V I D Y U
T O M B U D S M A N
Office of
ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION
5th
Floor, Singareni Bhavan, Red Hills,
Dated: 04-01-2007
Present: S. Surya Prakasa Rao
Ombudsman
Sri.
V.Rajanna
Sri.
V.Kiran Kumar
H.No.18-2,
Husnabad
(P.0) & (M)
Karimnagar
District ……. Appellants
and
1. Assistant
Divisional Engineer / Operation / Husnabad
2. Assistant
Engineer / Distribution / Town / Husnabad
……. Respondents
This
appeal dated NIL (received on 27-09-2006) filed by Sri Sri. V.Kiran
Kumar on behalf of his father Sri. V. Rajanna and himself (hereinafter called the consumer or appellant)
against the order dated 31-08-2006 of the Forum for redressal of grievances of
consumers (hereinafter called the Forum or CGRF), Northern Power Distribution
Company Ltd. (NPDCL), Warangal in C.G.No.7 of 2005 coming up for consideration
before the Ombudsman and having stood over till this day, the Ombudsman issued
the following:
ORDER
2. The facts on record in this case are briefly narrated
herein. The appellant is availing
electricity supply with S.C.No.5256 under LT Category – I for Domestic purpose
and another connection in his father’s name in the same premises with S.C.No.1313
under LT Category II for Non-Domestic purpose.
The meters of these two services were originally fixed inside the
premises in meter boxes, but later shifted by the respondents outside the
premises and fixed on the wall facing the street. The appellant protested for shifting the
meters outside the premises as the street boys are removing fuses frequently
and once the glass of one of the meters was broken, and made representations to
the appellants to re-shift the meters inside the premises. As the respondents have not taken action, the
appellant made a compliant before the Forum on 23-06-2005. The learned Forum in its order dated
31-08-2006, rejected the complaint stating that the shifting of meter was in
line with GTCS and Section 163(3) of the Electricity Act, 2003. Hence the appeal.
3. In his appeal the appellant made the following prime
contentions:
i.
The Forum erred in concluding that the meters are fixed in
accordance with clause 7.1.4 of the GTCS.
ii.
The deposition of respondents before the Forum that the
appellant refused entry to billing staff is false.
iii.
In such case, the respondents could have issued a 24 hour
notice u/s 163(3) of the Act and disconnect supply.
iv.
There is no safety for the meters as they were fixed on the
wall (on the side of street).
v.
The consumer cannot be held responsible for protecting the
meters.
For all the reasons mentioned above, the appellant requested
for relieving the consumers from the responsibility or protecting the meters or
alternatively order shifting of the meters inside the premises.
4. As per clause 8(1)(c) of Regulation No.1 of 2004 of APERC,
the Ombudsman is required, at the first instance, to endeavour to promote a
settlement by mutual agreement between the parties. Accordingly, by notice dated 29-09-2006 the
parties herein were requested to endeavour to arrive at a mutually acceptable
settlement by 28-10-2006, and by another notice dated 20-10-2006, the Ombudsman
informed the parties that, if no settlement could be arrived by the parties
themselves, the Ombudsman himself will mediate as envisaged in clause 11 of
Regulation No.1 of 2004 of APERC.
Accordingly, a meeting was convened at Karimanagar on 04-11-2006, which
was postponed and held on 06-11-2006 at Karimnagar. The respondents attended the meeting but the
appellant did not attend, on the ground that they are not aware of the
postponement.
5. Having discussed the issue in appeal with the respondents
present at the conciliation meeting held on 06-11-2006 at Karimnagar and having
regard to the circumstances of this case, the Ombudsman intended to promote a
settlement by mutual agreement and accordingly proposed a recommendation in
terms of clause 11 of the Regulation No.1 of 2004, as indicated hereunder:
Recommendation of Ombudsman for
settlement by mutual agreement:
1. The
appellants will confirm in writing that they will ensure that in future there
will be no scope for any complaint on not affording or delay in affording the
facility for meter reading by licensees staff or authorized agencies
2. The
Respondents will shift the meters of the two services to the original location
with in the premises of the appellants.
3. In the event of both the parties
agreeing to the proposed settlement and after Ombudsman confirming the
settlement by separate proceedings to be issued in this regard, the respondent
shall shift the meters with in 48 hours of the appellant furnishing the written
assurance mentioned in Para 1 above
6. The above recommendation was served to the parties herein by
notice dated 09-11-2006 with a request to consider the same and furnish the
acceptance within 15 days. In the said
notice, it was also informed that if either of the parties does not accept the
proposed settlement, the Ombudsman will takeup further proceedings in terms of
Regulation No.1 of 2004, and in such case the respondents were required to file
their counter by 02-12-2006 with copy to appellant and the appellant shall file
rejoinder if any by 12-12-2006 with copy to the respondents and that the
Ombudsman will hear the parties on 18-12-2006 in the office of the APERC.
7. The respondents have communicated their acceptance for the
proposed settlement on 06-12-2006 (received on 08-12-2006). The appellant has not furnished any reply to
the notice dated 07-11-2006. Instead, the
appellant sent a rejoinder stated to be in reply to the counter filed by the
respondents, enclosing a photo of a meter and copy of the bill of December
2006, alleging that the bills are not issued correctly. However, the respondents did not file any counter
except acceptance for the recommendation of Ombudsman as stated above.
8. As the appellant did not communicate acceptance for the
proposed settlement, the hearing was held on 18-12-2006 in the office of APERC
at Hyderabad. The respondents have not
attended the hearing (on the premise that they already accepted the proposed
settlement), while the appellant attended the hearing along with an advocate.
9. During the hearing Sri.D.Venkateswara Rao, learned advocate
of the appellant reiterated the contentions raised in the appeal and pleaded
for shifting of meters inside the premises as per clause 7.1.4 of the GTCS.
I asked the advocate to
clarify about the ownership of the platform adjoining the wall and the drain on
the street, and whether it constitutes the premises of consumer or not. The learned advocate desired to make written
submissions on this aspect. Accordingly,
written submissions were filed by the appellant on 30-12-2006.
10. In the written submissions, the appellant stated that the
platform between the drain and wall does not constitute premises and such
constructions require permission from statutory authority i.e., Municipal
Corporation or Gram Panchayat. He quoted
the provisions under sections 46, 299, 401 of Hyderabad Municipal Corporation
Act, 1955 and Section 99 of A.P. Panchayat Raj Act, 1994 in this regard.
11. In the background of the position stated above, the point for
consideration is
(i). Whether the action of the appellant in
shifting the meters is in accordance with the provisions of the General Terms
and Conditions of Supply (GTCS)?
(ii). Whether the consumers are absolved from
the responsibility of protecting the meters fixed outside the premises.
12. The relevant provisions of the GTCS as existing at the time of
the shifting of meter and as on today are extracted hereunder:
Prior to
06-01-2006:
Sub-clause 8 of Annexure under clause 6.2(g) of GTCS of
erstwhile APSEB / APTRANSCO:
“The Meter Box should be fixed at a
height not more than about 5’ feet in the first room/verandah etc., to enable
easy reading of the meter, and located at the entrance of the building”
From
06-01-2006
Clause 7.1.4 of GTCS approved by
APERC:
“7.1.4 - Meters shall be installed according to the convenience of accessibility for reading and inspection at any time.
To enable easy accessibility,
reading and inspections and to enable issue of bills to the consumers promptly,
the Licensee shall have a right to install meters for LT consumers at a
suitable location as the Licensee considers it necessary, including in the
boxes mounted on the poles. This shall be subject to the provisions of the
Regulation of the CEA under section 55 read with Section 177 (2) (c) of the
Electricity Act, 2003.
In respect of meters boxes mounted
on the poles, the authorised officer of the Licensee should inform the consumer
at the time of meter reading so that the consumer has the opportunity to be
present and see the meter reading.
In respect of the meters installed
within the premises of the consumers, the meter box should be fixed at a height
of not more than about 5' in the first room/verandah etc., located at the
entrance of the building to enable easy reading of the meter. In such cases, it shall be the consumer's responsibility
to ensure the safety of the main meter as well as the check meter, if any.”
13. The CEA has since notified the Regulations u/s 55 of the Act
2003, vide Notification dated 17-03-2006 (No.502/70/CEA/DP&D). The relevant provisions of this Regulation is
extracted hereunder:
“Clause 7 - Locations of meters.-
(1) …….
(a) Interface Meters
(i) ……
(ii) ……
(iii) ……
(b) Consumer meters
(i) The consumer meter shall be installed by
the licensee either at consumer premises or outside the consumer premises:
Provided that where the licensee installs
the meter outside the premises of the consumer, then the licensee shall provide
real time display unit at the consumer premises for his information to indicate
the electricity consumed by the consumer:
Provided further that for the
billing purpose, reading of consumer meter and not the display unit shall be
taken into account.
(ii) ……….
14. In view of the provisions cited by the appellant in his
written submissions dated 30-12-2006, it is to be construed that the said
platform between the wall of the premises and the drain along the public road
cannot be considered as the premises of the consumer (whether it was permitted
by the local authority or not) unless it is constructed on the land owned by
the individual. It is not necessary to
go into the aspect of ownership of the land for this purpose. Suffice to say that it does not form a part
of the premises of the consumer as per the written submissions of the
appellant.
15. It may be seen from the provisions of the TCS of APSEB
continued till 05-01-2006, that, the meters are to be erected in the premises
of the consumer as there is no express provision to erect the meters outside
the premises. Though the meters are
fixed to the wall of the building, it cannot be considered as “within’ the
premises. However, in the GTCS approved
by the Hon’ble Commission which came into force w.e.f. 06-01-2006, the licensee
is entitled to locate the meter at a suitable location as the licensee
considers it necessary including in the Boxes mounted on the poles, subject to
the provisions of Regulation of CEA under the Electricity Act, 2003. The CEA has since notified the regulation,
the relevant proviso of which was extracted at para 13 above.
16. Regarding the aspect of safety of the meters, it is to be
stated, that clause 13(3) of CEA Regulation, which is extracted hereunder
governs this aspect:
“13. Safety of meters. -
(1) ………..
(2) ………….
(3) Licensee shall be responsible for the
safety of the consumer meter located outside the premises of the consumer and
the consumer shall be responsible for the safety of the real time display unit
installed by the licensee in consumer premises.
(4) ………..
17. Concluding the above discussion I decide the following award
in this appeal:
(i). The licensee has to shift the meters inside
the premises, or alternately implement the provisions under clause 7.1.4 of
GTCS duly complying with the requirements as per the CEA Regulation referred
above.
(ii). If the meter is installed outside the
premises of the consumer, the consumer cannot be held responsible for the
safety of the meter.
18.
Reasons for delay in award:
There
is a delay of about one week in issue of this order over the
3 months limit specified by the Hon’ble Commission in Regulation No.1 of
2004. The delay is mainly due to the
mediation efforts undertaken by Ombudsman with a view to arrive at a mutually
acceptable settlement, by making a recommendation in terms of clause 11 of the
said Regulation. No one is responsible
for the delay.
VIDYUT OMBUDSMAN