already preferred an appeal against the order passed by the ATE before the Hon’ble Supreme Court and since the challenge also includes the issue of remanding the matter, it is requested that the matter may be adjourned for some more time and orders of the Hon’ble Supreme Court awaited. By doing so, no prejudice will be caused to the petitioner as any exercise and disposal of the matter at this stage would go in vain, if the Supreme Court finds that the remand of the matter by ATE is not correct.

 

b)         Re-determination of the demand and ordering payment of the amount requires fresh examination of the subject matter in the light of the observations made by the ATE, but it is not simple arithmetic calculation of the amount alone as is sought to be projected by the petitioner.

 

c)         The ATE did not comment on the PPA. It is not correct to state that there is no concluded PPA. Any directions given by the Commission will form part of the PPA and the same stands amended to that extent.  Whatever it might be, re-determination of the demand of the petitioner has to be done in the light of the letter of the Commission dated 02.01.2002 by which certain directions relating to the modifications, which are also applicable to the PPA of the petitioner dated 14.08.2001, were conveyed by the Commission.

 

 

10.       After conclusion of arguments, the Commission directed the respondents to file a statement either accepting or disputing the figures, filed by the petitioner,  item-wise,  within one week from the date of hearing. 

 

11.       Instead of accepting or disputing the figures, item-wise, as filed by the petitioner, on 11.05.2007, ‘a statement showing import bill of M/s GMR Industries Limited’ from the billing month of August, 2001 to March, 2007 (in tabular form containing 3 pages) was filed on behalf of the respondents.  At the end thereof,  it is mentioned that “the excess amount claimed by the petitioner” is Rs.58,017.   

 

12.       As the said statement submitted by the respondents appeared to be exhaustive, containing more detailed break-up of calculations vis-à-vis the information furnished by the petitioner on 05.05.2007, a notice was issued to the petitioner on 16.05.2007 directing it to verify the details submitted by the respondents and to file a statement, either accepting or disputing the different figures in the statement submitted on behalf of the respondents on 11.05.2007 as stated above.

 

13.       In pursuance of the notice issued by the Commission as stated above, a petition was filed on behalf of the petitioner accompanied by a verified affidavit stating that the petitioner accepts the calculations given by the respondents and further requesting  the Commission to pass appropriate orders in the interest of justice.

 

14.       The point that arise for consideration of the Commission is :

“what would be the demand of the petitioner in accordance with the PPA dated   14.08.2001”.

 

15.       In view of the order of the ATE and specific direction give by it, the limited issue before the Commission is to re-determine the ‘demand’ of the petitioner in accordance with the PPA dated 14.08.2001 and authorise adjustment of the amount refundable, if any, against the dues in future.  Respondents have not placed any material to show that stay of further proceedings before the Commission is granted.  Therefore, the Commission is of the opinion that the direction issued by the ATE is required to be complied with.

 

16.       Perusal of the order dated 07.03.2007 of the ATE in Appeal No. 203 of 2005, makes it abundantly clear that the PPA referred to therein, in paragraph-30 of the said order containing directions to the Commission, is the PPA dated 14.08.2001 and there is no ambiguity with regard to the same. For that reason, there is no force in the contention of the counsel for the respondents that re-determination of demand of the petitioner has to be done in the light of the letter / proceedings of the Commission dated 02.01.2002 and the same is rejected.

 

17.       In order to determine the demand of the petitioner in accordance with the PPA  dt. 14.08.2001 as directed by the ATE , firstly the statement submitted by the petitioner on 05.05.2007 is examined by the Commission.  It is found that the said statement does not contain particulars of demand of the petitioner for various months, as stated in the petition filed by the petitioner on 05.05.2007.  Instead, the petitioner mentioned the amounts charged by APTRANSCO, computed the amount which would have been charged as per clause 2.5 of the PPA and arrived at the differential amount charged in excessive, without however, furnishing the demand.  

 

18.       Even though the respondents did not specifically accept or dispute the figures furnished by the petitioner as stated above, they filed a detailed statement showing imported energy billing of the petitioner, as stated above and it contained calculations of the demand charges as per the PPA as well as those based on recorded MD.  Additionally, the respondents also submitted details of differential amount,  month-wise, working it out to a total Rs. 1,69,52,547 (Rupees one crore, sixty nine lakhs, fifty two thousand,  five hundred and forty seven only). 

 

19.       As per the statement submitted on behalf of the respondents on 11.05.2007, the following is the demand of the petitioner for various months:

 

Demand in KVA as per clause 2.5 of the PPA dated 14.08.2001

 

Billing Month

 

Demand (KVA)

Billing Month

Demand (KVA)

Aug-01

166.67

Jun-04

142.47

Sep-01

133.06

Jul-04

170.83

Oct-01

109.72

Aug-04

211.02

Nov-01

143.82

Sep-04

17.47

Dec-01

58.33

Oct-04

0.00

Jan-02

112.90

Nov-04

5.38

Feb-02

2.69

Dec-04

1.39

Mar-02

58.04

Jan-05

8.06

Apr-02

25.54

Feb-05

6.72

May-02

118.06

Mar-05

20.83

Jun-02

43.01

Apr-05

84.68

Jul-02

112.50

May-05

2.78

Aug-02

162.63

Jun-05

10.75

Sep-02

220.43

Jul-05

94.44

Oct-02

213.89

Aug-05

245.97

Nov-02

32.26

Sep-05

131.72

Dec-02

858.33

Oct-05

45.83

Jan-03

135.75

Nov-05

116.94

Feb-03

8.06

Dec-05

25.00

Mar-03

0.00

Jan-06

32.26

Apr-03

51.08

Feb-06

0.00

May-03

16.67

Mar-06

8.93

Jun-03

63.17

Apr-06

0.00

Jul-03

2.78

May-06

0.00

Aug-03

21.51

Jun-06

1.34

Sep-03

255.38

Jul-06

1.39

Oct-03

20.83

Aug-06

465.05

Nov-03

4.03

Sep-06

240.59

Dec-03

0.00

Oct-06

252.78

Jan-04

22.85

Nov-06

18.82

Feb-04

53.76

Dec-06

19.44

Mar-04

8.62

Jan-07

4.03

Apr-04

2.69

Feb-07

1.34

May-04

11.11

Mar-07

0.00

 

20.       By a petition filed on 21.05.2007, which was accompanied by a verified affidavit as stated supra, the petitioner accepted the calculations given by the respondents.

 

21.       Accordingly, the demand of the petitioner is re-determined as indicated in the paragraph 19 above for different months indicated therein.  With the result, the petition  is allowed with a direction to the respondents to adjust the amount refundable to the petitioner against dues in future, based on the demand as determined in paragraph 19 above, in accordance with the directions of the Hon’ble ATE in Appeal No.203 of 2005 dated 07.03.2007.  

 

The order is corrected and signed on this 25th day of May, 2007.

 

 

Sd/-

Sd/-

Sd/-

(R.RADHA KISHEN)

(SURINDER PAL)

(K.SWAMINATHAN)

MEMBER

MEMBER

CHAIRMAN

 

 

CERTIFIED COPY