VIDYUT
OMBUDSMAN
5th Floor, Singareni Bhavan, Red Hills,
Hyderabad –500 004.
Dated: 19-07-2006
Present: S. Surya Prakasa Rao, Ombudsman
M/s.
Saraswathi Binny Rice Mill
Pedda
Thanda (Post)
Khammam
Rural (Mandal)
Khammam
District. …
Appellant
and
1.
Divisional Engineer / Operation
/ Khammam.
2.
Assistant Divisional
Engineer / Operation / Rural / East / Khammam
3.
Assistant Accounts
Officer / ERO / Town / Khammam
… Respondents
This
appeal dated 15-05-2006 made by M/s Saraswathi Binny Rice Mill, Pedda Thanda,
Khammam (Rural) represented by Sri.B.Pulla Rao, (hereinafter called the
appellant) against the order dated 17-04-2006 of the Forum for redressal of
grievances of consumers (hereinafter called CGRF or Forum) NPDCL, Warangal in
C.G.No.29 of 2005 (Khammam Circle) coming up before the Ombudsman, and having
stood over till this day, the Ombudsman issues the following.
O R D E R
2. The facts on record in this case are briefly narrated herein. M/s Saraswathi Binny Rice Mill, is availing
LT supply under LT III(A) Normal category for a contracted load of 50 HP, with
service connection No.1526. The
consumer installed capacitors of required rating. Pursuant to the conditions
stipulated in the Tariff order of the APERC to provide HT metering for the LT
III(A) consumers having connected load of 50 HP to 75 HP, the HT metering was
provided to this consumer in April 2002.
The HT metering provided to the consumer was showing the monthly power
factor for this service as very low and hence the licensee started levy of low
power factor (LPF) surcharge. The
surcharge was first levied in October, 2003 and later in 8 months up to May,
2005, totaling to about Rs.1.5 lakhs. The consumer protested for this levy, but
paid a part of this surcharge after obtaining installments. He then filed a complaint before the Forum
of NPDCL stating that he has installed capacitors of required ratings and hence
LPF is not applicable. He sought
withdrawal of the surcharge levied and also sought refund of the surcharge
already paid by him. The Forum in its
order dated 17-04-2006 ordered for
levy of the surcharge @ 25% (instead of the scale of surcharge applicable for
HT consumers which varies from 1% to 3% for each 0.01 fall from the specified
factor of 0.90) every month from March, 2004 to November, 2005, which totalled
to an amount of about Rs.86,000 as against Rs.1,50,000 levied by the Licensee
for 9 months between 10/2003 to 5/2005.
Aggrieved by the said order of the Forum, the appellant filed this
appeal.
3. In his appeal, the appellant referred to two cases
viz;
(i)
The back billing
assessment made for 14 months in respect of the meter defect noticed during the
inspection of DE/DPE/Khammam on 24-12-2001 and requested to rectify the assessment
by limiting it to 6 months as per Electricity Act.
(ii) The
LPF surcharge levied by the respondents between October 2003 and May 2005 and requested for its withdrawal on
the following grounds:
(a) Capacitors of required rating were installed and they
are in working condition as certified by AAE/Operation/Rural/ Khammam in his
letter dated 26-12-2006.
(b) LPF surcharge is not leviable if the consumer
installed capacitors of required rating and when they are in working condition.
(c)
The Forum levied surcharge
with out considering the clarification issued by CMD/NPDCL. (He also enclosed a copy of Memo dated
01-12-2005 of NPDCL).
4. As required under clause 8(1)(C) of the Regulation No.1 of 2004, a
notice was issued on 18-05-2006 to the parties herein to arrive at a mutually
acceptable settlement by 05-06-2006. If
no settlement is reached, the respondent was required to file the counter by
12-06-2006 and the appellant was required to file rejoinder by 18-06-2006. The respondents have not filed any counter. As no settlement was reached, a notice was
issued on 24-06-2006 fixing
the date for hearing the matter on 10-07-2006 in the office of the Ombudsman at
Hyderabad. Subsequently by notice dated
07-07-2006, (faxed to the respondents and appellant through
SE/Operation/Khammam) the hearing place was shifted to Khammam, in the office
of SE/Operation/Khammam on the same day i.e. 10-07-2006. The appellant and respondents have attended
the hearing conducted in the office of SE/Operation/Khammam on 10-07-2006.
5. In the absence of detailed grounds in the appeal and in the absence of
counter by respondents, the Ombudsman has to depend on his own enquiry during
the hearing and on the material collected in the course of hearing, apart from
the detailed order of the Forum, a copy of which was filed by the appellant
along with the appeal.
6. During the hearing on 10-07-2006 the appellant made the following
submissions:
(i)
Even when zero units
are consumed, the LPF surcharge was levied.
(ii)
Licensee levied the
surcharge for 9 months only where as the Forum ordered for levy of surcharge
for 20 months.
(iii)
Even when all switches
are kept off for full day, the HT meter is recording 40 to 50 units per day and
thus he is paying five to six thousand rupees extra every month. This was brought to the notices of
respondents and CMD also may times.
(iv)
One unit of the
capacitors was rectified after receipt of notice in February, 2004.
(v)
No further notice was
received on the condition of the capacitors.
During the hearing the appellant drew my attention to the MRT test report dated 10-11-2004 and wanted me to study this report before taking the decision. He also handed over a copy of the letter dated 26-12-2005 of the AAE/Operation/Khammmam(R) addressed to AAO/ERO/ Town-Khammam (Respondent No.3) where in the AAE has stated that the consumer installed 3 X 6 KVAR plus 1 X 5 KVAR capacitors which are in working condition. Responding to the locus-standi issue raised by the respondents, (please see para 7(e)) the appellant produced a letter 10-07-2006 signed by Smt.A.Saraswathi, proprietor, Saraswathi Binny Rice Mill, authorizing him to represent the Rice Mill in this case.
In view of the above the appellant
asserted that the Licensee is not entitled to levy the LPF surcharge on the
consumer.
7. (a) The
DE/Operation/Khammam (respondent No.1) replied as follows on the questions put by me.
(i)
Supply was released to
this consumer on 11-03-1999.
(ii)
Though HT metering was
provided in April 2002, the power factor was not computed till September 2003.
The LPF surcharge was levied in 10/2003 as per the formula since power factor
was less than 0.9.
(iii)
The surcharge was not
levied in subsequent months till August 2004, as there was some doubt on the
procedure to be followed.
(b)
I have put a specific
question to the Assistant Divisional Engineer/Operation/Rural(East)/Khammam
(respondent No.2), to inform the basis on which the notice dated 15-02-2004 was
issued and whether any inspection was done and if so to furnish a copy of the
Inspection report. The ADE replied
stating that there is no record of having done any inspection before issue of
the notice in February 2004 and it appears that the notice was issued based on
the power factor computed as per the HT meter readings of January 2004, which
was 0.675. A copy of the notice dated
15-02-2004 issued to the consumer by the respondent No.2, is provided by the
respondents during the hearing, along with other documents mentioned
hereinafter.
(c)
Referring to the
contention of the appellant that he did not receive any further notice after
the notice of February 2004, the DE/Operation/Khammam stated that the consumer
was regularly informed of the low power factor at the time of monthly meter
readings which are also noted in consumer’s register. The ADE/Operation/Rural-East/Khammam, asserted that no reply was
received for the notice dated 15-02-2004 issued by him.
(d)
The respondents have
also stated that the appellant has no locus- standi in this case as the
consumer is a proprietary firm owned by Smt.A.Saraswathi.
(e)
I have drawn the
attention of the respondents to the instructions issued by CMD/NPDCL in Memo
dated 01-12-2005 and asked them to inform the action taken there on. The respondent No.1 stated that these
instructions were implemented only prospectively. He further stated that
inspection was conducted in specific cases which required inspection for
implementation of these instructions.
In view of the above, the respondents
pleaded that the consumer is liable to pay LPF surcharge. The respondents have furnished copies of the
following documents on 10-07-2006.
(i)
Copies of MRT Test
Reports dated 02-02-2000, 09-06-2000, 24-02-2001, and 10-11-2004.
(ii)
Copy of letter dated
26-12-2005 from AAE/Operation/ Khammam (R) addressed to AAO/ERO/Town, Khammam.
(iii)
Copy of the LT
application dated 05-06-1998 of the consumer along with its enclosure.
(iv)
Copy of notice dated
15-02-2004 issued to consumer by ADE/Operation/Rural (East), Khammam.
(v)
Copy of notice dated 29-09-2004
issued to the consumer by ADE/Operation/Rural (East), Khammam.
(vi)
Copy of Memo dated
21-01-2004 of CMD/NPDCL.
The respondent No.3 furnished the
readings of KWh, Energy charges, PF, LPF surcharge etc. in his letter dated
11-07-2006. This data however does not
contain the readings of KVAh, which are used for computing the power
factor.
8. Before framing the issues (points) for consideration in this appeal, it
is to be made clear at the out set that, as the matter relating to back billing
case of 2001 was not raised before the Forum and was not dealt by the Forum,
the appellant is not entitled to raise the same before the Ombudsman. Thus this matter out side the purview of appeal
and hence not considered by the Ombudsman.
Then
the point for consideration in this appeal is
“Whether the LT
category III(A) Industrial Normal category consumer with a connected load of 50
HP and above who is provided with HT metering is required to pay LPF surcharge
as per the power factor obtained in the HT meter readings even if such consumer
installed the capacitors of required rating and when they are in working
condition”.
Point:
9. In the background of the rival contentions narrated herein above, the
point for consideration is discussed in detail here under.
(a) This
matter is similar to the case recently dealt by the Ombudsman in Appeal No.7 of
2006 pertaining to M/s. Pranav Rice Industry, Rampur(K), Adilabad (Rural). In that case, the appellant has quoted the
provisions of Terms & conditions of supply clause 38.9(a) / 38.10(a),
Tariff conditions applicable for LT category III(A) Industrial Normal category
vis-à-vis LT category III(A) Industrial optional demand tariff category etc.,
while the respondents therein relied on clause 23 (LPF surcharge) of the Terms
& conditions of supply. Though the
appellant herein did not quote the relevant provisions, his stand appears to be
based on clause 38.9(a) which requires inspection of the premises and issue of
notice, providing opportunity to consumer to rectify the defect if any with in
30 days failing which only, the surcharge can be lievied. The relevant provisions of the Terms &
conditions of supply (herein after called TCS) and the relevant tariff
conditions (applicable during the period of this case) are extracted in the
Annexure I and Annexure II respectively.
(b) A detailed study of these provisions
reveal that in the case of LT
III(A)-Industrial Optional demand tariff category only, the Licensee can levy Low Power Factor (LPF)
surcharge as in the case of HT consumers, and in the case of others , i.e.,
L.T. III(A) Industrial Normal category, the Licensee has to establish that the
capacitors are defective and are not functioning properly and then issue notice
for its rectification with in a month and to confirm the same. If the consumer does not comply with the
notice, the surcharge can be levied even retrospectively. Though HT metering is
provided for LT III(A)-Industrial Normal
category consumers with
contracted load of 50 HP and above, it was not intended to be used for the levy
surcharge based on the power factor computed form these readings as can be
clearly under stood form the provisions of condition v(b) and v(c) under LT
III(A) Industrial, in part B, LT tariffs, in Annexure ‘D’ of the Tariff order
(2003-04, 2004-05 and 2005-06), which stipulate that the Low Power Factor (LPF)
surcharge is applicable as in the case of
HT consumers for LT category III(A) Industrial optional demand tariff category.
It is clear from this condition that LPF surcharge based on the low
power factor recorded in HT metering, can not be applied for LT III(A) Industrial-Normal category
consumers. Thus the procedure specified
in clause 38.9(a) of TCS should be followed for these consumers. In this case the respondents have not even
inspected the service before issue of notice dated 15-02-2004 and merely relied
on the low power factor recorded in the HT meter to conclude that the
capacitors are defective. This
procedure is not supported by any of the provisions, more so by clause 38.9(a)
of TCS. Hence the notice issued in
February, 2004 is not in accordance with the provisions of clause 38.9(a) of
the TCS.
(c) The respondents have stated before the
Forum that the LPF surcharge was levied as per the instructions of the CMD
NPDCL in Memo dated 21-01-2004, a copy of which is provided along with other
documents at the time of hearing on 10-07-2006. The clarifications issued in the said Memo do not appear to be in
line with the tariff conditions and the TCS discussed above. The fact that different instructions have
been subsequently issued by the CMD NPDCL in Memo dated 01-12-2005 proves this
point. In the Memo dated 01-12-2005,
the CMD/NPDCL issued instructions stating, inter alia, that if the consumer had
installed required rating capacitors, no surcharge need be levied even if the
power factor falls below 0.9 based on the readings of the Trivector meter, if
available. It was also stated there in that
this was also discussed with the APERC on 29-11-2005. The respondents have however implemented these instructions
prospectively from December 2005 onwards but not retrospectively.
(d) During the hearing on 10-07-2006, in
response to my question, the appellant stated that the capacitors were
connected after the main switch. This means that when the Rice Mill is not
working the capacitors will also be switched off. As, the metering is located on the HT side of the Distribution
Transformer (DTR) the reactive power drawn by the DTR during the idle period
would influence the monthly average power factor in the absence of compensation
from the capacitors of the consumer which will be in off position when the mill
is not working. More over rural
industries would not work continuously through out the day in a month. Further, it is to be noted that the DTR is
installed and maintained by the Licensee for LT consumers. In such case, whether the consumer should
compensate the Licensee for the impact of the reactive load imposed by
Licensee’s equipment is a moot question.
(e) Thus in the absence of specific enabling
provision by the competent authority to levy surcharge based on the power
factor recorded in the HT metering provided for LT consumers, I am of the view that
the Licensee can not levy the surcharge.
Perhaps it is necessary to consider the impact of Licensees equipment
(DTR) while prescribing such enabling provision, if any.
(f) In the case of this service, the power
factor computed from the HT readings as furnished in letter dated 11-07-2006 of
respondent No.3 have been far below 0.5 for most of the months while the power
factor (instantaneous) observed during the testing of the consumer load by MRT
Engineers on different dates stood between 0.8 and 0.9 as follows:
|
Date of Test |
Power factor observed |
|
02-02-2000 |
0.895 |
|
09-06-2000 |
0.797 |
|
24-02-2001 |
0.836 |
The
test report dated 10-11-2004 referred to by the appellant during hearing on 10-07-2006
showed the (instantaneous) power factor as follows:
|
R phase |
: 0.860 |
|
Y phase |
: 0.863 |
|
B phase |
: 0.881 |
In
view of the above, it is reasonable to infer that the reactive load of DTR during
non-working of the mill would have substantially influenced the average monthly
power factor computed from the readings in the HT metering, for which in all
fairness, the consumer should not be penalised.
(g) The
learned Forum in its order dated 17-04-2006 took the view that the Licensee is
entitled to levy LPF surcharge @ 25% for failure to rectify the capacitors
pursuant to the one month notice issued in this regard by the Licensee. In coming to this conclusion the learned
Forum appears to have taken it for granted that the LPF is attributable to
defect in the capacitors as contended by the respondents. But the Terms & conditions of supply or
the Tariff conditions do not provide for any such assumption and more over the
impact or DTR during non-working period of the Mill, is not taken into
account. Unless the defect is
established by conducting necessary tests (as per ISS) to check its output
(KVAR), I am of the view that the low power factor cannot be attributed merely
to non-functioning of capacitors. Hence
I am unable agree with the view of the learned Forum in this regard. The order of the learned Forum is therefore
liable to be set aside.
10. Concluding
the above discussion, I decide the following award in this appeal
(a) The surcharge levied on the consumer towards the low power
factor from October, 2003 on wards upto November, 2005 shall be withdrawn for
the following reasons:
(i)
The consumer provided
the LT capacitors of required rating as per the TCS and Tariff order and their
defect is not established by the respondents.
(ii)
There is no specific
provision in the Tariff orders of the Commission for the year 2003-04 to
2005-06 imposing the liability for payment of low power factor surcharge on LT
III(A) Industrial-Normal category consumers based on the power factor computed
as per the trivector metering provided on HT side of the DTR for such
consumers.
(b) The amount paid, if any, by the consumer towards the LPF
surcharge for the period between October, 2003 and November, 2005 shall be
refunded by adjustment in future CC bills.
(c) Such adjustment shall convence form the month in which the
appellant gives acceptance letter for this award in terms of clause 12 of the
Regulation No.1 of 2004.
11. Before
parting with this case, I would like to request the respondent No.1 to examine
whether the consumer be advised to install the 5 KVAR capacitors before the
main switch so that this capacitor bank would always be connected to the LT Bus
of the DTR and would compensate for the inductive load of the DTR even during
the non-working period of the Mill.
Such suggestion was made by the DE/Operation/Adilabad in the case of
Pranav Rice Industry referred in para 9(a) above.
This order is signed on the 19th day of July, 2006.
VIDYUT OMBUDSMAN
To
1. M/s. Saraswathi Binny
Rice Mill
Pedda Thanda (Post)
Khammam Rural (Mandal)
Khammam District.
2. Divisional Engineer /
Operation / Khammam.
3. Assistant Divisional
Engineer / Operation / Rural / East / Khammam
4. Assistant Accounts
Officer / ERO / Town / Khammam
Copy
to
The
Chairperson,
Forum
for redressal of grievances of consumers,
NPDCL,
Warangal.
The
Secretary, APERC,
Hyderabad.
Annexure - I
The relevant provisions of
TCS and the tariff conditions of Tariff order of the relevant period
Clause 38.9(a): “Power Factor of apparatus other than welding
Transformer: Every L.T. consumer using induction motors shall instal L.T. shunt
capacitors of specified rating as given below.
|
SI.No. |
Rating of individual motor |
KVAR rating of L.T.
Capacitors for various R.P.M. of the
motors |
|||
|
750 RPM |
1,000 RPM |
1,500 RPM |
3,000 RPM |
||
|
1. |
3 h.p. |
1 |
1 |
1 |
1 |
|
2. |
5 h.p. |
2 |
2 |
2 |
2 |
|
3. |
7.5 h.p. |
3 |
3 |
3 |
3 |
|
4. |
10 h.p. |
4 |
4 |
4 |
3 |
|
5. |
15 h.p. |
6 |
5 |
5 |
4 |
|
6. |
20 |
8 |
7 |
6 |
5 |
|
7. |
25 h.p. |
9 |
8 |
7 |
6 |
|
8. |
30 h.p. |
10 |
9 |
8 |
7 |
|
9. |
40 h.p. |
13 |
11 |
10 |
9 |
|
10. |
50 h.p. |
15 |
15 |
12 |
10 |
If
the existing consumer fails to install capacitors of required rating within
such time as may be fixed by the Board, such of those consumers as may be
specified by the Board are liable to pay surcharges as may be fixed by the
Board from time to time. If the
capacitors already installed are found, during inspection, to be damaged or
become defective or cease to function, the consumer shall be served with a
notice to get the same replaced/rectified or corrected within 30 days of the
inspection and intimate the fact of replacement/rectification to the concerned
Section Officer, Operation, of the Board, who will inspect the capacitors again
to verify their satisfactory performance.
In the event of failure on the part of the consumer to comply with the
above notice, the Board may levy a surcharge of 25% per month on the bill
amount or as may be prescribed by the Board from time to time from the date
from which the capacitor was defective or ceased to function till such time the
capacitor is replaced/rectified or corrected., Provided further that such
retrospective levy of surcharge shall be limited to one year from the date of
inspection. The consumer aggrieved by
the retrospective levy, may appeal to the concerned Superintending Engineer,
Assessments, whose decision shall be final.
The failure on the part of the consumer to comply with the above notice,
shall be treated as violation of Terms and Conditions of Supply and Board
reserves the right to terminate the contract and collect the balance initial
period agreement.”
Clause 38.10(a): “Every consumer whose connected load includes
welding transformer shall install L.T. shunt capacitors of the capacity
mentioned in clause 38.10.1 and 38.10.2 for improving the power factor. If the existing consumers fail to install
capacitors of required rating within such time as may be fixed by the Board
such of these consumers as may be specified by Board, are liable to pay
surcharge, as may be fixed by the Board from time to time.
If
the capacitors already installed are found, during inspection to be damaged or
become defective or cease to function, the consumer shall be served with a
notice to get the same replaced/rectified or corrected within 30 days of the
inspection and intimate the fact of replacement/rectification to the concerned
Section Officer (Operation) of the Board, who will inspect the capacitors again
to verify their satisfactory performance.
In
the event of failure on the part of the consumer to comply with the above
notice, the Board may levy a surcharge of 25% per month on the bill amount or
as may be prescribed by the Board from time to time from the date from which
the capacitor was defective or ceased to function till such time the capacitor
is replaced/rectified or corrected.
Provided further that such retrospective levy surcharge shall be limited
to one year from the date of inspection.
The consumer aggrieved by the retrospective levy, may appeal to the
concerned Superintending Engineer/ Assessments, whose decision shall be final.
The
failure on the part of the consumer to comply with the above notice, shall be
treated as violation of Terms and Conditions of Supply and Board reserves the
right to terminate the contract and collect the sum equivalent to the minimum
charges for the balance initial period of agreement.”
Clause 23 of TCS
“23:
Surcharges for lower power Factor: The power factor for the month
shall be the ration of Kw hours to the Kilo-Volt Ampere-Hours supplied to the
consumer during the month. The power factor
shall be calculated upto two decimal places.
The power factor of the consumer’s installation shall not be less than
0.90. If the power factor falls below
0.90 during any month, the consumer shall pay a surcharge as detailed below.
|
SI.No. |
Power factor Range |
Surcharge |
|
1. |
Below 0.90 & upto 0.85 |
1% of c.c. charges bill of
that month for every fall of 0.01 of power factor from 0.9 |
|
2. |
Below 0.85 & upto 0.80 |
1.5% - do - from 0.85 |
|
3. |
Below 0.80 & upto 0.75 |
2% - do - from 0.80 |
|
4. |
Below 0.75 |
3% - do - from 0.75 |
Should
the power factor drop below 0.75 and so remain for a period of 2 consecutive
moths, it must be brought to 0.90 within a period of 6 months by methods approved
by the Board failing which without prejudice to the right of the Board to
collect the surcharge and without prejudice to such other rights as have
accrued to the Board or any other right of the Board, the supply to the
consumer may be discontinued.”
Annexure
– II
Relevant Provisions of Tariff Orders
“Note: under LT
category III(A), part B, LT Tariffs of Tariff order (2003-04, 2004-05 and
2005-06)
(i)
. . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(v)
(a) . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . .
(b) For
loads 50HP to 75HP the metering will be provided on HT side of the Distribution
Transformer.
(c)
The Low Power Factor (LPF) surcharge is applicable as
in the case of HT consumers for LT Category III (A) Industrial – Optional
demand tariff category.”
“(6) SURCHARGE FOR LOW
POWER FACTOR
The power factor for the month shall be the ratio of
Kilo-Watt hours to the Kilo-Volt-Ampere Hours supplied to the consumer during
the month. The power factor shall be calculated
upto two decimal places. The power
factor of the consumer’s installation shall not be less than 0.90. If the power factor falls below 0.90 during
any month, the consumer shall pay a surcharge as detailed below:
|
S.No. |
Power
Factor Range |
Surcharge |
|
1. |
Below 0.90 & upto 0.85 |
1% of C.C. charges bill of that
month for every 0.01 fall in Power Factor from 0.90 |
|
2. |
Below
0.85 & upto 0.80 |
1.5% of C.C. charges bill of
that month for every 0.01 fall in Power Factor from 0.85 |
|
3. |
Below 0.80 & upto 0.75 |
2% of C.C. charges bill of that
month for every 0.01 fall in Power Factor form 0.80 |
|
4. |
Below 0.75 |
3% of C.C. charges bill of that
month for every 0.01 fall in Power Factor from 0.75 |
Should the
power factor drop below 0.75 and so remain for a period of 2 consecutive moths
it must be brought upto 0.90 within a period of 6 months by methods approved by
the Licensee failing which, without prejudice to the right of the Licensee to
collect surcharge and without prejudice to such other rights as having accrued
to the Licensee or any other right of the Licensee, the supply to the consumer
may be discontinued.”
Part ‘D’ of Annexure D of the Tariff Order (2003-04
and 2004-05).
1. FOR H.T. AGRICULTURAL CONSUMERS
Every
H.T. Agricultural Consumer using induction motors shall install L.T. Shunt
capacitors of specified rating as given below:
Table of rating of capacitors
|
2. FOR L.T. CONSUMERS
Every
L.T. Consumer using induction motors and welding transformers shall install
L.T. Shunt Capacitors of specified rating as given below:
(a) Motors
|
Table of rating of
capacitors |
(b) Welding transformers
|
Table of rating of
capacitors |
1.
If
any consumer fails to install the capacitors at all or fails to install the
capacitors of required rating or the capacitors already installed are found
during inspection to be damaged or become defective or ceased to function, such
consumer shall attract penal provisions as per General Terms and conditions of
supply notified by the licensee from time to time.
2.
Low
Power factor surcharge is to be levied for the consumers falling under LT III
(A) Industrial (Optional) and LT III (B) Industrial Optional categories as
applicable to HT consumers.
3.
In case the rated capacity of the induction motor or
welding transformer falls in between the steps of the stipulated ratings, the
capacitors suitable for the next higher step shall be installed by the
consumer.
4.
The failure on the part of the consumer to comply
with the above requirement shall be treated as violation of terms and
conditions of the supply and the Licensee can terminate the contract and
collect the sum
equivalent to the minimum charges for the balance initial period of
agreement.”
Part ‘D’ of Annexure D of the Tariff Order (2005-06).
PART ‘D’
POWER
FACTOR APPARATUS and Capacitor Surcharge
1.
FOR H.T. AGRICULTURAL CONSUMERS
Every H.T. Agricultural Consumer using
induction motors shall install L.T. Shunt capacitors of specified rating as
given below:
Table of rating of L.T. capacitors
|
2.
FOR L.T. CONSUMERS
Every L.T.
Consumer using induction motors and welding transformers shall install L.T. Shunt
Capacitors of specified rating as given below:
(a)
Motors
|
Table of rating of L.T.
capacitors |
(b) Welding transformers
|
Table of rating of
capacitors |
NOTE
1. New connections under HT Cat
IV(A),(B), LT Cat III(A),(B), LT Category
IV and LT Category V shall not be given unless the capacitors of required
ratings are installed.
2. If during inspection, no capacitor is
found, or the capacitors already installed are found to be damaged or having defect
or ceased to function, such consumer shall be liable to pay surcharge @ 25% of
the monthly bill amount, as per the terms and conditions of supply notified by
the licensee.
3. Low Power factor surcharge is to be
levied for the consumers falling under
LT III(A) Industrial (Optional) and LT III(B) Industrial Optional
categories as applicable to HT consumers.
4. In case the rated capacity of the
induction motor or welding transformer falls in between the steps of the
stipulated ratings, the capacitors suitable for the next higher step shall be
installed by the consumer.
5. The failure on the part of the consumer
to comply with the above requirement, shall be treated as violation of terms
and conditions of the supply and the Licensee can terminate the contract and
collect the sum equivalent to the minimum charges for the balance initial
period of agreement, apart from disconnection of supply as provided in the
Terms and Conditions of Supply.