|
ANDHRA
PRADESH CODE OF
TECHNICAL INTERFACE Section 4 OPERATION CODE |
Table of Contents
This Section specifies procedures to be followed and data to be exchanged between entities for forecasting demand of the distribution systems by DISCOMs and for forecasting total AP Grid Demand by APTRANSCO through time scales ranging from two years in advance plus the current year through to Control Phase and into real time operation. Long term demand estimation is necessary to ensure generation margin and short-term estimation helps frequency control. Demand Forecast estimates active and reactive power at different points of time in future period and also daily energy requirements for future days.
The maximum active and reactive power at day peak and night peak times and variation in a 24-hour day cycle (load curves) are predetermined by means of sound forecast methodology.
(i) To set out the requirement for consumers and to convey to APTRANSCO in advance the active power, reactive power and daily energy drawals from the transmission system into the distribution system at various connection points.
(ii) To set out the requirements for Users to provide demand and generation data to APTRANSCO to enable it to maintain a sufficient margin during Operational Planning Phase and Programming Phase and to know how much generating plant to schedule and to dispatch, to meet demand on the transmission system and to meet the License Standards. DISCOMs and APTRANSCO will take into account the factors specified when conducting Demand Forecast.
(In general Appendix D of OC is to be followed)
A. From
Large Consumers to DISCOMs:
By the end of October each year the HT and EHT consumers, Captive Power Plants and Cogeneration Units shall provide to the respective DISCOMs in writing details of their Demand (in MW, MVAr, MWh) for two years ahead (April to March year) and for the period November to March of the current year. They must clearly indicate the periods of shut down of their plant for overhaul/maintenance or for other reasons, the reduced demand during such periods and the reduced demand during periods of reduced production for any reason foreseen. The EHT consumers and Captive Power Plants and Cogeneration Units shall submit copies of their Demand forecasts to SLDC also
(i) Each DISCOM shall by the end of November each year provide to APTRANSCO in writing the entire demand forecasts for the period covering December to March of the current year and following two years (April to March year is followed), active power, reactive power, daily energy requirements, peak demands, times of day peak and night peak and daily variation during holidays, the months when maximum agriculture load is expected and the months during which agricultural load will be minimum.
The Methodology adopted in demand estimation may be appended to the data.
(ii) The DISCOMs shall also provide to APTRANSCO estimates of load that may be shed in discrete blocks with details of arrangements of such load shedding.
(iii) Monthly energy, maximum demand and minimum demand by 15th of the preceding month.
C. From
APTRANSCO to other Utilities:
(i) The demand forecasts submitted by DISCOMS to APTRANSCO are modified and rendered more realistic utilising the facility available under the Southern Region System Coordination and Control Project (SRSC&C) and taking into account holidays and weather forecasts received from meteorological Department. The improved versions of the daily demand forecasts for one week ahead and weekly forecasts for one month ahead for various DISCOM territories are transmitted to DISCOMs for use in the operation of distribution systems
(ii) To enable Users to be acquainted with the trends in demand growth during the following two years APTRANSCO shall communicate the validated demand estimates to all existing and prospective generators. APTRANSCO may opt to publish a summary of Demand Forecast in any media.
(iii) Further APTRANSCO shall furnish the information required by any User. APTRANSCO may refuse to furnish any item of data requisitioned by any User if it feels that the particular data is not required by the User for conducting its (the User’s) business.
(iv) APTRANSCO shall furnish to SRLDC the predicted power flows in parts of ISTS relevant to AP System and drawals from ISGS corresponding to the forecasted State demand on daily /weekly/monthly basis for the current year in time scales as mutually agreed between APTRANSCO and SRLDC.
(v) APTRANSCO shall also furnish data to SRLDC for manually feeding the Southern Region System Coordination and Control Project as and when required by SRLDC.
(a) The output in MW and MVAr of each Power Station will be monitored. In case of failure of data transmission channel of APTRANSCO at the State Load Despatch Centre an alternative communications facility will be used.
(b) Loading profiles estimated for each Generating unit for two years ahead shall be furnished in writing by each Generator to APTRANSCO by the end of November each year. Such estimates shall include output in MW for each month in the period.
If the Loading profile of non-centrally dispatched generation materially changes or is expected to change during the Control Phase the Generator must notify SLDC each day, by 10.00 hours, an estimate in writing giving details of the revised estimate of the loading profile for the relevant generating plant for the next schedule day
4.1.4.1 Demand Forecast Procedures to be followed by
DISCOMS:
DISCOMs shall adopt a sound methodology for carrying out Demand forecast. The load growth as foreseen in the first two/three years as per the long term forecast carried out under the provisions of the Planning Code is considered.
Daily variation of the loads of different categories of consumers (domestic, industrial, agricultural) and Demand Side Management implemented are taken into account.
The load variation of different categories of consumers is determined from historical data and synthesized to obtain the total demand at each Connection Point at different times of the day. Seasonal variations and variations on holidays are taken into account. DISCOMs shall obtain data from EHT consumers, Captive Power Plants, Cogeneration Units, Railways (for traction load), and various other industries. General growth trends in housing, industry and agriculture are obtained from the respective Government departments. The expected agriculture load at different times in different seasons is estimated.
4.1.4.2
Demand
Forecast Procedures to be followed by APTRANSCO
(a) Operational Planning and Programming Phase:
APTRANSCO utilises the facility it acquires under SRSC&C Project in estimating the simultaneous maximum Demand of AP State by synthesizing the demand estimates of all DISCOM territories furnished by the DISCOMs.
APTRANSCO shall take into account the following factors in estimating the Grid demand: -
(i) Local factors such as trade holidays, school holidays, seasonal variations of loads and weather forecasts received from meteorological department.
(ii) Anticipated loading profiles submitted by generators and other information furnished by Users.
(iii) Customer demand management.
(iv) Anticipated transfers across external connections.
(b) Control Phase
The factors mentioned in Section 4.3 (Schedule and Despatch) shall be taken into account by APTRANSCO /SLDC for conducting Demand Forecast in the Control Phase.
(a) DISCOMs are responsible for weekly and monthly estimation of demands for the current year and monthly estimates for the year I and Year II ahead for the total service territory of the respective DISCOM as well as for each connection point.
(b) APTRANSCO is responsible for estimation of total AP State demand and power flows in various parts of the transmission system, power flows at ISTS connection points and drawals from ISGS on weekly basis for the current year and monthly basis for Year I and Year II ahead.
(c) Validation of Demand Forecasts prepared by DISCOMS is done by APTRANSCO. APTRANSCO shall independently prepare Demand forecasts using historic data and applying reasonable growth rates. The growth rates are derived from historic growth rates. If the differences between DISCOMs estimates and APTRANSCO projections are small, or if the differences are large but the DISCOMS justify the differences by stating the details of real loads awaiting imminent release of supply (eg. imminent commissioning of new industries or charging of lines supplying new colonies) to the satisfaction of APTRANSCO, the estimates prepared by the DISCOMS are accepted as realistic. Otherwise APTRANSCO shall request DISCOMs to revise the forecasts. If the differences persist, APTRANSCO shall adopt the weighted average of the estimates of DISCOMS and the projection of APTRANSCO. The degree of weightage given to each of the two estimates is decided by APTRANSCO, which is responsible for the consequences of divergence between forecasted demand and actual demand. The decision of APTRANSCO is final.
(d) DISCOMs shall maintain database of the demand at each connection point and for the total demand of the respective DISCOM territory on an hourly basis.
(e) APTRANSCO shall maintain database of the State demand on an hourly basis.
This
Section sets out procedures for coordinated outage Planning of Generating Units, Transmission Lines,
Inter-connecting Transformers and Power Transformers whose
4.2.2
Hormonisation
of Outage Plan
First outage programme of all generating units is evolved so that at any time the total injection into the Grid is adequate to meet the total demand or the deficit is minimum. Priority is given to decide the outage of Generating units because the generating equipment comprises many rotating machines and high temperature systems including furnaces which essentially require shutdown for maintenance, repairs and overhaul for giving good life time performance and enhance availability. Defaulting the maintenance schedules of generating plant may reduce life of the equipment or may reduce the output below MCR. Sometimes postponement of outage may defeat the purpose of postponement by the resulting breakdowns and forced outages. Therefore the generation outage plan is first prepared and basing on this, the outages of transmission elements (including inter-connecting transformers) are decided to correspond the outages of the respective generating units, ensuring that evacuation of the generation from units in service is not affected and the integrity and security of the Grid are maintained. Similarly the outages of distribution systems and transformers feeding 33 kV and 11 kV networks are planned coordinating, the transmission outages. Optimal utilization of hydel power is made possible by a good generation plan.
All Generators shall furnish the tentative outage plans of their generating units for the current year, year 1 ahead and year 2 ahead to APTRANSCO by 30th November. The generators shall indicate urgency for shutdown of particular units, which may be damaged if not shutdown for repair/ maintenance within a given time. SRLDC shall furnish the data pertaining to ISGS.
The methodology to be adopted by APTRANSCO in formulating generation and outage planning is as
follows:
For arriving at generation capability, consideration
is given to the past performance of the thermal
units for the previous three years. From this the available generation for the
future period is estimated.
Regarding Hydel Stations, the average water inflow into
the reservoirs for the last ten years is considered for estimating the average
generation. The annual Hydro Generation
plan formulated by the High Power Irrigation Power Co-ordination Committee is
the main basis for irrigation related hydel generation planning.
Both peak power delivering capability and energy
output are considered.
Demand Forecast carried out as per Section 4.1 are
utilized in preparing Outage Plans.
The objective of this procedure is to define
operational methods used to assist SLDC
to produce a coordinated generation outage program considering all the
available resources and taking into account the constraints in the transmission
system as well as constraints caused by release of water for irrigation or any
other purposes.
To minimize surplus or deficits, if any, in the system
requirement of power and energy and help operate the system at the desired
frequency.
APTRANSCO shall coordinate all utilities and shall
coordinate generation planning.
4.2.6.1 Load Generation Balance
APTRANSCO shall prepare the proposal for the combined
Load Generation Balances for the current Year, Year I and Year II, ahead based
on the Generation Plan submitted by APGENCO,
IPPs, JVCs, CPPs and the AP
State Entitlements from ISGS.
The proposed Load - Generation Balance shall indicate
Power and Energy availability, Generating Units availability, outage periods
and demand forecast for the planning period.
In the quarterly review by the APTRANSCO and in
further examination of monthly programmes by APTRANSCO the proposed Load - Generation Balance Plan prepared by SLDC shall be studied and then the Load
Generation Balance Plan shall be issued for implementation.
APTRANSCO shall periodically review and prepare proposal
for readjusting the Generation Plan to optimise the utilisation of the
available resources in co-ordination with the outages of the transmission
system.
4.2.7 Generation Outage Planning Process
4.2.7.1 Year
I and Year II ahead
a) APTRANSCO shall utilise data received
from AP GENCO, IPPs, ISGS, JVCs, CPPs
and all other generation stations in the preparation of Generation outage
planning for Year I and Year II ahead.
b) APTRANSCO,
shall determine the total power and energy availability for each constituent
for each month for a period of 2 years with the help of the data submitted by APGENCO, IPPs, ISGS and other generating stations.
c) APTRANSCO, shall compile tables
depicting month-wise availability vs. requirement of power and energy, along
with the associated conditions for all
support levels of Thermal Units and release of water for Hydro-stations.
d) The
deficit / surplus rows of the table will indicate periods during which scope
exists for raising, reducing generation.
e) If there
are both surplus and deficits over the planned period, the SLDC shall provide proposals to suitably co-ordinate and stagger
generation outage periods to eliminate or reduce the deficits.
f) If there
are only deficits all through the planned period, the SLDC shall endeavor to even out high and low deficits by similar
shifting of outage periods. Also APTRANSCO
shall endeavor to reduce the average deficit by arranging to import power from
outside the state and increase drawal from ISGS beyond Andhra Pradesh
entitlements.
g) APTRANSCO after having satisfied itself
that maximum improvements have been derived, shall prepare a draft generation
plan and circulate it among all the constituents, requesting for suggestions.
h) The APTRANSCO shall scrutinise and approve
after consulting SRLDC, the
Generation Outage Plan for current year and Year I.
i) The
Generation Outage Programme after coordinating with ISGS shall form the basis
for outage planning cycles.
j) Generation
outage programme shall be harmonised with the Transmission outage planning in
4.2.8 to 4.2.11.
k) No outage
shall be planned for hydel units during the months when overflow of reservoirs
and flooding are normally expected.
a) The
Generation Outage Programme aproved by the Regulatory Commission shall form the
basis of generation outage planning for the current year.
b) The
outage Planning shall be reviewed by APTRANSCO,
taking into account the system conditions viz. transmission plans, unscheduled
outages of transmission lines and generating units, demand changes,
availability of generation in the system.
4.2.7.3
Amendments to Planned Outages
In the case of a planned outage which
APTRANSCO would like to move
(a)
beyond the period
or
(b)
within the period
or with less than 7 days notice. APTRANSCO may upon giving a Generator written
notice, request that the start date or time of outage be advanced or deferred.
If the Generator agrees or APTRANSCO and the Generator agree to some other
period/ date the Generator will take the outage in accordance with that agreement.
A Generator may by notice submitted to APTRANSCO in writing
at any time during year ‘O’, request that a CDGU be substituted by another
comparable CDGU at the Generator’s Power Station having substantially the same
contracted capacity or GSDPs (Generation Scheduling and Dispatch Parameters).
APTRANSCO shall not unreasonably withhold its consent to such substitution. If
APTRANSCO does consent, the final outage programme shall be amended
accordingly.
4.2.8 Transmission and Distribution Outage Planning
The outage
of transmission elements is primarily coordinated with outages of Generating
Units and secondarily with Distribution System outages.
APTRANSCO may convene coordination meetings with Generators.
The outage programmes of the Distribution Systems for the current year,
year 1 and year 2 shall be informed by all DISCOMs to APTRANSCO by 30th
November.
4.2.8.1 SLDC shall prepare a tentative Transmission Outage
Plan including Inter connection Transformers (ICTs), coordinating with the
Generation Outage Plan and with the Distribution Outage Plan. APTRANSCO shall modify the Distribution
Outage Programme following the order of priority, i.e., outage of transmission
elements must be coordinated with generation outage plan and outages
distribution systems must be adjusted to coordinate with transmission
outage. Only minimum changes shall be
made to the outage plans prepared by DISCOMs. APTRANSCO shall communicate the
tentative transmission plan to SRLDC, DISCOMs and Generators by December 15.
The Transmission outage planning shall be done for the following:
1. 400 kV Transmission lines and 400 kV/220 kV Auto
Transformers.
2. 220 kV Transmission lines and 220 kV/132 kV Auto
Transformers.
3. Identified critical 132 kV grid lines of State System
which will affect Transmission System and Grid Operation.
4. Outage planning for 132 kV Radial lines feeding
Distribution Systems and 132 kV consumers shall be carried out separately in
Consultation with Distribution Companies.
The Distribution Outage Plans revised by SLDC shall also
be communicated to DISCOMs by December 15. Coordination meetings shall be
convened by APTRANSCO to discuss and produce coordinated Transmission Outage
Plan and to revise Distribution Outage Plan at the Headquarters of SRLDC and
SLDC. APTRANSCO’s representative shall attend the coordination meetings
convened by SRLDC.
4.2.8.2 The ISTS Outage Plan shall be
communicated by SRLDC to SLDC by 15th December.
4.2.8.3 SLDC shall revise the State
Tranmission Outage Plan to coordinate it with ISTS Outage Plan after taking
into account the decisions and recommendations of the Operation Coordination
Committee of SREB and produce the Draft Transmission Outage Plan. The Draft
Plan is communicated to SRLDC and all users by 31st December.
4.2.8.4 Outage of Power Transformers whose LV
Voltage is 33 kV and 11 kV.
Although the Transformers are owned by APTRANSCO the
operation is to be coordinated with the DISCOMs. The Outage Plan of these
transformers shall be harmonized with the outages of DISCOM Systems and with
the Transmission Outage Programme. DISCOMs shall communicate the Outage Plan of
the Transformers to APTRANSCO before 31st December.
No interruption or minimum interruption to consumers
and Distribution Systems shall be aimed at in formulating coordinated outage plan
of Transmission elements, Transformers and Distribution lines. Parallel
Transformers and alternative line feeding shall be utilized to the extent
possible.
4.2.8.5 Verification with Transformer Outage Plan.
APTRANSCO shall ensure the Transformer Outage Plan is
consistent with Transmission Outage Plan.
4.2.8.6 APTRANSCO shall ensure there is no
evacuation problem in respect of Generating units in service due to
Transmission constraints while evolving Transmission Outage Plan.
4.2.9 Final Verified Overall Outage Plan
APTRANSCO shall issue the final Outage Plan comprising
outage of Generating Units, Transmission and Distribution System by 31st
January and communicate the Plan to SRLDC, all Generators and DISCOMs. The
final overall outage plan as agreed by all entities is released by 1st
March each year.
4.2.10 Postponement
of Outages
The SLDC is authorized to defer any planned shut down
where the following events will affect the satisfactory operation of the
system.
1. Major grid disturbance and total or partial black-out.
2. Systems Isolation
3. Any other incident on the system that may cause an
impact on the system by the proposed outage.
SLDC shall intimate the revised programme as soon as
possible to the user concerned.
4.2.11 Release of Circuits and Generating Units Included in
Outage Plan
Notwithstanding
provisions in any approved outage plan, no cross boundary circuits or unit of a
Generator shall be removed from service without specific release from SLDC.
This restriction shall not be applicable to an individual generating unit of a
CPP.
Once an outage has commenced, if any delay in
restoration is anticipated, the SLDC or the User concerned shall inform the
other party promptly together with a revised estimate of the restoration time.
This Section specifies the procedure to be adopted for
the scheduling and dispatch of Generating
Units to meet demand and allocation requirements
and maintain voltage and frequency within an acceptable range, and defines the
contributions by Users to help achieve this goal.
The objective of this Section is to detail the actions
and responsibilities of SLDC in
preparing and issuing a daily generation schedule and the responsibilities of Users to supply the necessary data and
to comply with this schedule. It also specifies the responsibilities of SLDC and Users in voltage and frequency
management.
APTRANSCO may issue Indicative Running Notification (IRN) informing CDGUs of the generation schedule to be maintained and percentage load it is scheduled during the following Scheduled Day.
APTRANSCO shall use Demand Forecast as the basis for preparing IRN. Outage Plan is also taken into account.
In the absence of
IRN all Generators
shall provide the hourly MW/MVAr availability (00.00 - 24.00 hours) of all Generating Units, to SLDC on the day ahead basis by 10.00
hours. CPPs shall provide the hourly import/export figures on the day
ahead basis by 10.00 hours.
In working
out the MW/MVAr availability, Hydro Power Stations shall take into account
their respective reservoir levels and any other restrictions and shall report
the same to SLDC.
SLDC shall
obtain from SRLDC, the hourly MW
entitlements from ISGS, by 11.00 hours on a day ahead basis. SLDC shall produce a day ahead hourly generation
schedule after consolidation of the data provided by the Generators and SRLDC. It will take into account the hourly demand
estimates and latest planned schedule agreed with SRLDC. In preparation of the schedule, SLDC shall take into account of the relative commercial costs to APTRANSCO of the operation of
Generation units. Full generation at all
Hydel stations will also be included during flooding when reservoirs are full.
SLDC shall intimate the generation schedule/import schedule for the following
day to all Generators / CPPs (including any Generating Unit not required to run) by 16.00 hours.
Generators shall promptly report to SLDC, changes of Generating
Unit availability or capability, or any unexpected situation which could
affect its operation. All CPPs shall similarly report regarding
their export to APTRANSCO.
SLDC shall advise Users as soon as
possible of any necessary rescheduling.
SLDC shall prepare the day ahead generation schedule based on the following:
i)
Transmission System constraints.
ii)
Hourly load
requirements as estimated by SLDC.
iii)
The need to
provide operating margins and reserves required to be maintained.
iv)
The availability
of generation from Generators,
Central Sector Generators and CPPs together with any constraints in each case.
v)
Overall economy
to APTRANSCO and Customers.
SLDC shall
instruct Generators to hold capacity
reserves (spinning and/or standby) to the agreed SREB guidelines or as determined for local conditions. SLDC may also require the Generators/CPPs to generate MVAr within
their respective capability limits to hold station bus bar voltages at
specified levels. If it is not possible to create
reserve, SLDC shall request DISCOMs to arrange rotational load shedding and
create margin.
All Generators
shall regulate generation and CPPs shall regulate their export according to the daily generation schedule.
All Generating
Units, above 30 MW, other than those in a CPP, will be subject to central dispatch
instructions. CPPs will be subject
to these instructions as applicable to their respective exports to APTRANSCO.
SLDC will dispatch by instruction all generation and imports from CPPs according to the hourly day ahead generation schedule, unless
rescheduling is required due to unforeseen circumstances.
In the absence of any dispatch instructions by SLDC, Generators and CPPs
shall generate/export according to the day ahead generation schedule.
Dispatch instructions shall be in standard format.
These instructions will recognise declared availability and other parameters
which have been made available by the Generator
to SLDC. These instructions
shall include time, Power Station, Generating Units (total export in the
case of CPP), name of operators
sending and receiving the same.
Dispatch instructions may include:
i)
To switch a Generator into or out of service.
ii)
Details of
reserve to be carried on a unit.
iii)
To increase or
decrease MVAr generation to assist with voltage profile.
iv)
To begin
pre-planned Black Start procedures.
v)
To hold spinning
reserve.
vi)
To hold Generating Units on standby.
4.3.4.1
Changes in parameters
In
respect of changes in GSDP values the CDGU concerned shall send a GSDP Notice
to SLDC by 1000 hrs on the day before the Schedule Day in respect of revised
values of which the generator is then aware of or after 1000 hrs on the day
before the Schedule Day in respect of revised values of which the generator
subsequently learns.
Dispatch instructions shall be issued by
E-Mail/telephone, confirmed by exchange of names of operators sending and
receiving the same and logging the same at each end. All such oral instructions shall be complied
with forthwith and written confirmation shall be issued promptly by Fax,
teleprinter or otherwise.
All Generators
shall provide hourly generation (MW and MVAr) to SLDC on real time basis.
All Generators
and CPPs shall comply promptly with
a dispatch instruction issued by SLDC
unless this action would compromise the safety of plant or personnel.
The Generator
and CPPs shall promptly inform SLDC
in the event of any unforeseen difficulties in carrying out an instruction.
All Generating
Units shall have Automatic Voltage Regulator (AVR) in service.
All Generators shall
promptly transmit OUTAGE NOTICE to APTRANSCO/SLDC intimating all unplanned
outages of any generating units/ auxiliaries which reduce the generation
contribution to the grid.
All Generating
Units shall have the governor available and in service and must be capable
of automatic increase or decrease in output within the normal declared
frequency range and within their respective capability limit.
Generators shall immediately inform SLDC by telephone of any loss or change (temporary or otherwise) to
the operational capability of any Generating
Unit which is synchronised to the system or which is being used to maintain
system reserve. Generators shall inform SLDC
any removal of AVR and/or governor from service with reasons.
CPPs shall similarly inform any
change in status affecting their ability in complying with dispatch
instructions.
On receiving Notice to synchronise by SLDC, generators shall sysnchronise the
particular unit to the grid within the time prescribed. Inability to do so shall be intimated to SLDC
without loss of time.
Generators shall not de-synchronise Generating Units, other than in respect of CPPs, without instruction from SLDC
except on the grounds of safety to plant
or personnel which shall be promptly reported to SLDC.
Generators and CPPs shall report any abnormal voltage and
frequency related operation of Generating
Units/feeders promptly to SLDC.
Generators shall not synchronise Generating Units, other than in respect of CPPs, without instruction from SLDC.
In emergency situations, the Generator may
synchronise Units with the grid without prior intimation in the interest of the
operation of the grid following standing instructions developed for such
purpose under “contingency planning”.
Should a Generator
fail to comply with any of the above provisions, it shall inform SLDC promptly of this failure.
Schedule and dispatch procedures shall be suitably
enhanced to cater to tariff agreements as soon as any such agreement is reached
with Generators, CPPs, and IPPs.
SLDC shall monitor the frequency of the transmission system and take action to
ensure that they are within acceptable limits in coordination with SRLDC. Corrective
action shall be initiated when frequency deviates by 1% from the nominal value.
Whenever the frequency tends to fall below 50.0 Hz SLDC shall increase the
drawals from Generating Stations including ISGS, according to a pre-arranged
pattern based on economic and merit order despatch. Inter-state drawals also
may be increased/ commenced as per agreements in force.
SLDC shall monitor actual drawal against scheduled drawal and regulate
internal generation/demand to maintain this schedule. The scheduled drawal
shall be intimated by SLDC
beforehand to all Users (DISCOMs and
EHT Customers). The scheduled drawal shall be estimated from previous maximum drawal (power as well as daily energy drawal). The DISCOMs can exceed the scheduled drawal
by 5% without prior approval on any single day provided the frequency is above
49.5 Hz but must obtain prior approval from SLDC to continue the excess drawal from the second day onwards. The
drawal can be increased without limit with prior approval of SLDC. Normally SLDC is expected to approve increase in load if the generation
margin is deemed sufficient.
Generators and CPPs shall follow the despatch instructions
issued by SLDC.
SLDC shall issue standing instructions to all DISCOMs and EHT consumers to
reduce load by a given percentage at different low frequencies. APTRANSCO may
request SRLDC to institute similar
procedure in other Southern States.
Distribution Companies
shall cooperate with SLDC in
managing load, especially for
maintaining the frequency during contingencies such as unexpected generation
outage, by reducing the drawal from the transmission system on instruction from
SLDC.
Whenever the
frequency is below 49.5 Hz the drawals shall be restricted to drawal
schedules. When the frequency falls below 49.0 Hz requisite load shedding
shall be arranged by SLDC through the DISCOMs.
Frequency
indicating meters shall be installed at ALDC control rooms, EHT Sub Stations,
33 kV Sub Stations feeding more than 10 MW and in the premises of EHT
consumers, captive power plants and cogeneration units. Standing instructions
may be given by SLDC regarding action to be taken when frequency falls below 50
HZ.
When the frequency is tending to increase above the
statutory upper limit, SLDC shall
request the Generators to reduce generation and request SRLDC to take necessary
action at Regional level. While reducing generation, merit order despatch
procedure shall be followed by SLDC. In order to implement the merit order
despatch, the relevant cost data shall be furnished by all CDGUs on one-month
ahead basis.
The instructions to reduce generation will be issued
by SLDC by Telephone
communication. Failure of a Generator to
follow the SLDC instructions in this
context will constitute a violation of the CTI and will entail penalties.
During periods of high frequency operation, the SLDC telephone instructions to
Generators shall supercede other provisions of the CTI, and all Acts, Rules and
Regulations of State and Central Governments.
Adequate authority shall be delegated to the duty Engineers of SLDC to
enable them to take spot decisions for on-line operation of the Grid.
On demand by a generator the SLDC shall confirm its
verbal instruction by written instruction after the operation is
completed. SLDC is responsible for
complying all Codes, Acts, etc and must justify its instructions in the light
of Codes, Acts, etc or must be ready to justify any deviation in dealing with
an unforseen emergency threatening the security of the Grid.
SLDC shall carry out load flow studies from time to time to predict where
voltage problems may be encountered and to identify appropriate measures such
as changing transformer tap settings or switching in compensation equipment to
ensure that voltages remain within the defined limits. On the basis of these studies SLDC may instruct Generators and CPPs to maintain specified voltage levels
at interconnecting points and determine voltage levels at the interconnection
points with Distribution Companies.
SLDC shall continuously monitor 400/220/132 kV voltage levels at strategic
sub-stations and communicate the values to SRLDC as basis of on-line operation.
Generators shall make available to SLDC the up-to-date capability curves for all Generating Units, as detailed in the Connection Code, indicating
any restrictions, to allow accurate system studies and effective operation of
the Transmission System. CPPs
shall similarly furnish the net reactive capability that will be available for
export to / import from Transmission
System. Generators and CPPs shall inform SLDC of
their reactive reserve capability promptly on request. SLDC may instruct Generating
Units and CPPs to regulate MVAr generation within
their declared parameters and request SRLDC,
Distribution Companies shall participate in voltage management by regulating
their drawal and by installing compensaton equipment as may be required.
If acceptable voltage levels still cannot be
maintained by these measures, APTRANSCO
shall take steps to augment the transmission system to meet the required voltage criteria.
Users shall provide SLDC
with data for this Section as specified in Appendix 4D-
This Section
describes the actions to be followed by all Users in the event Load
Shedding is required and the recovery process to be followed by all Users in the event of total or partial
blackouts occurring in the Transmission System or Regional System.
The objective of this Section is to define the responsibilities of all Users to prevent a Transmission System or Regional
System blackout, and in the event of such an occurrence, to achieve the
fastest recovery, taking into account essential loads, Generator capabilities and system constraints.
Black start restoration requires a coordinated
approach by all participants to ensure a safe and timely return of electric
service to the distribution companies. Each participant is required to have
procedures in place to facilitate a timely return of electric supply to the
entire grid. Some large coal generating plants require start-up power within
one hour of a blackout or they will take a minimum of five hours to start up
again. It is imperative that these procedures are coordinated and that the
associated control center staff are prepared.
Blackouts disrupt essential services throughout the state. Areas and municipalities will have disaster
plans in place to deal with such disruptions and the State Government will be
requested by APTRANSCO to set up a Disaster Management Cell with a control room
having a twentyfour hours telephone service to assist with these disaster
plans. Whenever a large area of the
state is in a blackout condition, the APTRANSCO
would notify the Disaster Services with information pertaining to the extent of
the outage, expected duration and a phone number to be used for follow-up.
Diesel Generators shall be installed at
all hydel stations except those hydel stations like Pochampadu which dry
up during summer, of capacities sufficient to allow start-up of one generating
unit without need for external power.
Under falling frequency conditions, SLDC shall take appropriate action to
issue instructions, in co-ordination with SRLDC,
to arrest the falling frequency and restore it to be within normal range. Such instructions may include instructions to
Users to reduce load demand by
appropriate manual and /or automatic
load sheddings.
Users shall
provide to SLDC estimates of load
that may be shed, when required, in discrete blocks with the details of the
arrangements of such load sheddings.
SLDC shall maintain a record of Power
Station Black Start capability and associated Power Station Black Start
plans.
APTRANSCO is responsible for
maintaining uptodate restoration procedures following total or partial
blackout. These procedures shall
document the process to be followed by their associated control centre staff to
ensure a safe, reliable, coordinated and expedient restoration of the electric
supply to the transmission grid.
APTRANSCO
shall recognize the need to integrate and coordinate with the restoration
activities of other transmission grids.
It is especially important that these procedures recognize the need to
restore the grid in an organized and efficient manner regardless of ownership
of generating plants and obligations to any particular load center.
APTRANSCO
shall be responsible for gaining the endorsement of their black start
procedures from the other transmission grids.
APTRANSCO
shall be responsible for keeping their control centre staff adequately prepared
and trained to restore the transmission grid in accordance with procedures
defined above.
Users shall agree to Black
Start procedures of APTRANSCO
and promptly inform SLDC when unable
to follow these procedures.
SLDC shall be responsible for directing the overall Transmission System restoration process
by coordination with all Users and SRLDC.
DISCOMs shall be responsible for sectionalising the Distribution System into discrete,
unconnected blocks of demand. They shall
advise SLDC of the amount of MW
likely to be picked up by the synchronising Generating Unit.
Generators shall be responsible for commencing their planned Black Start procedure on the instruction
of SLDC and steadily increasing
their generation according to the demand which SLDC is able to make available.
Hydel Stations shall maintain the Diesel Generating units in good
condition so that the hydel generating units can be started without external
power as provided in 4.5.2.
Current copies of black start procedures will be
circulated to the appropriate agencies not later than November 15th of each
calendar year. Approval by all agencies
shall be acquired no later than December 31st of the same calendar year.
The situation prevailing prior to the occurrence of
the contingency, e.g. availability of specific Generators, transmission
circuits and load demands, will largely
determine the restorations process to be adopted in the event of a total
blackout. SRLDC and SLDC shall
coordinate to determine the extent of the problem. SLDC shall advise all Users
of the situation and follow the strategy as outlined below for restoration.
Each User shall
have designated persons authorised for operation and control available for
communication and acceptance of all operational communications throughout the
contingency. Communication channels shall be restricted to operational
communications only till normalcy is restored.
First it is to be ascertained whether AP System is blacked out or the entire Southern Region is blacked out. If the entire Southern Region is blacked out SLDC shall play its partial role. If only AP System is blacked out SLDC shall direct restoration and obtain assistance from other States and SRLDC.
SLDC shall instruct all relevant Generators having Power
Stations with Black Start
capability to commence their pre-planned Black
Start procedure. SLDC may
require CPPs to extend start-up power supply to Generators as may be feasible.
SLDC shall prepare the Transmission
System for restoration by creating
discrete power islands with no interconnection. Close co-ordination with concerned Distribution Companies shall be maintained during the restoration process to
arrange for discrete demand blocks becoming available to stabilise Generating Units, as these become
available in individual islands. Generators
to whom start up power supply is made available shall sequence their start
up to match their auxiliary power demand with the supply available.
Generators shall inform SLDC
as Generating Units become available to take load, in order that the APTRANSCO may assess the MW demand
which the Generating Unit is likely
to pick up on circuit breaker closure.
SLDC shall co-ordinate with Generators and Distribution
Companies to:
i)
Form discrete
power islands with one Generating Unit
feeding some local demand.
ii)
Extend islands by
adding more Generating Units and
more demand in a coordinated manner maintaining load generation balance.
iii) Synchronise
islands to form a larger, more stable island.
SLDC shall, taking into account sites where system
synchronisers are available, gradually extend the synchronisation until all demand is restored.
SLDC shall utilise any Regional or interstate assistance available, if appropriate, at any
time to assist in the above process. The
procedure developed by SRLDC shall be followed. Also the Indian Electricity
Grid Code is to be followed.
SLDC shall carry out the strategy for total Regional blackout.
SLDC shall carry out simultaneous action to utilise radial
feeders from the Southern Region and
neighbouring States.
SLDC shall ensure with Users that the security of the healthy part of the Transmission System is maintained.
SLDC shall gradually extend the healthy
system to provide start – up power to appropriate Generating Units.
SLDC shall, in close co-ordination with the Distribution Companies and Generators, gradually restore demand to match generation as it becomes available.
All users shall take care to ensure load generation balance is maintained at all times under SLDC’s direction.
4.4.5.4 Blackout involving ISTS
Elements:
Where ISTS elements or important elements of AP State system having significant operational impact on ISTS are involved in the black out the recovery procedures provided in the relevant Section of IEGC are to be complied with.
During the restoration process following Transmission System or Regional System back out conditions, normal standards of voltage and frequency shall not apply.
A list of essential
loads and priority of restoration is given in the Appendix C.
Distribution companies with essential loads shall separately identify non-essential components of such loads, which may be kept off during system contingencies. Distribution Companies shall draw up an appropriate schedule with corresponding load blocks in each case. The non-essential loads can only be re-energised when system normalcy is restored, and as advised by SLDC.
All Users shall pay special attention in carrying out the procedures so that a secondary collapse, due to undue haste or inappropriate loading, is avoided.
Despite the urgency of the situation, careful, prompt and complete logging of all operations and operational messages shall be ensured by all Users to facilitate subsequent investigation into the incident and the efficiency of the restoration process. Such investigation shall be conducted promptly after the incident.
4.5. Operational Coordination with PGCIL, CTU,SRLDC and
SREB
b) APTRANSCO shall
coordinate the day to day operational issues of the A.P Power System and
furnish the data required by SRLDC/SREB and participate in smooth integrated
operation of Southern Region.
c) APTRANSCO shall
depute its experts to the quarterly Protection Committee Meetings (which
analyse fault trippings and decides on improvements which may be necessary) and
also to Operation Committee meetings of SREB.
d) APTRANSCO will
co-ordinate with SREB transmission line outage planning, generation planning
and scheduling of generation unit outage planning, demand estimation, system
operational improvement transmission augmentation and similar operational and
planning programmes of AP Electricity Sector.
e) SLDC shall, in emergency situations,
co-ordinate with SRLDC with regard to power exchange and service restoration.
f) All
utilities including all Generators and DISCOMs shall comply with the
instructions of SLDC and SRLDC to carry out the integrated operation of the
Southern Regional Grid of which AP State is a part. To this end the utilities shall follow the
CTI (AP Grid Code), the Indian Electricity Grid Code, “Operating Procedures of
Southern Region” issued by SRLDC and the Operating Procedures and Manuals
formulated by PGCIL and APTRANSCO . All
utilities shall comply with the instructions issued by APSLDC and SRLDC in the
course of their real time operation and control of the system. If any entity
has a grievance or objection to the spot instructions of SLDC or SRLDC,
the entity must first comply and then the lack of fairness must be brought to the notice of SLDC/ SRLDC for redressal in subsequent period, failing which the entity
may lodge a complaint with APERC /CERC. If any
entity cannot immediately implement an instruction of SLDC/ SRLDC due to
reasons beyond its control or due to the equipment limitation then the entity
must immediately intimate the same (inability to comply) to SLDC/SRLDC and seek
a revised instructions which can be implemented under the circumstances.
4.5.2 Coordination
with SREB and SRLDC
APTRANSCO shall coordinate with SREB and SRLDC in maintaining the voltage, frequency and security in the Southern Regional Grid. The Transmission lines of PGCIL, Inter – State lines, critical lines of AP System and the entitlements of ISGS are listed in statements 4 –1, 4 –2 and 4 – 3. The updated lists are to be kept with SLDC . Also a list of important elements vital for the operation of Southern Regional Grid as recognised by SRLDC in addition to those listed in statements 4 –1 and 4 – 2, is prepared and kept with SLDC for enabling compliance with sub section 6.2 (c) and (d) of Indian Electricity Grid Code wherein it is stipulated that no important element of the Regional Grid shall be deliberately opened without prior clearance of SRLDC.
Table 4-1
I.
Central Sector Interconnecting Transmission Network in
A.P
|
1. |
400kV Cuddapah – |
AP — Karnataka |
|
2. |
400kV Nagarjuna Sagar – Raichur |
AP — Karnataka |
|
3. |
400kV Gooty – |
AP — Karnataka |
|
4. |
400kV Cuddapah – Sriperambadur |
AP — Tamil Nadu |
|
5. |
400kV Ramagundam –
Chandrapur Double Circuit |
AP — |
|
6. |
400kV Gazuwaka—Jeypore |
AP— Orissa |
|
7. |
400kV Ramagundam— Double Circuit |
AP |
|
8. |
400kV Single Circuit |
AP |
|
9. |
400kV Ramagundam—N’sagar Double Circuit |
AP |
|
10. |
400kV Ramagundam—Khammam Single Circuit |
AP |
|
11. |
400kV Khammam—Nunna Single Circuit |
AP |
|
12. |
400kV Nunna—Vishakapatnam Single Circuit |
AP |
|
13. |
400kV N’Sagar—Cuddapah Double Circuit |
AP |
II.
Interstate Lines Connecting
|
1. |
220kV Gachibowli,Hyd – Sadem, |
AP—Karnataka |
|
2. |
220kV Gooty— |
AP— Karnataka |
|
3. |
220kV Chittor—Tiruvalam |
AP— Tamil Nadu |
|
4. |
220kV Sulurpet—Gummidipundi |
AP— Tamil Nadu |
|
5. |
132kV Guntakal—Hampi |
AP— Karnataka |
|
6. |
66kV |
AP— Karnataka |
|
7. |
220kV |
AP— Orissa |
|
8. |
HVDC |
AP— Madhya Pradesh |
(1)
Kothagudem –
Shapurnagar
(2)
(3)
KTPS –
Miryalaguda Single Circuit
(4)
(5)
VTS – Tallapalli
– Double Circuit
(6)
Srisailam –
Somayajulapalli – Gooty Double Circuit
(7)
Srisailam –
Mydukur-Cuddapah-Chinakampally.
(8)
Srisailam –
Chandrayanagutta Double Circuit
(9)
VTS--Tadikonda Double Circuit
(10)
Tadikonda--Ongole Single Circuit
(11)
Ongole--Podili Double Circuit
(12)
VTS—Podili Double Circuit
(13)
Podili—Srisailam Double Circuit
(14)
Tallapalli—Srisailam Double Circuit
(15)
Nagarjunasagar—Tallapalli Double Circuit
(16)
Nagarjunasagar—Tallapalli Single Circuit
(17)
VTS—Malkaram Double Circuit (Via Narketpalli and
Chilakallu)
(18)
KTS
V—Khammam Double Circuit
(19)
Khammam— Wadde
Kothapalli
National Power
Stations With AP Entitlements
|
|
TOTAL
CAPACITY (MW) |
AP
SHARE (MW) |
|
1.Ramagundam Super Thermal Station (
NTPC) |
2100 |
580 |
|
2. |
340 |
28 |
|
3. National Lignite Corporation
(NLC) |
|
|
|
Mine cut II , Stage I |
580 |
97 |
|
Mine Cut II, Stage II |
790 |
180 |
|
TOTALS |
3810 |
885 |
|
Approximate AP Share of unallocated Capacity |
|
115 |
|
Total Approximate AP Entitlement from National Power
Stations |
|
1000 |
Protection committee shall be formed with following composition:-
|
Chairman |
Deputee from APTRANSCO |
|
Secretary |
Deputee from APTRANSCO |
|
Member |
APGENCO (Thermal) Protection in Charge |
|
Member |
Protection
Engineer of any IPP, Deputed by all IPPs to
represent all IPPs, CPPs and JVCs |
|
Member |
Protection of APGENCO
(Hydro) |
|
Member |
SREB |
|
Four Members |
One from each of the four DISCOMs |
(The Chairman and Secretary who are from APTRANSCO and the Representative of SREB shall represent the interests of SRLDC, PGCIL and ISGS also).
The Committee shall hold a meeting at least once
quarterly and also after every major incident in the AP Grid. All trippings and incidents shall be discussed at the Meetings and any remedial
measures including modification to protection schemes, change of relay setting
etc. shall be resolved at these meetings.
Revisions to the parts of the CTI dealing with
protection issues shall be proposed and initiated by the Protection
Committee. When such revisions are
contemplated, the protection committee shall send its representative to CTI
review meetings for placing the issues and committee's recommendations before
the Panel.
The Protection Committee may invite experts from relay
manufacturers, consultants and representatives of other power sector
organizations for participation in the meetings without voting rights.
The Chairman of the Protection Committee is ex-officio
member of the CTI Review Panel and he or his representative shall attend all
CTI Review Panel Meetings whenever protection matters are discussed.
This Section sets down the requirements
for maintaining safe working practices associated with cross boundary
operations. It lays down the procedures to be followed when work is required to
be carried out on electrical equipment that is connected to another User's
system.
The objective of this Section is to achieve agreement
and consistency on the principles of safety as prescribed in Indian Electricity
Rules when working across a control boundary between APTRANSCO and another User.
APTRANSCO and all Users shall nominate suitably authorised
persons to be responsible for the co‑ordination of safety across
APTRANSCO/User interfaces and boundaries. These persons shall be referred to as
Safety Coordinators.
4.7.4.1 General
(i)
APTRANSCO
shall issue a list of Safety Coordinators (names, designations and telephone
numbers) to all Users who have a direct control boundary with APTRANSCO. The jurisdiction of each Safety Coordinator
shall be clearly indicated in the list.
This list shall be updated promptly whenever there is change of name,
designation or telephone number.
(ii)
All Users with a
direct control boundary with the APTRANSCO
shall issue a similar list of their Safety Coordinators to the APTRANSCO, which shall be updated
promptly whenever there is a change to the Safety Coordinators list.
(iii)
Whenever work
across a control boundary is to be carried out, the Safety Coordinator of the
party wishing to carry out work shall directly contact the other relevant
Safety Coordinator. Code words will be agreed at the time of work to ensure
correct identification of both parties.
(iv)
Contact between
the Safety Coordinators shall normally be by direct telephone. Should the work
extend over more than one shift the Safety Coordinator shall ensure that the
relief Safety Coordinator is fully briefed on the nature of the work and the
code words in operation.
(v)
The Safety
Coordinators shall co‑operate to establish and maintain the precautions
necessary for the required work to be carried out in a safe manner. Both the
established isolation and the established earth shall be locked in position,
where such facilities exist, and shall be clearly identified preferably with
easily visible signs.
(vi)
Work shall not
commence until the Safety Coordinator of the party wishing to carry out the
work is satisfied that all the safety precautions have been established. This
Safety Coordinator shall issue agreed safety documentation to the working party
to allow work to commence.
(vii) When work is completed and safety precautions are no
longer required, the Safety Coordinator who has been responsible for the work
being carried out shall make direct contact with the other Safety Coordinator
to request removal of those safety precautions.
(viii) The equipment shall only be considered as suitable for
return to service when all safety precautions are confirmed as removed, by
direct communication using code word contact between the two Safety
Coordinators, and return of agreed safety documentation from the working party
has taken place.
i)
APTRANSCO
shall develop an agreed written procedure for cross boundary safety and
continually update it.
ii)
Users shall also
develop written procedure for crossboundary safety at each connection point.
iii)
Any dispute
concerning Cross Boundary Safety shall be resolved at an appropriate higher
level of authority.
(i)
For cross
boundary circuits, all Users shall comply with the agreed safety rules which
must be in accordance with IE Rules.
(ii)
All equipment on
cross boundary circuits which may be used for the purpose of safety
coordination and establishment of isolation and earthing, shall be permanently
and clearly marked with an identification number or name, that number or name
being unique in that sub‑station. This equipment shall be regularly
inspected and maintained in accordance with manufacturer's specification. Each Safety Coordinator shall maintain a
legibly written safety log, in chronological order, of all operations and
messages relating to safety coordination sent and received by himself. All
safety logs shall be retained for a period of not less than 10 years.
The Safety
Coordinator and working party at a connection site shall refer to the Site
Responsibility Schedule for that site and follow the safety rules pertaining to
that site. These safety rules shall be recorded on the Site Responsibility
Schedule.
Operational Liaison details the requirement for exchange of information relating to
operations and/or events on the total system including the Southern Regional
System which may have an operational effect on:
a)
The APTRANSCO System in the case of an
Operation and/or Event occurring on a User system.
b)
A User System in
the case of an Operation and/ or Event occurring in the APTRANSCO System.
The procedure for issue of warnings in the event of a risk of serious and
widespread disturbances on the whole or part of the APTRANSCO system are set out in the following sections.
The objective of this section is to specify the
information to be exchanged between Users in order to identify the potential
impact of an operation and/or event and to assess the possible risk arising
therefrom, so that appropriate action is taken by the relevant party to
maintain the integrity of the APTRANSCO
system. Also in the case of an Operation in the system of one User the
execution of associated, corresponding and coordinating operations by other
Users and/or APTRANSCO in the
correct sequence and with the required promptness are to be ensured through a
Operational Liaison (O.L) process to safeguard the integrity and healthy
operating condition of the APTRANSCO
System as well as the systems of the Users concerned.
Operation: means scheduled or planned actions relating to the
operation of a system.
Event means an unscheduled or unplanned occurrence on a
system including faults, incidents and breakdowns.
Operational
Effect shall mean any effect on
the operation of the relevant system which may cause the system of APTRANSCO or the other Users to operate
differently from the way in which they would have operated in the absence of
that effect.
a) APTRANSCO: In the case of an operation or an unplanned event in
the APTRANSCO system which may have
an operational effect on a User system, APTRANSCO
will notify the User whose system may, in the opinion of APTRANSCO, be affected.
b) User: In the case
of an operation or an unplanned event on a User system which may have an
operational effect on the APTRANSCO
system, the Users will notify APTRANSCO
who will in turn notify other Users on whose systems the operations may have an
operational effect in the opinion of APTRANSCO.
c) The following are examples of scheduled or planned
actions for which notification in advance will be required under 4.8.4 if they
may have an operational effect.
·
Planned operation
of any circuit breaker or isolator or any sequence or combination of the two
other than at the instruction of APTRANSCO.
·
Voltage Control
d) All
operations on elements of 132 kV or higher voltage or on lines and equipment
having impact on the Regional Grid, must be notified by SLDC to SRLDC.
These
examples are by way of illustration and do not in any way limit the general
requirement to notify in advance.
a)
A notification
under 4.8.4 must contain sufficient details to describe the operation to enable
the recipient to consider and assess the implications and risks existing and
will include the name of the individual reporting the operation on behalf of APTRANSCO or the User. The notification needs to state the cause,
but the recipient may ask questions to clarify the notification and the
notifying party shall provide the necessary information using its reasonable
efforts.
b)
A notification
shall indicate that operation on the Total System or any part of the Total
System is likely, the general nature of the Operation and if
associated power supplies are likely to be affected the estimated time of the
interruption and return to service. The
notification need not state the cause of the operation.
c)
Timing:- A notification under 4.8.4 must be given as
far in advance as practicable as will reasonably allow the recipient to assess
the implication and risks arising.
d)
Recording:- The notification shall be given orally or in
writing. The oral notification is to be confirmed in writing if required either
by the sender or the recipient but response actions shall be taken by the
parties based on the oral notification.
a)
APTRANSCO:-
An event or a planned operation on the APTRANSCO
System which has an operational effect on a User system will be notified by APTRANSCO to the Users whose systems
have been affected.
b)
User:- An event or a planned operation on a User
system which has an operational effect on the APTRANSCO System shall be notified by the User to the APTRANSCO who will in turn notify the
other Users on whose systems the event
may have an operational effect.
c)
An event or a
planned operation of APTRANSCO system which has an operational effect on the
Regional Grid shall be notified by APTRANSCO to SRLDC.
d) The
following are examples of situations where notification will be required if
they have an operational effect.
(i)
Where plant and/
or appratus being operated in excess of its capability or may present a hazard
to personnel
(ii)
Activation of any
alarm or indication of any abnormal operating conditions.
(iii)
Adverse weather
conditions being experienced or forecast.
Breakdowns of, or faults in or temporary changes in, the capability of
plant and/or apparatus.
(iv)
Breakdown of, or
faults on, control, communication or metering equipment.
(v)
Increased risks
of protection operations.
(vi)
Breakdown or
fault in the APTRANSCO System.
(vii)
Opening and
closing of Isolators and Circuit
Breakers.
These examples are illustrative only and in no way limit the general
requirement to notify.
A significant incident is an
event with a significant effect on either the APTRANSCO system or a User’s
system and usually entails one or more of the following operational effects:
·
Tripping of plant
and/ or apparatus manually or automatically.
·
Voltage outside
statutory limits.
·
System frequency
outside statutory limits.
·
System
instability
· System overloads.