ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION

Hyderabad

 

Dated: 10-08-2006

 

Present

 

Sri K. Swaminathan, Chairman

Sri Surinder Pal, Member

Sri. R. Radha Kishen, Member

 

O.P. (SR) No.41 of 2006

 

Between

 

1. Transmission Corporation of Andhra Pradesh

2. Andhra Pradesh Power Co-Ordination Committee

3. Andhra Pradesh Central Power Distribution Company Ltd.                              

4. Andhra Pradesh Southern Power Distribution Company Ltd.                           

5. Andhra Pradesh Northern  Power Distribution Company Ltd.                            

6. Andhra Pradesh Eastern Power Distribution Company Ltd.                                                            Petitioners

 

 

and

 

1. Andhra Pradesh Generation Corporation Ltd

2. Lanco Kondapalli Power Pvt. Ltd, Kondapalli

3. NTPC SinhadriThermal Power Station

4. Spectrum Powrer Generation Ltd

5. GVK Industries Ltd

6. Reliance Energy Ltd

7. Srivathsa Power Projects Ltd                                                                                                    Respondents

 

 

 

            This petition coming on for hearing on 29.07.2006 in the presence of Sri P. Shiva Rao, Advocate, for the petitioners, and having stood over for consideration to this day, the Commission delivered the following:

 
O R D E R

 

 

This petition is filed under Sub-sections (1), (2), (3) and (4) of Section 33 read with Section 86(1)(f) of the Electricity Act, 2003 seeking the following reliefs:

 

(i)                 Directing the respondents to pay the amount of Rs.9.017 crores towards the loss sustained by the first petitioner (hereinafter referred to as ‘APTRANSCO’) for the period from 01.04.2004 to 31.03.2005 by the respective generator as specified in the Annexure-I to the petition.

 

(ii)               Directing the respondents to pay an amount of Rs.14.700 crores towards the loss suffered by the four petitioners, No. 3 to 6 (hereinafter collectively referred to as the ‘DISCOMs’) for the period from 01.04.2005 to 31.03.2006 by the respective Generators as specified in the Annexure-II to the petition.

 

(iii)             To award cost of the petitions.

 

 

2.         The averments made in the petition in brief are as follows:

 

a)         The first petitioner was till June, 2005 engaged in the purchase of energy and transmission of power.  Subsequently in the Third Transfer Scheme, the power purchase function has been taken over by all the four DISCOMs.  However, to have co-ordination in the business of purchase of energy on behalf of all the four DISCOMs, the second petitioner (APPCC) was constituted by G.O.Ms.No.59 dated 07.06.2005.  However as far as maintenance and operation of load dispatch centre is concerned, APTRANSCO is operating the same as per Section 31(2) of the Electricity Act, based on the direction of  Government of Andhra Pradesh (for short GoAP).  Thus all the applicants are required to join together in filing this case against the respondent-generators.

 

b)         The Section 33 of the Electricity Act, 2003, contemplates achieving the maximum economy and efficiency in the operation of power system in the State.  Besides, the Section 33 which deals with operation of State Load Dispatch Centre (SLDC), there is yet another provision, namely, Section 86(1)(b) from where the power of this Commission to regulate the Electricity purchase and procurement process of distribution licensees including the price at which the electricity shall be procured from the generating companies, can be traced.  Thus the Hon’ble Commission has jurisdiction to decide the dispute, which arose due to non-compliance of directions of SLDC by the generating companies, u/s 33(4) as well u/s 86(1)(f) of the Electricity Act, 2003.

 

c)         It is necessary to mention here that the formulation of principles of merit order and monitoring of merit order in the real time, are integral parts of electricity procurement process by the licensees.  The SLDC performs stupendous task of maintaining balance between the merit order and real time constraints, thereby directing the generators time to time either to ramp up or to back down, by taking into consideration the overall economy and efficiency in the operation of power system in the State.  The SLDC alone has the comprehension of State grid and has the real time information of the intra-state network parameters as well as information of several network parameters of Regional grid which need to be monitored in order to maintain the stability of the power system.  Thus it is inevitable on the part of Generation Stations, licensees or any other person using the State grid, to comply with the instructions of SLDC forthwith. 

 

d)         The necessity of compliance of the instructions of SLDC has been outlined u/s 43 scheduling and dispatch of the code of technical interface (Grid Code) 2001 approved by the Hon’ble Commission.  The non-compliance of the instructions of SLDC by the generators amounts to violation of the Grid Code. 

 

e)     The applicants submit that due to non-compliance with instructions of SLDC by the respondent-generators, the other generators having lesser variable cost of generation had to be backed down to operate the power system in a safe and secured manner.  The said indiscipline of respondents resulted in high cost of purchase of power by the licensees only to unjustly burden the end consumers.  The financial burden on the applicants or the end consumers, due to non-compliance of the instructions by the respondents is set out in detail in the Annexures to the petition.  The said default invites penal action also.  The applicants have submitted the details of non-compliance to Hon’ble Commission from time to time every month.

 

f)          The APTRANSCO during 2004-05 suffered financial loss.  In respect of thermal generating stations of APGENCO, the first respondent the backing down instructions of SLDC are based on the revised technical limits, as suggested by APGENCO.  Like-wise after June, 2005, all the four DISCOMs have sustained financial loss, the details of which are submitted in Annexure-2 to the petition.   Although the first applicant is entitled to impose penalty, to have smooth conduct of business, penal action is not resorted to.

 

g)         Cause of action to file the petition arose when the respondents failed to comply with the instructions of backing down and when the respondents failed to make good of the loss suffered by the applicants.

 

h)        In view of the limitations provided in Section 158 of the Electricity Act, 2003, and other provisions in the repealed enactments, though there is arbitration clause in PPA (the Power Purchase Agreements), the same is not enforceable and the Hon’ble Commission has power to adjudicate upon the dispute as per Section 33(4) of the Electricity Act, 2003.  The necessary amount as required under regulations has been paid.

 

3.         Before admitting the petition, notice was ordered to all the petitioners to appear before the Commission on 29.07.2006. On that date, the Commission heard the arguments of Sri. P. Shiva Rao, Advocate for the petitioners, who submitted that --

 

(a)   the prayer    is   for    payment    of    about    9 crores, as   apportioned    in Annexure-I,    towards    the   loss   sustained   by    the   Petitioner No.1   for  the     period   from     01.04.2004   to   31.03.2005   in   view   of    failure  of the    respondents   to   comply     with   the     instructions   of   backing    down      and     for      payment     of     about   Rs.14 crores,  as apportioned in Annexure-II, also towards the loss suffered by the Petitioners No.3 to 6 for the above-mentioned reason.

 

(b)   SLDC is the authority to operate grid and to run the system in an appropriate manner.  For that purpose, the petitioners are required to maintain balance between the merit order and real time constraints.  Consequently, directions were issued to the respondents from time to time to ramp up or backing down the generation.  However, the respondents did not follow the directions issued.  As a result of non-compliance of such directions, the petitioners were forced to purchase power at higher rates.

 

(c)   Two courses of action are open for the petitioners: (i) as per Section 33(5) of the Electricity Act, 2003 if a generating company fails to comply with the direction issued by SLDC in exercise of power of supervision and control for ensuring integrated grid operations, such generator shall be liable to pay penalty of Rs.5 lakhs.  Under this provision of law, SLDC can itself levy fine which is a penal provision, but it will not remedy the loss sustained by the petitioners which is substantial compared to the amount of penalty prescribed under the above mentioned provision of law, and (ii)  as per Section 33(4), if any dispute arises in relation to any directions by SLDC for ensuring integrated grid operations in the State, the petitioners can refer the same to the State Commission for a decision.

 

(d)   As non-compliance of directions issued by the SLDC by the respondents resulted in loss to the petitioners, the matter falls under Section 33(4) of the Electricity Act, 2003, as mentioned above.  Moreover, under Section 86(1)(f) of the Electricity Act, the Commission is empowered to adjudicate upon the dispute between licensee and the generating companies.  Thus this is a fit case for the Commission to entertain the petition and to decide upon the dispute between the parties.

 

(e)   In order to keep the system secure, the petitioners were forced to back down other generators having lesser variable cost of generation during the period mentioned in the petition and for that purpose, incurred additional expenditure.  As the petitioners’ organizations are running on commercial and financial principles, levy of penalty of Rs.5 lakhs by SLDC against the generators will not be sufficient to offset the loss sustained by them. The respondents did not oblige to pay the loss sustained by the petitioners as demanded by them and therefore there exists a dispute.

 

(f)     For all these reasons and for the reasons mentioned in the joint petition filed on behalf of the petitioners, it is prayed that the Commission may adjudicate the matter and grant the reliefs as prayed by the petitioner in the petition.

 

4.         The point that arises for consideration is:

                        whether the petition is maintainable.”

 

5.         For better appreciation of the contentions of the petitioners’ counsel, it is necessary to extract Section 33 of the Electricity Act, 2003 which reads as follows:

 

“Section 33.   Compliance of directions::

(1) The State Load Despatch Centre in a State may give such directions and exercise such supervision and control as may be required for ensuring the integrated grid operations and for achieving the maximum economy and efficiency in the operation of power system in that state.

 

(2) Every licensee, generating company, generating station, sub-station and any other person connected with the operation of the power system shall comply with the directions issued by the State Load Depatch Centre under sub section (1).

 

(3) The State Load Despatch Centre shall comply with the directions of the Regional Load Despatch Centre.

 

(4) If any dispute arises with reference to the quality of electricity or safe, secure and integrated operation of the State grid or in relation to any direction given under sub- section (1), it shall be referred to the State Commission for decision:

 

Provided that pending the decision of the State Commission, the directions of the State Load Despatch Centre shall be complied with by the licensee or generating company.

 

(5) If any licensee, generating company or any other person fails to comply with the directions issued under sub-section(1), he shall be liable to penalty not exceeding rupees five lacs.”

 

6.         The contention of the petitioners’ counsel is that the respondents failed to comply with the instructions given by SLDC with regard to backing down, due to which the petitioners incurred loss.  Violation of the instructions issued by SLDC would come within the purview of the provisions u/s 33 and the Commission has got jurisdiction to entertain the petition under sub-section(4) of Section 33 of the Electricity Act, 2003.

 

7.         It is also the contention of the petitioners’ counsel that the Commission is empowered to decide the matter u/s 86(1)(f) of Electricity Act, 2003.  At this juncture, it is also relevant to extract Section 86(1)(f) of the said Act :

 

“Section 86.   Functions of State Commission:.

(1) The State Commission shall discharge the following functions, namely: -

(a)    xxxxxxxxxxx

(b)    xxxxxxxxxxx

(c)    xxxxxxxxxxx

(d)    xxxxxxxxxxx

(e)    xxxxxxxxxxx

 

(f)      adjudicate upon the disputes between the licensees, and generating companies and to refer any dispute for arbitration; “

 

8.         It is the contention of the petitioners’ counsel that due to non-compliance of the instructions given by SLDC by the respondents, the petitioners incurred loss of 9.017 crores for the period from 01.04.2004 to 31.03.2005 and 14.700 crores for the period from 01.04.2005 to 31.03.2006.

 

9.         It is also the contention of the petitioners’ counsel that even though there is a remedy under sub-section (5) of Section 33 of the Electricity Act, 2003 for the first petitioner operating the SLDC to impose penalty on the generators i.e. the respondents, the remedy has not been invoked to have smooth conduct of business with the respondent-generators.  It is the contention of the petitioners’ counsel that the Commission is empowered to decide the dispute, hence the petition may be taken on file and decide the matter. 

 

            The Commission is not inclined to accept the above contentions of the petitioners’ counsel for the following reasons:-

10.       The intention of Section 33 is to ensure integrated grid operations and for achieving maximum economy and efficiency in the operation of power system in the State and the SLDC is empowered to issue directions and exercise supervision and control over the grid operations for achieving that objective.  If any licensee or generating company  or any other person fails to comply with the directions issued under sub-section (1) of the Section 33, the said person shall be liable to a penalty not exceeding 5 lakhs.  A bare reading of sub-section(4) of Section 33 of the Electricity Act, 2003 would disclose that if any dispute arises with reference to quality of electricity or safe, secure and integrated operation of State grid or in relation to any direction given under sub-section (1), it shall be referred to the State Commission.  The recovery of the loss with regard to grid operations is not covered under Section 33 of the Act ibid. The purpose of Section 33 of the Electricity Act, 2003 is only to see that safe, secure and integrated operation of State grid is achieved.   In the present case, the petitioners have not approached the Commission to direct the concerned respondent-generator to implement the directions given by SLDC to maintain integrated grid operations properly and for achieving maximum economy and efficiency in operation of power system in the State.  Moreover the relief sought for is to direct the respondents to pay certain amounts which are said to represent the quantum of loss sustained by the petitioners herein for the respective periods as mentioned in the petition.  None of the provisions of Section 33 ibid enables the Commission to assume any power whatsoever to direct recovery of loss on account of power purchases by the petitioners at higher cost due to non-compliance of directions of SLDC by any generating company.  The said section only provides for the levy of penalty, by SLDC. Hence the petition filed u/s 33 of the Electricity Act, 2003, for recovery of financial loss, is not maintainable.

 

11.        The other matter for consideration is whether the petitioner is entitled to get the relief sought for, in this petition by invoking the provisions of Section 86(1)(f) of the Electricity Act, 2003.  In order to bring the matter u/s 86(1)(f), there must be a dispute between the licensee or licensees and generating companies.  In this case, the dispute is not between the licensees and generating companies, but between SLDC and generators as the only contention of the petitioners’ counsel is that the respondents have not complied with the directions given by the SLDC with regard to backing down. For that reason, the contention of the petitioners’ counsel  that the Commission can entertain this petition u/s 86(1)(f) the Electricity Act, 2003 is also not tenable.

 

12.       Even though it is true that Petitioner No.1 is operating the SLDC as notified by the State Government, yet it is also a fact that SLDC is not a party before this Commission in this petition.  In any case, the SLDC is neither a licensee nor a generating company.  The provisions of Section 86(1) (f) are therefore not attracted. 

 

13.       On the factual aspects also, the petitioners have not filed the necessary documentation to enable the Commission to come to a possible conclusion that there indeed is a dispute between the parties herein.  The Commission directed the petitioners herein to file the copies of the notices supposed to have been issued to the respondents and also the response of the respondents to such notices, but this was not done.  In the absence of such material, it is not possible to arrive at a conclusion that a dispute exists between the parties.

 

14.       For all the reasons mentioned above, the Commission is of the view that the petitioners have failed to make out a case for the maintainability of the petition.   In the result, the petition is not admitted as not maintainable.

 

The Order is corrected and signed on this 10th day of August, 2006.

 

 

Sd/-

Sd/-

Sd/-

R. Radha Kishen

Surinder Pal

K. Swaminathan

MEMBER

MEMBER

CHAIRMAN

 

 

CERTIFIED COPY