Table Of Contents
1 GENERAL CODE
1.1 General Issues
1.1.1 Scope
The Code of
Technical Interface is a document that defines the boundary between
APTRANSCO and Users and establishes procedures for operation and development
of facilities connected to the Transmission system. It lays down both the information requirements and procedures governing
the relationship between APTRANSCO and Users.
The C.T.I.
shall be complied with by APTRANSCO,
in its capacity as holder of the
Transmission and Bulk Supply Licence, and by Generators, Distribution Companies,
Suppliers and Bulk Power Consumers in the course of
their activities in generation, supply, and utilization of electricity
and in the capacity as holders of Retail Supply Licence.
The CTI is
designed to facilitate the development, operation and maintenance of
an efficient, co-ordinated and economical AP State transmission system
by specifying to all parties connected to that system, including APTRANSCO, their technical and procedural
obligations. It seeks to be
non-discriminatory and to ensure that interfaces are not areas of weakness
in the supply chain.
The Transmission
and Bulk Supply License requires APTRANSCO to prepare and continually maintain in force, a Grid Code
(or Code of Technical Interface)
Section 18
(Part III) of the License issued
by APERC to APTRANSCO is
reproduced below:
“Section-18 Grid Code
18.1
Except as provided in paragraph 18.4, the Licensee
shall ensure that, within six months from the issue of the Licence,
there is in force at all times a Grid Code, which meets the requirements
of this paragraph 18. Subject to Paragraph 18.11, the Licensee shall
implement and comply with the Grid Code.
18.2
The Grid Code shall include:
(a)
All material technical aspects relating to, connections
to, and the operation and use of the Transmission System including the
operation of electric lines and electrical plant and apparatus connected
to the Transmission System in so far as relevant to the operation and
use of the Transmission System including, but not limited to connections
specifying the technical, design and operational criteria to be complied
with Transmission System or by any Generating Company who is connected
with or seeks connection with the transmission System or the Distribution
System of any Supplier.
(b)
An Operating Code, specifying the conditions under
which the Licensee shall operate the Transmission System and under which
Generating Companies shall operate their plant and the Suppliers shall
operate their Distribution System, in so far as necessary to protect
the security and quality of supply and safe operation of the Transmission
System under both normal and abnormal operating conditions.
(c)
A Planning Code, specifying the technical and design
criteria and procedures to be applied by the Licensee in the planning
and development of the Transmission System;
(d)
A Scheduling and Despatch Code specifying the system
for the scheduling and despatch of Generating Sets.
(e)
Procedures relating to the co-ordination of outages
for scheduled maintenance of Generating Sets and transmission and distribution
circuits;
(f)
A Metering Code, setting
out requirements and procedures for metering, and
(g)
A Protection Code, setting out the requirements and
co-ordination of protection systems.
18.3
The Grid Code shall:
(a)
be designed so as to permit the development, maintenance
and operation of an efficient, coordinated and economical system for
Transmission and Bulk supply in the state of Andhra Pradesh; and
(b)
allow the Licensee to comply with its obligations in
relation to the inter–state transmission of power.
18.4
Where no Grid Code in the form provided for in this
paragraph 18 is in force at the effective date of
this license it shall not be considered a breach of this paragraph 18 provided that:
(a)
the Licensee shall file with the Commission a compilation
of the Interim Grid Code within 60 days of the grant of this License;
(b)
the Licensee shall implement and comply with the Interim
Grid Code from the date of its submission to the Commission, subject
to such modifications as the Commission may direct; and
(c)
Within six months of the commencement of this License,
the Licensee shall submit the comprehensive Grid Code described in Paragraph
18.2 and 18.3 for the approval of the Commission, which must be formulated
by the Licensee after consultation with Suppliers, Generating Companies,
Distribution Licensees, Central Transmission Utility, Regional Electricity
Board and such other Persons as the Commission may direct.
18.5
The Interim Grid Code shall continue to remain in effect
until such time as the Commission has approved the final Grid Code.
18.6
The Licensee shall, in consultatant with Distribution
Licensees, Generating Companies, the Central Transmission Utility, the
Regional Electricity Board and such other persons as the Commission
may specify, review the Grid Code and its implementation from time to
time. The Licensee shall also undertake such review as and when directed
to do by the Commission. All the representations received during the
interim period shall be considered by the Licensee.
Following any such review, the Licensee
shall send to the Commission:
(a)
a report on the outcome of such review;. and
(b)
any proposed revisions to the Grid Code from time to
time as the Licensee reasonably thinks fit for the achievement of the
objectives referred to in paragraph 18.2 and
(c)
all written representations or objections from suppliers
arising during the consultation process.
18.7
All revisions to the Grid Code shall require the prior
written approval of the Commission.
18.8
The Commission may issue directions requiring the Licensee
to revise, supplement or replace the Grid Code in such manner as may
be specified in the directions, and the Licensee shall comply with any
such directions.
18.9
The Licensee shall make available a copy of the Grid
Code in force to any person requesting it at a price not exceeding the
reasonable cost of duplicating it.
18.10
In preparing , implementing and complying with the
Grid Code (including in respect of the scheduling
of maintenance of the Transmission System), the Licensee shall not unduly
discriminate against or unduly prefer:
(a)
any one or any group of Persons or
(b)
itself in the conduct of any business other than the
Transmission Business.
18.11
The Commission may issue directions relieving the Licensee
or (following consultation with the Licensee) third parties of their
obligations to implement or comply with the Grid Code to the extent
as may be specified in the directions.”
The Code of
Technical Interface is not concerned with the detailed design and operation
of the Generator’s Power Stations and Supplier’s Distribution systems,
provided that their overall compatibility with the needs of the Grid
is assured. The responsibilities of the entities are defined and demarcated.
Similarly, the CTI is not meant to be the internal operating instructions
of APTRANSCO's transmission system.
1.1.2 Interpretation
The
meaning of certain terms (which are usually printed in bold letters
and/or capitalized) used in the Code of Technical Interface (CTI) shall
be in accordance with the definitions listed in Section 1.2, “Definitions”
of the C.T.I..
1.1.3
Implementation
and Operation of the C.T.I.
APTRANSCO has the duty to implement
the Code of Technical Interface (CTI). All Users are required to comply
with the CTI, which will be enforced by APTRANSCO. Users must provide
APTRANSCO reasonable rights
of access, service and facilities necessary to discharge its responsibilities
in the User’s premises. Users
shall comply with instructions issued by
APTRANSCO which are reasonably required
to implement and enforce the Code.
If
any User fails to comply with any provisions of the C.T.I., the User
shall inform APTRANSCO without
delay of the reason for its non-compliance. Repeated failures to comply
with the C.T.I. may lead to the disconnection of the User’s plant and/or
facilities. The responsibility for the consequences of disconnection
including payment of damages and compensation to consumers rests with
the User who consistently violates the CTI.
The
Operation of the C.T.I. will be reviewed regularly by the C.T.I. Review
Panel in accordance with the provisions of the relevant Section of the
C.T.I..
The
C.T.I. contains procedures to permit equitable management of day to
day technical situation in the Electricity supply system, taking into
account a wide range of operational conditions likely to be encountered
under both normal and abnormal circumstances, relevant both in the present
conditions and future expanded system and in the present generation
shortage period, as well as surplus generation period which may come
in the future.
However,
the C.T.I. cannot predict and address all possible operational conditions.
APTRANSCO is therefore empowered in such
unforeseen circumstances to act decisively to discharge its obligations
under its License. Users shall provide such reasonable cooperation and
assistance as APTRANSCO may
request in such circumstances. It is to be recognized that the SLDC is required to make quick decisions for remedying Grid crises
and the instant judgments and decisions may contain oversight errors.
Post-event corrections shall be made by SLDC
itself, taking into consideration the feedback from various stakeholders
and consumers. The Users and
consumers have the right to approach the Regulator for redressing their
grievances and unfairness. All
parties must first comply with the spot instructions of SLDC
and if injustice is experienced, the matter shall be represented to
SLDC.
If SLDC does not carry out the necessary changes in the subsequent operation,
the aggrieved party may complain to the APERC.
1.1.4 Code
Responsibilities
In
discharging its duties under the Code of Technical Interface, APTRANSCO has to rely on information which
Users supply regarding their requirements and intentions. APTRANSCO shall not be held responsible
for any consequences that arise from its reasonable and prudent actions
on the basis of such information.
1.1.5
Confidentiality
Under
the terms of the Code of Technical Interface APTRANSCO will receive information from Users relating to their intentions
in respect of their generation or supply businesses. APTRANSCO
shall not, other than as required by the Code of Technical Interface,
disclose such information to any other person without the prior
written consent of the provider of the information.
1.1.6 Dispute
Settlement Procedures
In
the event of any dispute between any Users and APTRANSCO, or between Users, regarding interpretation of any Clause of the Code of Technical Interface,
the matter will be resolved according to procedures set up in this Code
(Section 1.5). The Commission will be the final arbitrator whose decision
shall be final and binding. In the event of any conflict between any
provision of the Code of Technical Interface and any contract or Agreement
between APTRANSCO and a User, the provision of
the Code of Technical Interface shall prevail.
1.1.7
Communications between Licensee and Users
All
communications between APTRANSCO
and Users shall be in accordance with the provision of the relevant
section of the Code of Technical Interface. Unless otherwise specifically
required by the Code of Technical Interface, all communications shall
be in writing, except where operation time scales require oral communication,
in which case these communications shall be confirmed in writing as
soon as practicable.
1.1.8 Partial
Invalidity
If
any provision or part of a provision of the Code of Technical Interface
should become or be declared unlawful for any reason, the validity of
all remaining provisions or parts of provisions of the Code of Technical
Interface shall not be affected.
1.1.9
Directives
Under
the provisions of the Act, the State Government may issue policy directives
in certain matters. The Licensee shall promptly inform the Commission
and all Users of the requirement of such directives. The Users, subject
to the relevant section of the Act, shall comply with the directive.
1.2 Definition of Terms
In the Code of Technical Interface the following
words abbreviations and expressions shall bear the following meanings:
|
TERM
|
DEFINITION
|
|
Act
|
The A.P. State Electricity Reforms Act 1998
|
|
Active Power or MW
|
Product
of voltage and current and cosine of the phase angle between them
measured in units of
Watt
(W)
Kilowatt
(kW) = 103 W
Mega
Watt (MW) = 106 W
Giga
Watt (GW) = 109 W
Tera
Watt (TW) = 1012 W
|
|
Active Energy
|
The electrical energy
produced, flowing in or supplied by an electrical circuit during
a time interval, being the integral with respect to time of Active
Power, measured in units of watt-hours or standard multiples thereof,
that is :-
1000 Wh = 1kWh =
1 unit
1000 KWh = 1MWh
1000 MWh = 1GWh =
1MU (Million units)
1000 GWh = 1 TWh =
1012 Wh
|
|
A.C.
|
Alternating Current
|
|
Agreed Procedure
|
Procedure
for dealing with specific situations in metering as specified
in Section 5.2.3 of the Metering Code.
|
|
Alternator
|
The electrical machine
which is driven by a prime mover and generates AC electric power.
The term Generator is reserved for another meaning to avoid confusion
(see def. of Generator)
|
|
Annual Hydro Plan
|
The plan prepared
by APTRANSCO on the instructions of High Power Electricity Irrigation
Coordination Committee by mid September each year relating to
Water Resource Management during the period of twelve months commencing
on 1st October in that year.
|
Apparent Power
|
S = P + JQ. Magnitude
is calculated by the formula S =
Ö(P2 + Q2) expressed in units
of Volt-amps (VA) or multiples like kVA, MVA
|
|
A.P. Code of Technical Interface
|
The set of principles
and guidelines prepared by APTRANSCO in accordance with the terms
of the Transmission License, as amended from time to time by the
direction of the Commission, relating to the Planning, Design
and Operation of the APTRANSCO System and all Users connected
to it.
|
|
APERC
|
Andhra Pradesh
Electricity Regulatory Commission. (referred to as the ‘Commission’)
|
|
Apparatus
|
All equipment in which
electrical conductors are used, supported or of which they may
form part.
|
|
Appendix
|
An Appendix to a Section
of the Code of Technical Interface
|
|
APGENCO or APGC
|
Andhra Pradesh Generation
Corporation Ltd., registered under the Companies Act and successor
of APSEB in generation of power
|
|
APTRANSCO or APTC
|
Transmission Corporation
of A.P Limited, Registered in 1999 under the Act of 1998 which
is the successor to APSEB in Transmission of Electricity and other
general functions like coordinating all Power Sector entities
in AP State.
|
|
APTRANSCO Control Centre
|
A location used for
the purpose of control & operation of the APTRANSCO system
which, on the transfer date is at Vidyut Soudha in Hyderabad,
Andhra Pradesh
|
|
APTRANSCO Data Collector
|
A data
collecting device owned by APTRANSCO which transmits data to the
Data Collection System of APTRANSCO for the purpose of compiling
information
|
|
APTRANSCO Demand
|
The
Demand on the APTRANSCO system less the output of Independent
Generating Plant limited to provision by the Connection Agreement
|
|
APTRANSCO Site
|
A Site
owned by APTRANSCO, or owned by a User but occupied by APTRANSCO,
in which there is a Connection point.
|
|
APTRANSCO System
|
The
transmission system at voltage levels of 400 kV, 220 kV, 132 kV
and 66 kV.
(The
Distribution system shall be treated as a separate entity of the
Supplier.)
|
|
APTRANSCO System Data
|
Data
concerning the APTRANSCO System to be supplied by APTRANSCO to
Users. APTRANSCO system data consists of salient features to the
existing system and future system as per the perspective plan.
Such data shall contain details of EHV lines (i.e.132KV and above)
and shall include the following:
(a)
Single line diagram of the APTRANSCO system indicating the existing
lines and proposed lines (shown dotted).
(b)
Map of A.P showing the existing lines of the APTRANSCO system
and proposed lines (dotted) preferably to scale 1Cm = 10 kM
|
|
Area of Supply
|
As defined in the
license concerned.
|
|
Area Load Despatch Centre
|
One of the four stations
in AP State being established under Southern Region System Coordination
and Control Project, having as main functions: - Data acquisition
and transfer to SLDC and supervisory control of 132 kV and 33
kV equipment.
|
|
Automatic Load Shedding
|
A Load shedding scheme
implemented by APTRANSCO to prevent frequency collapse or other
problems and to restore the balance between generation output
and demand on the APTRANSCO system
|
|
Automatic Voltage Regulator (AVR)
|
A continuously acting
automatic excitation system to control the voltage of a Generating
Unit measured at the Generator Terminals
|
|
Back Supply
|
Supply of electricity
to the APTRANSCO and for its own use
|
|
BIS
|
Bureau of Indian Standards.
|
|
Black
start
|
The procedure necessary
for a recovery from a Total Shutdown or Partial Shutdown.
|
|
BPTA
|
Bulk Power Transmission
Agreement
|
|
Break-down
|
An occurrence relating
to equipment of supply system which prevents its normal functioning
|
|
Cancelled
start
|
A response by a Generator
to an instruction from APTRANSCO canceling a previous instruction
to synchronize to the APTRANSCO system
|
|
Capability
|
The Capability of
a Generating unit, expressed in MW, to generate electricity determined
at the Interconnection point (after deducting consumption of auxiliaries)
|
|
Captive Power Plant
(CPP)
|
A Power Station which
is primarily operated to meet a Captive Demand
|
CCGT Module
|
A group of Generating
Units comprising one or more Gas Turbine Units and one or more
Steam Units wherein the waste heat from the gas turbines is passed
to the water/steam system of the steam units thereby increasing
the overall efficiency of CCGT Module.
|
|
CEA
|
The Central Electricity
Authority of India.
|
|
CCGT
|
Combined Cycle Gas
Turbine
|
|
CCGT Unit
|
A Generating Unit
within a CCGT Module
|
|
Central Despatch
|
The process of scheduling
and issuing Despatch Instructions in relation to CDGUs direct
to a Generating plant by APTRANSCO pursuant to the Code of Technical
Interface
|
|
CERC
|
Central Electricity
Regulatory Commission established under Electricity Regulatory
Commission Act 1998 and Electricity Laws (Amendment) Act 1998
(Central Acts)
|
|
Central Sector Projects
|
Power Projects and
Transmission Projects built and operated by Central Organisations
such as National Thermal Power Corporation (NTPC), National Hydro
Power Corporation (NHPC), Power Grid Corporation of India Limited
(PGCIL)
|
Centrally Despatched
Generating Unit or CDGU
|
A Generating Unit
within a Generating Plant
|
|
Changed Status Data
of a CDGU
|
Newly arisen factors
pertaining to a CDGU and its parameters which may have a material
effect on the probable output of a CDGU and which must promptly
be intimated to the SLDC by the Generator concerned (Refer also
“GSDP” Notice)
|
|
Civil Emergency
|
Any National disaster
or other emergency which is declared by the State/National Government
as one that is likely to disrupt Electricity supplies
|
|
Code of Technical Interface
Review Panel
|
A standing body established
by APTRANSCO to carry out the following functions.
(a) Keep the Code
of Technical Interface and its working under periodic review
(b) Review any suggestions
for amendments to the CTI at meetings of the panel held in accordance
with the Panel’s constitution, and
(c) Give guidance
in relation to the Code of Technical Interface, its implementation,
performance and interpretation on the reasonable request of any
User.
|
|
Commission
|
The A.P Electricity
Regulatory Commission established pursuant to Sec.3 of the A.P.
Electricity Reforms Act 1998, same as APERC.
|
|
Confirmation Statement
|
A daily statement
prepared by a Generator and submitted to APTRANSCO in accordance
with the relevant PPA.
|
|
Connected Load
|
Aggregate
of rated capacity of all apparatus including portable apparatus
in the Consumer’s premises which are supplied or declared by the
Consumer to be taking supply from the system. This shall be expressed
in kW, kVA
|
|
Connection Agreement
|
An Agreement
between APTRANSCO and a User setting out the terms relating to
a connection to and/or use of the APTRANSCO system
|
|
Connection Conditions
|
Chapter
of the Code of Technical Interface dealing with the condition
of connection of a User’s system to the APTRANSCO System.
|
|
Connection Point
|
A point
at which a User’s Plant and/or Apparatus connects to the APTRANSCO
system or Inter-State Transmission system.
|
|
Connection Site
|
A site
containing a Connection point
|
|
Consumer
|
Any
person supplied with electrical energy by the supplier either
as owner or lawful occupier and whose premises are for the time
being connected to the supplier’s system and includes the consumer
whose power supply, notwithstanding the subsistence of agreement
has been disconnected for the time being
|
|
Contingency Reserve
|
The
margin of generating capacity over forecasted Demand required
in the period from 24 hours ahead down to real time to cover against
uncertainties in Generating plant availability, imports from external
connections and against Demand forecast variations. It is provided
by Generating plants not required to be synchronized but must
be held available to synchronize within 10 to 15 minutes.
|
|
Contract Demand
|
Maximum
kW or kVA agreed to be supplied by the Supplier and reflected
in the agreement executed between the parties
|
|
Contracted Capacity
|
In relation
to a CDGU, the maximum capability of the CDGU as specified in
the relevant PPA. It is
the net active power that can be injected by the CDGU into the
Transmission System at the connection point, excluding the power
consumed in the auxiliaries of the CDGU.
|
|
Control Person
|
A person
identified as having responsibility for cross boundary safety
under relevant Section.(Cross Boundary Safety) of the Code of
Technical Interface
|
|
Control Phase
|
The
phase that follows the Programming phase and starts with the issue
of the Indicative Running Notification for the next schedule day
and covers the period down to real time.
|
|
CTU
|
Central
Transmission Utility. It is an organisation which owns and operates
inter-state and inter-regional transmission system in the territory
of India.
|
|
Data Acquisition System
(DAS)
|
A device provided to record the sequence of operation in time, of the relays / equipment
/ system parameters at a location.
|
|
Data Collection System
|
A system operated by APTRANSCO to collect
data from Generating Stations and Connection points of EHT consumers
and Distribution Systems.
|
|
Delivery Point at Generating
Stations
|
The
point at which a generator transfers power and energy to the APTRANSCO
system and with reference to which the transaction of power and
energy between Generators and APTRANSCO are made. This normally
corresponds to the interface boundary. Meters are usually connected
at this point and if connected at some other point, the quantities
of power and energy will be adjusted with respect to this point.
Generally
the delivery point corresponds to the relevant connection site.
|
|
Delivery Point of Bulk Supply
|
The
point at which energy is delivered by APTRANSCO to a DISCOM and
with reference to which the transaction between APTRANSCO and
the DISCOM is made. This normally corresponds to the interface
boundary. Meters are usually connected at this point, and if located
at some other point, the quantities of energy and power will be
adjusted with respect to this point.
Generally
the delivery point corresponds to the relevant connection site.
|
|
D.G.C
|
The
part of the Distribution Code which is identified as the Distribution
General Supply Code.
|
|
Disclosee
|
Person
to whom confidential information has been disclosed because it
is essential for that person to know the particular confidential
information in order to fulfill his duties/obligations and statutory
requirements.
|
|
Disputes Procedure
|
The
procedure detailed in a PPA for resolving disputes between APTRANSCO
and another party.
|
|
D.O.C
|
That
portion of the Distribution Code which is identified as the Distribution
Operating Code
|
|
D.P.C
|
That
portion of the Distribution Code which is identified as the Distribution
Planning and Connecting code.
|
|
De-Loaded
|
The
condition in which a Generating unit has reduced or is not delivering
electric power to the System to which it is synchronized and the
terms “De-Loading” and “De-Load” shall be construed accordingly.
|
|
De-synchronised
|
The act of taking out a Generating
unit from the APTRANSCO system to which it has been synchronized;
like terms shall be construed accordingly.
|
|
Demand
|
The
Demand of active power and reactive power unless otherwise stated
|
|
Demand Charges
|
Fixed
charges payable by the Consumer at the rate fixed by the Supplier
per KVA of Maximum Demand attained
by the consumer’s system or 80% of Contracted Demand whichever
is higher.
|
|
Demand Control
|
All
or any of the methods of achieving a Demand reduction set out
to the provisions made by APTRANSCO and procedures to be followed
by APTRANSCO and Users to permit reductions in Demand
|
|
Demand Forecast
|
The process which specifies procedures to
be followed and data to be supplied to APTRANSCO to enable APTRANSCO
to forecast Demand on the APTRANSCO system through time scales
ranging from Two years in advance plus the current year through
to the control phase and into real time operation.
|
|
Despatch
|
The
issue by APTRANSCO of instructions to Generating plant pursuant
to Scheduling and Despatch Section(4.3) of Operation Code and
the term “Despatched” shall be construed accordingly.
|
|
Despatch Instructions
|
An instruction by APTRANSCO to a Generator
to operate a CDGU issued in accordance with Section 4.3 (Scheduling
and Despatch) of Operation Code.
|
|
Detailed Panning Data
|
Data
specified in Planning Code.
|
|
Development
|
A Modification
relating to a User’s Plant and/or Apparatus already connected
to the APTRANSCO system.
|
|
Disconnect
|
The
act of physically separating User’s (or Customer’s) equipment
from the APTRANSCO system.
|
|
Distribution Code
|
The
document produced by Distribution Company pursuant to condition
of the Electricity Supply License
|
|
Distribution Mains
|
Portion
of main supply line owned and managed by Supplier with which the
service line is or intended to be connected.
|
|
Distribution System
|
The
Distribution System comprising electric lines and apparatus at
voltage levels of 240V, 400V, 11 kV, 33 kV which as at the Transfer
Date, is owned by APTRANSCO.
|
|
Distributor
|
A person
appointed through an operating agreement for the operation of
a part of the Distribution system
|
|
Earthing
|
A way
of providing a connection between conductors and earth by an Earthing
Device.
|
|
Earthing Device
|
A means
of providing a connection between a conductor and earth being
of adequate strength and capability and conforming to Indian Standard
Code of Practice.
|
|
Earth Fault Factor
|
EFF at a particular location is the ratio
of the highest RMS phase voltage at Power frequency in a sound
phase during earth fault in other phases to the RMS phase voltage
without fault.
|
|
Effective Date
|
The
Transfer Date
|
|
Electricity Board
|
The
erstwhile A.P. State Electricity Board
|
|
Electricity Supply Act
|
The
Electricity Supply Act’1948 as amended up to date
|
Emergency Manual
|
Load
shedding carried out at short notice or no notice for safety of
personnel and equipment or when a Regulating Margin cannot otherwise
be achieved.
|
|
Energy
|
Quantity
of electrical energy measured in units equal to one Kilowatt hour
(kWh) or multiples thereof such as:
1000
Wh = 1
kWh (One Unit)
1000KWh
= 1 MWh
1000MWh
= 1 MU (Million units)
= 1 GWh
|
|
Engineer
|
The Executive Engineer of the Division having
jurisdiction over the area of supply in which the premises to
be served are located and includes any other subordinate Engineer
duly authorised by him or his superior officer.
|
|
Event
|
An unscheduled or
unplanned occurrence on a Grid including faults, incidents and
breakdowns.
|
|
Event Logger (EL) or
|
A device provided
to record the sequence of operations in time, of the relays/equipments
at a location during an event.
|
|
Event Recorder
(ER)
|
|
Export
|
In respect of any party, a flow of electricity
from the plant or apparatus of such party to the plant or apparatus
of another party and the verb “export” and its respective tenses
shall be construed accordingly.
|
|
External Interconnections
|
Apparatus for the
transmission of Electricity to or from the APTRANSCO system into
or out of a Transmission system located outside A.P.State.
|
|
Extra High Voltage or
EHV
|
A voltage exceeding
33000 volts under normal conditions subject, however, to the percentage
variation allowed by the Indian Electricity Rules, 1956 as amended
up to date.
|
|
Fault Locator (FL)
|
A device provided
at the end of a transmission line to measure / indicate the distance
at which a line fault may have occurred.
|
|
Final Metering Scheme
|
A Tariff Metering
scheme as set out in Metering Code Sub-Code 2, intended to be
the permanent metering system after the FMS Date
|
|
Financial Year
|
Period commencing
on 1st day of April and ending on 31st day of March of next year
|
|
Five Minute Reserve
|
That component of
the Operating Reserve which is fully available within 5 minutes
from the time of a frequency drop or a Despatch Instruction pursuant
to Section 4.3 (Scheduling and Despatch) of Operation Code and
which is sustainable for a period 24 hours.
|
|
Flexible Alternating Current Transmission
(FACT)
|
Facilities that enable
power flows on AC lines to be regulated, to control loop flows,
line loadings etc.
|
|
FMS Date
|
In respect of Generation
Metering, the date on which the Final Metering Scheme comes into
effect for all Units and Relevant Connection Sites subject to
such exceptions as may be agreed with the Commission after consultation
in each separate case with the party which operates the Generating
Unit or occupies the Relevant connection site which is subject
to such exception.
|
|
Force Majeure
|
Has the meaning ascribed to that term in the
relevant PPA
|
|
Forced Outage
|
An outage
of a CDGU or item of Power Station equipment of which no notice
can be given by the Generator to APTRANSCO.
|
|
Frequency
|
The
number of alternating current cycles per second (expressed in
Hertz or Hz) at which a System is running.
|
|
Frequency Control
|
The
control of the frequency of the APTRANSCO System. (Practically
it is the control of frequency of the Southern Grid).
|
|
Frequency Sensitive
Mode
|
The operation of a Generating unit whereby
its generation level is varied automatically to compensate for
variations in the frequency of the APTRANSCO System.
|
|
Frequency Transient
|
An abrupt increase or decrease of 0.5 Hz or
more in the frequency of the APTRANSCO System.(and therefore in
the frequency of Southern Region.)
|
|
Frequency
Variation Index (FVI)
|
A performance index representing the degree
of frequency variation from the nominal value of 50.00 HZ over
a specified period of time
N
S (fi – 50)2
i = 1
FV1=10 X --------------------------------
N
Where F i = actual frequency in Hz at i the
time period
N= number
of measurements over the specified period of time
|
|
Full Load
|
Maximum
net electrical output of a Generating Unit after Auxiliaries,
measured at the Interconnection point.
|
|
Generating Plant
|
A Power
Station subject to Central Despatch
|
|
Generator
Data Collector
|
A
data collecting device owned by a Generator available to transmit
data directly to the relevant Generator and dedicated at all times
to such transmission of data to such Generator.
|
|
Generating
Scheduling and Despatch Parameters
|
Information provided by Generator
to APTRANSCO pursuant to the relevant section of the PPA and Section
4.3 of the Code of Technical Interface to enable APTRANSCO to
formulate the generation schedule and dispatch instructions. Such
information shall comprise the capacity and availability of all
generating units and any special factors that may affect the output
of the CDGU
|
|
Generating Unit
|
Any
Apparatus which produces electrical energy including a CCGT Unit.
|
|
Generation Schedule
|
A statement
prepared by APTRANSCO detailing the generation schedule of each
CDGU for a Schedule Day (00 to 24 Hrs) and issued by 1600 hrs
on the previous day with the object of maintaining quality and
security of supply (with adequate margin if available) taking
into account inter-state transfers, the output of central generating
stations, IPPs , JVCs and CPPs.
|
|
Generator
|
A person
or agency who generates electricity and who is subject to the
Code of Technical Interface either pursuant to any agreement with
APTRANSCO or otherwise.
|
|
Generator Reactive Performance
Chart
(Capability Curve)
|
A diagram
which shows the MW and MVAR Capability limits within which a CDGU
is expected to operate under steady state conditions in the manner
prescribed by the manufacturer of the alternator. The diagram
shall indicate the output under different power factors.
|
|
Generator Terminals
|
The
stator terminals of an alternator.
|
|
Good Utility Practice
|
Any
of the practices, methods and acts engaged in or approved by a
significant portion of the electric utility industry during the
relevant time period which could have been expected to accomplish
the desired results at a reasonable cost consistent with good
business practices, reliability, safety and with expedition.
|
|
Governor Droop
|
In relation
to the operation of the Governor of a Generating Unit, the percentage
drop in APTRANSCO system frequency which would cause the Generating
Unit under free governor action to change its output from zero
to full load.
|
|
Grid Code
|
Synonym
of the Code of Technical Interface.
|
|
Grid Entry Point
|
A point
at which a Generating Unit or an External Interconnection connects
to the APTRANSCO system
|
|
Grid Exit point
|
A point
at which electricity may be delivered from the APTRANSCO system
to a customer or to a Distribution System.
|
|
GSDP Notice
|
A notification
by a Generator to APTRANSCO of any change in the GSDP values of
any of its CDGUs previously notified by the Generator in its last
GSDP Notice
(a)
given by 10.00 hours on the day before the relevant Schedule Day
in accordance with Section 4.3.4.1 of Operation Code in respect
of revised values of which the generator is then aware of.
(b)
given after 10.00 hours on the day before the relevant Schedule
Day in accordance with Section 4.3.4.1 of Operation Code in respect
of revised values of which the generator subsequently becomes
aware of.
|
|
High Voltage or HV
|
Voltage
exceeding 650 Volts.
|
|
Hot Standby
|
In relation
to a Generating Unit, a condition of readiness of the Generating
Unit’s boiler to enable the Generating Unit to be synchronized
to the APTRANSCO System and attain an instructed output in a specified
time scale.
|
|
HV Apparatus
|
High
Voltage electrical circuits forming part of a System
|
|
Hydro Station
|
A Hydro-electric Power Station.
|
|
IEGC
|
Indian Electricity Grid Code, a document developed
by the Central Transmission Utility and approved by the Central
Electricity Regulatory Commission which lays down procedures for
operation and development of Regional Grids and the relationship
between various constituents and users of each Regional Grid and
the relationship between the Regional Electricity Board/RLDC and
the constituents in the Region and which primarily deals with
ISTS and ISGS and incidentally with the State Systems.
|
|
Import
|
In respect
of any party, a flow of electricity to the Plant or Apparatus
of such Party from the Plant or Apparatus of another Party and
the verb “import” and its respective tenses shall be construed
accordingly.
|
|
Implementing Safety
Coordinator
|
A person
nominated by APTRANSCO and/or a User to be responsible for the
co-ordination of safe working procedures at a connection point
when cross boundary work is carried out which necessitates the
provision of safety precautions on HV Apparatus. An Implementing
Safety Coordinator may be responsible for more than one connection
point.
|
|
Independent Generating
Plant
|
A Power
Station which is not subject to Central Despatch.
|
|
Independent Power Producer
(IPP)
|
A generating
company not owned /controlled by the Central/State Government.
|
|
Indicative Running Notification
(IRN)
|
A notification
issued by APTRANSCO informing the CDGUs the period and the loading
for which the CDGUs may schedule their units during the following
scheduled day. The Generator may confirm or seek modification
immediately.
|
|
In-Situ test
|
A test
or calibration made on a meter, CT or PT in its normally located
place, with respect to physical mounting, and where it normally
functions.
|
|
Interconnection Point
|
In relation to a CDGU
or generating station the point at which the CDGU or generating
station is connected to the APTRANSCO system and at which Energy
is delivered to APTRANSCO, as specified in the relevant PPA.
|
|
Interconnections
|
The
electric lines, plant or apparatus and meters for the transfer
of electricity to or from the APTRANSCO Transmission System include
into or out of the transmission system of the Power Grid Corporation
of India (PGCIL) or neighboring States.
|
|
Interested Party
|
In relation
to Metering of Generator Circuits at any Relevant Connection Site
of a Generating unit, the Generator which operates such Generating
unit; in relation to Substation metering, APTRANSCO are the interested
parties.
|
|
Inter-State Generating
Station (ISGS)
|
A Central
/MPP/ other generating station in which two or more than two States
have a share and whose scheduling is to be coordinated by RLDC.
|
|
Inter-State Transmission
System (ISTS)
|
Any
system for the conveyance of energy by means of a main transmission
line from the territory of one State to another State
and includes:
(i)
The transmission system to convey energy across
the territory of an intervening State as well as the system for
conveyance of energy within a State, which is incidental to such
inter-state transmission of energy.
(ii) The
system for transmission of energy within the territory of a State
built, owned, operated, maintained or controlled by the Central
Transmission Utility or by any person/ agency under the supervision
and control of the Central Transmission Utility.
|
|
Interim Metering Scheme
|
In respect
of Generation Metering, a Tariff Metering scheme as set out in
the Metering Code, Sub-Code 1, which takes effect from the Effective
Date in relation to Generating Units and Relevant Connection Sites,
commissioned on or prior to such date, until the Final Metering
Scheme comes into effect.
|
|
Intertripping
|
A method of tripping
a circuit breaker on receipt of a signal initiated from protection
at another location
|
|
Isolating Device
|
A switching device
which when in the open position provides an isolation distance. It shall be possible to observe the isolation
distance.
|
|
Isolation
|
The disconnection
of any HV Apparatus from the remainder of the System in which
the HV Apparatus is isolated by approved means such that electricity
cannot pass through the Apparatus and the Apparatus is de-energised.
The state of isolation must be capable of observation.
|
|
Joint System Incident
|
An event occurring
anywhere on the Total System which has or may have a serious and
widespread effect on a User System or on the APTRANSCO system
or may result in cross-boundary
consequences.
|
|
JVC
|
Joint Venture Company,
it is a company in which both Government and a private party hold
substantial stocks.
|
|
KVA
|
Kilovolt Ampere
|
|
LCP
|
Line Clear Permit
|
|
License
|
A License granted
under the Act for the purpose specified
|
|
Licensee
|
Licensee or License
Holder is a person or Corporation to whom a License or Authorisation
is issued by the AP State Government or, under Section 15 of AP
Electricity Reform Act 1998, by the AP Electricity Regulatory
Commission for carrying out transmission, bulk supply or retail
supply of electrical energy in AP State, or a territory inside
AP State for a given period.
|
|
License Standards
|
The standards set
out or referred to in the Transmission License
|
|
Load
|
The
Active and Reactive Power, as the context requires, generated,
transmitted or distributed and all like terms shall be construed
accordingly.
|
|
Load Factor
|
Ratio
of total number of units consumed during a given period to the
total number of units that could have been consumed, had the contract
demand/maximum demand been maintained throughout the same period.
It is usually expressed as a percentage.
|
|
Load Management
Arrangements
|
Agreement
between certain large Users and APTRANSCO for Users to reduce
their Demand at certain times of the year having been given an
advance notice of this requirement by APTRANSCO.
|
|
Load Price
|
That
element of the Generation prices for a CDGU (expressed in Rupees/hour
of operation of the CDGU) which relates to the operation of the
CDGU at no load but which is applicable for all loads of output
of the CDGU.
|
|
Local Safety Instructions
|
The combined sets
of safety instructions supplied by a User to APTRANSCO and by
APTRANSCO to a User which provide necessary information pertaining
to safety precautions and safe working procedures such as, but
not limited to, isolation and earthing, on its side of the connection
point at each connection site. The timing of the issue of the
safety instructions shall be as stated in the connection agreement.
|
|
Loss of Load Probability
(LOLP)
|
The probability of
not being able to meet the peak load of APTRANSCO system due to
planned or forced outage of Generating units.
|
|
Low Frequency Relay
or Under Frequency Relay
|
An electrical measuring
relay intended to operate when
the frequency falls below predetermined value.
|
|
Low Voltage or LV
|
A voltage below 250
volts under normal conditions subject, however to the percentage
variation allowed by the I.E.Rules 1956.
|
|
M.U.
|
Million
Units of Energy (106 kWh)
|
|
Margin
|
An appropriate Operational Planning margin,
set by APTRANSCO, of generating capacity over that required to
meet APTRANSCO Demand.
|
|
Maximum Demand
|
In respect
of any Settlement Period, four times the largest number of Kilowatt
hours supplied and taken during any continuous fifteen minute
period (calculated from either the commencement or the middle
of an hour).
|
|
Mega
Power Project (MPP)
|
A generating station of an IPP having two
or more States as beneficiaries.
|
|
Merit
Order
|
A priority
order of CDGUs compiled by APTRANSCO pursuant to Schedule and
Despatch Section (4.3), generally in ascending order of cost of
energy and taking into account the PPAs, flood water utilisation
at hydel stations, conservation of fuel and lowest cost consideration
for APTRANSCO.
|
|
Metering
|
Tariff
Metering in respect of energy transfer from Generating Stations
to the Grid and from the Grid to Distribution Systems and operational
metering at Generating Stations and EHT Sub-Stations for operational
purposes.
|
|
Metering Code
|
That part of the Code of Technical Interface
identified as the Metering Code and dealing with Interface Metering.
|
|
Metering Committee
|
The Committee in the relevant form established
in accordance with 5.15
|
|
Minimum Demand Regulation
|
That
margin of Active Power sufficient to provide a regulating margin
for adequate frequency control.
|
|
Minimum Generation
|
The
minimum output which a Generating Unit can generate continuously.
This parameter is registered with APTRANSCO as GSDP.
|
|
Monthly Contribution Schedule
|
For
Independent Generating Plants which cannot be despatched the Generator
shall furnish a monthly schedule of contribution of power to the
APTRANSCO system.
|
|
MVA
|
Mega
Volt Ampere = 1000 kVA
|
|
National Grid
|
The
entire inter-connected electric power network of the country,
which would evolve after inter connection of Regional Grids.
|
|
Non-Tariff Consumer
|
A Consumer
who purchases electricity under the terms of a special agreement
and who is subject to Code of Technical Interface either by virtue
of a License or pursuant to an agreement with APTRANSCO, or otherwise.
|
|
Notice to Synchronize
|
A Despatch instruction
given by APTRANSCO to a Generator requiring a CDGU to synchronize
to the APTRANSCO system
|
|
Notified
Area
|
Scheduled areas within
which the Distribution Company/Corporation or Supplier is licensed
to distribute and sell electricity.
|
|
NTPC
|
National
Thermal Power Corporation
|
|
Operating Margin
|
Extra generation capacity
comprising Contingency Reserve and Operating Reserve, that is
required in a system to cover uncertainties in plant availability,
variation in Demand forecast, loss of external connections, loss
of Generation, weakness of APTRANSCO system and other factors
so that the system is operated within the specifications and standards
of the License. (APTRANSCO will issue timely instructions to Generators
to hold the required reserves).
|
|
Operating Reserve
|
The additional output
from the Generating plant and/or the reduction in Demand which
is available to respond/contribute to containing and correcting
any APTRANSCO system frequency deviation to an acceptable level
in the event of a loss of generation, or a loss of import from
an External Interconnection, or mismatch between generating output
and Demand.
|
|
Operational Boundary
|
The
boundary between the systems of any two entities in the total
system or network. It divides the responsibilities and facilities
between the Corporations and defines jurisdiction.
|
|
Operational Metering
|
Meters
and associated equipment including metering and protection equipment
installed by or on behalf of APTRANSCO for:
i) Operational
and System control purposes
ii)
Monitoring Power stations in order to check the output of generating
units or any part thereof, excluding any tariff metering and generator
circuits.
|
|
Operational Planning
|
The
process carried out by APTRANSCO which involves planning through
various time scales, the matching of Generating Capacity with
forecasted APTRANSCO Demand, together with a reserve of generation,
to provide a suitable system margin, taking into account the output
of Independent Generating Plant and External Interconnections,
in order to maintain the security and integrity of the APTRANSCO
system
|
|
Operational Planing
Phase
|
In respect
of Grid Operation and Generation despatching the period between
the fourth week from real time to the end of year II.
|
|
Other User’s Network
|
A system
of a co-generator having a network of its own connected to the
transmission system of APTRANSCO.
|
|
Outage
|
In relation to a CDGU, a total or partial
reduction in Availability due to failure or maintenance of the
CDGU or its auxiliary system; or an interruption in supply of
fuel. In relation to APTRANSCO system, the removal of any part
of the APTRANSCO system due to breakdown or maintenance.
|
|
Outage
Notice
|
A notice
submitted by a Generator under the relevant clause of the Operating
Code notifying APTRANSCO of an unplanned outage or a notice issued
by APTRANSCO to a DISCOM, notifying the DISCOM of an unplanned
outage of APTRANSCO’s system/equipment which affects the supply
to the DISCOM’s System.
|
|
Outage Programme
|
The
programme of outages prepared by APTRANSCO under Operation Code.
|
|
Output
|
The
actual output at the Interconnection point of a CDGU derived from
data measured pursuant to the Metering Code.
|
|
Overall Accuracy
|
The
combined accuracy of meters and instrument transformers whose
secondary circuits feed the meters.
|
|
Ownership Diagram
|
A Diagram
containing numbering and nomenclature prepared for each connection
site indicating the ownership of plant and apparatus by each Corporation.
|
|
Part Load
|
Condition
of a Generating Unit which is loaded but is not running at its
declared availability.
|
|
Partial Shutdown
|
The
condition of a complete loss of generation in a separate part
of the total system with no electricity supply available from
any other part of the total system or external interconnection.(That
part of the total system which cannot begin to function again
without APTRANSCO direction relating to a Black Start). Planned
outage is also applied to the outage of any part of APTRANSCO,
system which may affect supply to any DISCOM’s system of which
APTRANSCO intimates the DISCOM one year ahead.
|
|
Party
|
Any
person, company, organisation, authority, firm or association
subject to the provisions of the Code of Technical Interface
|
|
Planned Outage
|
An Outage
in relation to a CDGU or items of Power Station Equipment which
has been planned and agreed with APTRANSCO in advance of the year
in which it is to be taken. Planned outage also means the outage
of any part of APTRANSCO’s System which may affect supply to a
DISCOM’s System which is intimated by APTRANSCO to the DISCOM
one year ahead.
|
|
Power Factor
|
Ratio
of active power (kW) to apparent power (kVA)
|
|
Power Grid (or PGCIL)
|
The
Power Grid Corporation of India Limited
|
|
Power Purchase Agreement
or PPA
|
The
Agreement entered into between a Generator and APTRANSCO pursuant
to which APTRANSCO amongst other matters, agrees to purchase from
the Generator the capacity of its
Generating Units.
|
|
Power
Station
|
An installation
comprising one or more Generating units (even where sited separately)
owned and/or controlled by the same Generator, which may reasonably
be considered as being managed as one Power Station.
|
|
Power Station Equipment
|
Items
of plant in a Power Station which are integral to the operation
of a CDGU, but which are not used exclusively in the operation
of such CDGU, the outage of which will, or is likely to reduce
the output or availability of a CDGU.
|
Power System Stabilizers
(PSS)
|
A device
into which is fed data of speed, frequency and power and which
controls the output of the exciter of an alternator such that
power oscillations of the synchronous machines are dampened.
|
|
Primary Response
|
The automatic response
of the Governor of a generation unit to APTRANSCO system frequency
changes over a time period of 0 to 30 seconds, from the time of
frequency changes and fully available by 30 seconds and sustainable
for up to 3 minutes.
|
|
Programming Phase
|
The period between
the Operational Planning Phase and the Control Phase, i.e, reckoning
from real time, the period from the issue of IRN to the end of
the Fourth week
|
|
Protected Customer
|
A Customer in relation
to whom, in accordance with guidelines prepared by APTRANSCO and
approved by the Commission, Load Shedding shall, so far as possible,
not be exercised.
|
|
Protection
|
Provisions for detecting
abnormal conditions on a System and initiating fault clearance
and activating alarms and indications.
|
|
Prudent Utility Practice
|
Those practices, methods,
techniques and standards as changed from time to time, that are
generally accepted internationally for use in electric utility
industries taking into account conditions in India and commonly
used in prudent electric utility engineering and operations to
design, engineer, construct, test, operate and maintain equipment
lawfully, safely, efficiently and economically as applicable to
power stations and substations of the size, service and type of
project; and which practices, methods, standards and acts shall
be adjusted, to the extent necessary in order:
1) to conform to operation
and maintenance guidelines recommended by the equipment manufacturers
and suppliers to the project and according to the guidelines given
in the IS code of practice for such equipment.
2) to ensure compliance
with the Indian Electricity Act and Rules and all other Acts and
Laws
3) to take into account
the site location, including without limitation, the climatic,
hydrological and other environmental or general conditions thereof.
4)
to conform to energy conservation and
5)
to conform to General Safety Standards.
|
|
Reactive Power or MVAr
|
The
product of voltage and current and the sine of the phase angle
between them measured in units of volt-amperes reactive (Var)
and standard multiples thereof i.e
1000
VAr. = 1kVAr
1000
KVAr = 1MVAr
|
|
Reactive Energy
|
the
integral with respect to time of the Reactive Power measured in
units of volt ampere hours reactive or standard multiples thereof,
that is:
1000
VArh = 1 kVArh
1000
k VArh = 1 MVArh
|
|
Recorder
|
An apparatus
that stores a series of instantaneous readings at different times
and interval and records the data obtained through a direct internal
or external connection, feeding all such data into an instrument
that allows such internal data to be retrieved at a future point
in time.
|
|
Regional Grid
|
The
entire synchronously connected electric power network of the Region,
comprising ISTS, ISGS and intra-State systems (India is divided
into various Regions each Region comprising a few contiguous states)
|
|
Regional Load Despatch
Centre
|
The
centre so designated for a specified region where the operation
of the power system in that Region and the integration of the
power system with other Regions and areas inside or outside India
are coordinated.
|
|
Registered Capacity
|
The
normal maximum Capability of a Generating Unit (expressed in MW)
|
|
Registrant
|
the
party referred to as such in the
Metering Code who is responsible for a particular Metering.
|
|
Regulating Margin
|
The
margin of generating capacity over Demand which is required in
order to maintain Frequency Control.
|
|
Relevant Connection
Site
|
A site
which includes a point of connection of a Power Station or a DISCOM’s
distribution system or a customer to the APTRANSCO Transmission
system. Generally corresponds to Delivery Point or Metering Point
|
|
Requesting Safety Coordinator
|
The
Safety Coordinator who has responsibility for the HV apparatus
on which work is to be done
|
|
Rotational Load Shedding or Rota Load Shedding
|
Planned Disconnection of Customers on rotational
basis during periods when there is a significant shortfall of
generation required to meet the total demand.
|
|
Safety Coordinator
|
The
person responsible for safe work practices in cross boundary work.
This includes the Implementing Safety Coordinators and the Requesting
Safety Coordinator
|
|
Safety Management
|
The
procedure adopted by APTRANSCO, a Distribution Company or a User
to ensure the safe operation of its system and the safety of personnel
required to work on that system.
|
|
Safety Precautions
|
Methods
and procedures adopted to ensure safety and avoid danger when
working in hazardous environment. In relation to working on HV
apparatus, this entails but is not limited to Isolation and/or
Earthing.
|
|
Safety Procedures
|
The
procedures specified within a safety management system.
|
|
SCADA
|
See
“Supervisory Control and Data Acquisition”
|
|
Scheduling
|
The
process of compiling a Generating schedule as set out by the SLDC,
and the term “scheduled” and like terms shall be construed accordingly.
|
|
Secondary Response
|
The
automatic governor response to Frequency transients which is fully
available within 30 seconds from the time the Frequency transient
occurs and maintained for at least 30 minutes
|
|
Settlement Period
|
In relation
to metering, any period of 15 minutes commencing on the hour or
half hour or quarter hour
|
|
Settlement Values
|
Values
of Active Energy and Reactive Energy delivered and the maximum
demand occurring over a settlement period, as recorded by metering
required by and operating in accordance with the Metering Code,
or as estimated or submitted in accordance with the Metering Code.
Settlement values are identified by the time at the end of the
relevant settlement period
|
|
Shut Down
|
The condition of a Generating Unit where it is at rest or on
barring gear.
|
|
Significant Incident
|
An
event with a significant effect on either the APTRANSCO system
or a User’s system and usually entails one or more of the following
operational effects:
·
Tripping of plant and/ or apparatus manually
or automatically
·
Voltage outside statutory limits
·
System frequency outside statutory limits
·
System instability
·
System overload
Whether
an event has a significant effect on a system is determined by
the entity (APTRANSCO or User) that owns that system.
|
|
Site Responsibility
Schedule
|
For
connection to the APTRANSCO system for which a connection agreement
is required, a schedule prepared by APTRANSCO pursuant to the
relevant connection agreement which shall state for each item
of plant and apparatus at the connection site:-
1) Ownership
of the Plant/Apparatus
2) Responsibility
for control of the Plant/Apparatus
3) Responsibility
for operation of the Plant/Apparatus
4) Responsibility
for maintenance of the Plant/Apparatus and
5) Responsibility
for all matters relating to the safety of any person at the connection
site.
|
|
Site Common Diagram
|
Drawings
prepared for each connection point, which incorporates layout
drawings, electrical layout drawing, common protection/ control
drawings and common service drawings.
|
|
SLDC
|
State
Load Despatch Centre situated at Hyderabad. The SLDC is responsible
for system control and load despatch on real time basis round
the clock for the State of Andhra Pradesh.
|
|
Southern Region System Coordination and
Control Project
|
A unified
computerised facility for carrying out advanced system operational
functions for the power system in the Southern Region (including
SCADA and EMS functions) and comprising SRLDC (Bangalore), SLDC
of all constituent States and ALDCS in each State as main stations.
|
|
Spinning Reserve
|
Unloaded
generating capacity, which is synchronized to the system and is
ready to provide increased generation at short notice pursuant
to Despatch Instruction or instantaneously and automatically in
response to Frequency drop.
|
|
Spinning
Reserve Capability
|
The
ability of a CDGU to provide Spinning Reserve as specified in
the relevant PPA
|
Spinning
Reserve Capability Schedule
|
A schedule
supplied to APTRANSCO in accordance with the Planning Code, listing
all CDGU’s of a Generator and setting out the reserve required
at each MW output of each CDGU
|
|
SREB
|
The
Southern Regional Electricity Board
|
|
SRLDC
|
The
Southern Regional Load Despatch Centre
|
|
Standing
Instructions
|
An instruction
for the Despatch of a CDGU notified to a Generator in advance
by APTRANSCO, whereby when the specified circumstances arise (which
will be capable of being known by the Generator), the Generator
will take the specified action as though a valid Despatch Instruction
had been issued by APTRANSCO.
|
|
Standard Metering
|
The Metering System that as a whole and all
its component parts conform to the relevant Indian Standards and
the Metering Code.
|
|
Start date (outage)
|
The
date on which a planned outage is to begin
|
|
Start time (outage)
|
The
time at which a planned outage is to begin
|
|
Start-up
|
The
action of bringing a Generating unit from shut down to the speed
required by the Generating unit to enable it to be synchronized
to the APTRANSCO system.
|
|
Start-up Price
|
That
element of the Generation Prices for a CDGU which relates to the
start-up of the CDGU.
|
|
State
|
The
State of Andhra Pradesh
|
|
State Government
|
Government
of Andhra Pradesh State.
|
|
Static Var. Compensator
(SVC)
|
An electrical
facility designed for the purpose of generating or absorbing reactive
power.
|
|
Statutory Requirements
for Frequency Control
|
In accordance
with the stipulation under Rule.55 of the Indian Electricity Rules
1956 the Frequency of supply of alternating current shall not
vary by more than 3 percent from the declared frequency which
is 50Hz.
|
|
STU
|
State
Transmission Utility. An Organisation which owns and operates
the Transmission System of the State.
|
|
Substation
|
An assembly
of equipment including any necessary housing for the conversion,
transformation, switching or control of electrical power.
|
|
Subsystem
|
Part
of a System which by itself constitutes a system such as a type
of equipment in a generating plant
|
|
Supervisory Control
and Data Acquisition or SCADA
|
A real
time control and monitoring system in which the control and data
collection functions are carried out from a central station through
a communications system. System data is monitored and fed back
to the central terminal continually, based on which control instructions
are issued to all parts the system. The communication system can
be telephone lines, radio, microwave or any other means of communication.
|
|
Supplier
|
A person
authorised to supply electricity to a consumer under a License
issued by the Commission pursuant to the Act. A Distribution Division
under APTRANSCO drawing power from a Grid substation shall be
treated as Supplier until the Distribution is privatised or corporatised
|
|
Synchronized
|
The
condition where an incoming Generating unit or system is connected
to another system so that the frequencies and phase relationships
of that Generating Unit or System, as the case may be and the
system to which it is connected are identical and the terms “Synchronize”
and “Synchronization” shall be construed accordingly.
|
|
Synchronous compensation
|
The
operation of rotating synchronous Apparatus for the specific purpose
of either the generation or absorption of Reactive Power.
|
|
System Test
|
A Test
carried out by a User or APTRANSCO which involves simulating conditions
or the controlled application of irregular, unusual or extreme
conditions on the User’s system or the APTRANSCO system which
may affect the Total System.
|
|
Tariff Customer
|
A person
who requires a supply of electricity and is supplied by a supplier
on general terms and conditions which are applicable to all customers
belonging to that particular category.
|
|
Tariff Metering
|
The
entire system of measurement of active and reactive energy or
relating to a Relevant Connection Site, comprising meters, associated
current and voltage transformers, metering protection equipment
including alarms, electrical circuitry, their associated data
collectors (including Generator data collectors) and wiring and
other devices or any part thereof. Based on these measurements,
the energy supplying entity raises bills payable by the energy
receiving entity.
|
|
Test Panel
|
A panel
made up of representatives of APTRANSCO, Generators and DISCOMs
as detailed in the Operating Code, which is responsible for various
matters including consideration of proposed system tests and preparation
of a Test Programme.
|
|
Test Programme
|
A programme
prepared by APTRANSCO for conducting tests on the system which
will include.
(a)
Procedures to be adopted for carrying out the system test including
the switching sequence and proposed timings of the sequence.
(b)
The manner in which the system test is to be maintained.
(c)
List of members of staff who will be involved in carrying out
the system test including those who will be responsible for safety
at the connection site/Power station and
(d)
Other matters that APTRANSCO considers appropriate including matters
suggested by Users and identified by APTRANSCO.
|
|
Test Proposer
|
The
entity or authority who first proposes the system test.
|
|
Testing
|
Testing
carried out by APTRANSCO pursuant to System Tests of CDGUs and
User’s Equipment and the term “Test” shall be construed accordingly.
|
|
Tolerance
|
The
allowable deviation from despatch instructions such that at the
end of the Monitoring Period, if the Generator has achieved each
Despatch instruction for the period within the relevant tolerance
limits as per provisions in the PPA, the CDGU will be deemed to
have complied with each Despatch instruction.
|
|
Total Shutdown
|
The
condition of complete loss of generation in the total system with
no electricity supply from any External Interconnection. The total
system will not begin to function again without APTRANSCO’s directions
relating to Black Start.
|
|
Total System
|
Together,
the APTRANSCO system and all other User systems in A.P State.
|
|
Transfer Date
|
The
date notified by the Government of A.P under Section 23(b) of
the Act
|
|
Transmission System
|
The
system consisting of EHV lines owned and/or operated by APTRANSCO
for the purposes of the transmission of electricity from a Power
Station to a Substation or to another Power Station or between
Substations or to or from any External Interconnection including
any plant and Apparatus and meters owned or used by APTRANSCO
in connection with the transmission of electricity.
|
|
Under
Frequency Relay or Low Frequency relay
|
An electric
measuring relay intended to operate when its characteristic quantity
(frequency) decreases below the relay setting by decrease in frequency.
|
|
Unit Load
Controller
|
A device
which regulates the generation level when the Generating Unit
is operating in a Frequency Sensitive Mode to ensure (so far as
possible) that it does not exceed or fall short of previously
set limits.
|
|
User
|
Person
or entity that uses the APTRANSCO system. More specific definitions
are identified in each Section of the Code of Technical Interface.
Examples: A Generator whose generating unit is connected to the
APTRANSCO’s system and a DISCOM whose distribution system is connected
to, and receives power from, the APTRANSCO’s system.
|
|
User System
|
Any
System owned or operated by a User including Generating Units,
Distribution Systems and Customer equipment together with plant
and/or Apparatus connecting them to the APTRANSCO system
|
|
Utility
|
Any
person or entity engaged in the generation, transmission, sale,
distribution or supply, as the case may be of energy.
|
|
Var
|
A single
unit of Reactive Power (Volt-ampere reactive)
|
|
Virtual Metering Point
|
An effective
point of measurement, that may or may not be physically locatable,
where active energy or reactive energy deemed to have been transferred
through the point is derived from an algorithmic manipulation
of the active energy and reactive energy data of one or more metering
points. The phrases “Virtual measurement point”, “real metering
point” and “real measurement point” are to be construed accordingly.
|
|
Warning Notice
|
A notice
issued by APTRANSCO to a Generator informing the Generator that
it has failed to comply with Despatch instructions
|
·
All the expressions used herein but not specifically
defined shall have the same meaning as defined in the I.E Act, 1910,
Electricity Supply Act,1948 and the rules framed there under and if
the said Act, Rules and Codes are silent, the expressions shall have
the same meaning assigned to them in the General Clause Act, 1877 or
in the absence thereof, the meaning as commonly understood in the Electricity
Supply Industry and current Electrical Engineering practices.
1.3
Management
of the Code of Technical Interface (CTI)
1.3.1 Introduction
Under the
terms of the A. P. Transmission and Bulk Supply License, The Licensee (APTRANSCO) is required to implement and comply with the CTI and periodically
review the same and its implementation.
For the above
purpose a CTI Review Panel
comprising representatives of all Users of the Transmission System shall
be established.
Except
under conditions described in the next paragraph, no revision or modification
of the CTI may be made without being discussed at the CTI Review Panel meeting and approved by the Andhra Pradesh Electricity
Regulatory Commission (APERC).
In an
unusual situation where normal day to day operation is not possible
without revision of some clauses of CTI., a provisional revision may
be implemented before approval of APERC
is received, but only after discussion at a special Review Panel Meeting
convened on emergency basis. The APERC
should promptly be intimated about the provisional revision by recorded
means of communication.
The APERC may issue directions requiring APTRANSCO to revise the CTI in such a
manner as may be specified in those directions, and APTRANSCO shall promptly comply with any such directions.
The document defines the procedure to be followed by APTRANSCO in maintaining the CTI and also
in pursuing any change.
The
objective of this procedure is to define the method of managing the
CTI., submitting and pursuing of any proposed change to the CTI and
the responsibility of all Users to effect that change.
1.3.3
Responsibilities
APTRANSCO will
be responsible for managing and servicing the CTI., for discharging
its obligations under the License. APTRANSCO
shall establish and service the requirements of the CTI Review Panel
in accordance with provisions of the relevant sections of the Code.
1.3.4 C.T.I.
Review Panel
APTRANSCO will inform all Users of the
names and addresses of the Panel Chairman and Member Secretary at least
seven days before the first Panel meeting and shall inform Users in
writing of any subsequent changes.
Each User
shall inform the Panel Member Secretary of the names and designations
of their Panel Representatives not less than 3 days before the first
Panel meeting and shall inform the Panel Member Secretary in writing
of any subsequent change.
The Panel shall be chaired by APTRANSCO
and shall consist of the following members:
·
Chairman to be nominated by APTRANSCO
·
Member Secretary to be nominated by APTRANSCO
·
One Member from APGENCO
to represent all Hydel Stations
·
One Member from APGENCO
to represent all Thermal Stations
·
One Member from N.T.P.C.
·
One Member from PGCIL.
·
One Member from SRLDC
(Southern Regional Load Dispatch Centre)
·
One Member to represent all Joint Venture Companies
·
One Member from each Distribution Companies
·
One Member to represent all private IPPs
·
One Member to represent all Captive Power Plants
·
One Member to represent all EHT Consumers
·
The Chairman of the Metering Committee is an
Ex–Officio Member of the Panel.
The Chairman
of the Protection Committee is an Ex-Officio Member of the Panel and
shall attend the Panel meeting whenever protection matters are discussed.
The Panel
shall invite the Chairman of each of the Standing Committees concerned
with particular items of the Agenda. The Chairman of a Standing Committee
may delegate a representative to take part in the discussion.
The Panel
may invite representatives from Consultants, CEA, Central Electricity
Regulatory Commission or, at their discretion, any other Organization
such as Railways, Telecom Department, Indian Standards Organization, Financing Institutions or academic / technical
institutions, to attend the Panel Meeting as observers or non-voting
Members, depending on the Agenda.
The rules
to be followed by the Panel in conducting its business shall be formulated
by the Panel itself and shall be approved by the APERC. The Panel will meet at least once
in three months.
The functions
of the Panel are as follows:
1. To keep CTI and its workings under continuous
scrutiny and review.
1. To
analyze any major Grid disturbances soon after the occurrence, and evolve
any consequent revision to the CTI.
2. To
consider all requests for amendment to the CTI which are proposed by
the Users.
3. To
publish recommendations for changes to the CTI together with the reasons
for the changes and any objections, if applicable.
4. To
issue guidance on the interpretations and implementation of the CTI
5. To
examine problems raised by Users.
6. To
prepare operating instructions
APTRANSCO may
hold sub-meetings with a User to discuss individual requirements and
with a group of Users to prepare proposals for the Panel meeting. The
Panel may set up sub-committees for detailed study of related problems.
1.3.5
CTI
Review and Revisions
The Member
Secretary shall present all proposed revisions of the CTI to the Panel
for its consideration.
APTRANSCO shall
send the following reports to the Commission at the conclusion of each
review meeting of the Panel.
1.
A report on the outcome of such review.
2.
Any proposed revisions to the CTI as APTRANSCO reasonably thinks necessary for achievement of the objectives
referred to in the relevant paragraph of the Transmission & Bulk
Supply License.
3.
All written representations or objections from Users
raised during the review.
All revisions
to the CTI shall require approval of the Commission. APTRANSCO shall publish revisions to the
CTI., once approved by the APERC.
APTRANSCO shall present proposals to the
APERC to allow relaxation,
where Users have difficulties in meeting the CTI.
Every change
from the previous Version shall be clearly marked in the margin. In
addition, a revision sheet shall be placed at the front of the Revised
Version noting the number of every changed sub-section, together with
a brief statement of change.
APTRANSCO shall keep an up-to-date list
of the recipients and locations of all serviced copies of the CTI.
1.4 Communications Between Entities
The Communications existing on the date
of issue of approved CTI are the minimum requirements of communications
and shall be maintained by the respective corporations in good working
condition. The additional communication
facilities as prescribed in the following paragraphs shall be established
within a period of five years from the date of issue of approved version
of the CTI.
1.4.1 Head
Office Communications
The following communications
are to be established between APTRANSCO’s Registered office and Business Head Quarters and each
Generating station.
PSTN Telephone (Listed)
PSTN Telephone (Unlisted)
FAX on DoT Telephone
FAX on Wide band
Telecom network
APTRANSCO
Head Quarters shall have wide band Optical Fiber/Digital Microwave network
communication with all Generating Stations of 50 MW installed capacity
and higher, 400 kVSSs, 220
kVSSs and Inter System Power Exchange Stations connected to PLCC at
nodal points. All EHT sub-stations shall also have DoT telephones
as backup communication.
1.4.2
Communication Between SLDC and Sub-LDC
The following communications are to be
established between SLDC and Sub-LDC offices:
4-Synchronous Data channels for computer
to computer linkage.
4-Voice channels on administrative network.
4-Voice channels on Express network.
All the above channels shall be connected
on Wide Band network communication system i.e., either Optical Fiber
or Digital Microwave.
1.4.3
Communication
Between SLDC & Generating Stations.
The
following communications are to be established between SLDC and Generating
Stations:
Express
channel to Generating Stations
either directly or through EPAX of Sub-LDC connected on Wide Band Network/PLCC.
One administrative channel
to a Generating station through EPAX of Sub-LDC.
DoT Telephone in all Generating
stations and Sub-stations.
SLDC shall have Hot Line connection with
all generating stations of 200 MW capacity and higher on the Wide Band/Digital
network.
1.4.4
Communication
Between Remote Terminal Unit Location And Sub-LDC
The following communications are to be
established between Remote Terminal Unit
locations and Sub-LDC offices:
|
Data
|
Asynchronous
Data channel to Sub-LDC connecting the RTU at each EHT SS to the
computer at the respective Sub-LDC.
|
|
Voice on Admin Dialing Network
|
Admin. Voice channel to Sub-LDC generally routed through EPAX at intermediate
Substations (not more than two or three PLCC lines)
|
|
Voice on Express Dialing Network
|
One Express voice channel single PLCC hop between RTU
location and Sub-LDC with back to back connections at intermediate
stations terminated on EPAXs at either end.
Alternate routes to Sub-LDC via., neighboring PLCC nodes
for redundancy wherever possible
|
|
PSTN Telephone
|
All RTU locations and Sub-LDCs shall have PSTN telephones as backup for
Voice
|
1.4.5 Communication Between
Corporate offices of DISCOMs / District Head Quarters
The following communications are to be
established between Corporate offices of DISCOMs and District Headquarters,
either on PLCC or WIDE-BAND communications:
Administrative
Channel to Sub-LDC
Express Channel
to sub-LDC
Express channel
to SLDC
Administrative
Channel to SLDC
APTRANSCO
Headquarters shall have INTERNET connection. Major EHT consumers
having a demand of 30 MW or more or having captive power plant that
can be connected to the Grid, shall have suitable radio communication
to the connected APTRANSCO
substation and DoT/PSTN phone for voice communication as back-up.
Mini Generating
Stations of capacity less than 30 MW shall have VHF wireless communication
with the connected APTRANSCO substations.
1.4.6
Communication Between EHT Substations
Wide band Network connected between EHT substations shall also
cater to Data and Voice Communication with PLCC as backup. EHT substations not on Wide-Band network shall
have PLCC, PSTN Telephones for Voice / FAX requirements.
1.4.7 Communication between
EHT Substations and 33 kV SS
Point–to–Multipoint Radio Communication
systems shall be provided from each EHT Substation (Master Station)
to all 33 kVSSs (Outstations). Master
stations shall be interfaced to the Broad Band Telecom Network at the
nearest node. PSTN Telephones
shall also be connected at all 33 kV Substations as backup.
1.4.8 Communication For Emergency
& Disaster Management (Voice, Data and MIS) Inter / Intra Entities
VSAT based Satellite Communication shall be provided at all
Generating Stations, 220 kV Substations, Intersystem Power Exchange
Points and nodal 132 kV Substations among and within the entities for
Voice, Data throughout and MIS requirements as backup and for emergency
and disaster management.
1.4.9
Written
Confirmation
all oral or
telephonic communications between
different entities must be confirmed in writing within a reasonable period.
1.4.10 Communication between SLDC and SRLDC. As required by SRLDC.
1.5 Disputes
1.5.1
Disputes regarding interpretation of C.T.I:
The provisional Agreement between
the Corporations having different interpretations is to be followed
till a ruling is issued by the CTI Review Panel.
If one or both parties are not satisfied with the ruling of the
Panel the matter shall be referred to APERC
whose decision is final.
1.5.2 Dispute pertaining to
issues not covered by CTI:
The issue shall be discussed by the
executives of the corporations who shall arrive at an Agreement. If an Agreement cannot be reached the executives
shall formulate a provisional working arrangement and then refer the
issues to the CTI Review Panel even if the issue is not covered by the
C.T.I. The ruling issued by
the CTI Review Panel shall supercede the provisional agreement and shall
be implemented, by all parties. If
any party is not satisfied by the ruling of the CTI Review Panel the
matter shall be referred to the APERC. The decision
of APERC shall be final and
binding.
1.5.3 Continuity of Functioning
of Corporations:
Immediately after a dispute arises the entities shall discuss
and arrive at an agreement. If
an agreement cannot be reached the corporations shall, after deliberations,
formualte a provisional working arrangement which shall be implemented
till a valid ruling is issued by an appropriate authority / arbitrator.
The objective of this procedure is that no dispute should stall
the daily operations of any Corporation.
1.6 Unforeseen
Circumstances:
In situations not addressed by any clause
of the Code of Technical Interface, APTRANSCO
shall convene an emergency meeting with all affected entities to formulate
a solution and the actions to be taken in the circumstance by the various
entities. If no agreement can
be reached, APTRANSCO shall
provisionally determine the action to be taken after giving consideration
to the views expressed by other corporations.
APTRANSCO shall, as
soon as possible, refer the matter to the CTI Review Panel whose decision
shall prevail over the provisional determination of APTRANSCO. If any entity appeals to APERC over the decision of the Panel,
the decision of APERC shall
supersede the decision of the Panel. The normal operations of any Corporation
should never be disrupted by any situation or dispute. The majority
decision of the meeting of entities or the considered determination
of APTRANSCO shall be implemented unless and until the CTI Review Panel
issues a different ruling; and the ruling of the Panel shall be in force
unless and until a different decision is issued by APERC (if the issue is referred to APERC). The decision of APERC is ultimate and shall be implemented
by all corporations.
1.7 Equipment owned
by Third party:
References in the CTI to Plant/Apparatus/Equipment
shall include the Plant/ Apparatus/equipment owned by a third party
but used by a User/APTRANSCO
under any agreement with the third party.
1.8
System Control:
Where a User’s system is, by aggreement,
under the control of APTRANSCO,
then for the purposes of coordination, communication and operational
schedules, APTRANSCO may
treat that User’s system, as part of APTRANSCO’s
system, but, as between APTRANSCO
and Users, it shall remain to be treated as the User’s system.
1.9 Emergency Periods:
In periods of emergency like fuel shortage,
war, national calamities and abnormal law and order situations the State
Government or Government of India may issue certain directions, restrictions,
controls and orders, and if these orders contradict any provisions of
the CTI those provisions, paragraphs or clauses of the CTI shall be
treated as temporarily suspended so as to facilitate implementation
of the Government’s orders as long as the emergency lasts.
1.10 Precedence
of Indian Electricity Grid Code:
This CTI is prepared such that it is consistent
with the IEGC. However if any
clause of the AP CTI (AP Grid Code)
contradicts the provision
of the IEGC during a real situation, the IEGC takes precedence. It is open to APTRANSCO to obtain from CERC
exemption from any provision of IEGC in favour of a clause of AP CTI
where the issue pertains solely to the internal system of A.P (considering
the present, future, direct and indirect impacts) and does not impact
the Southern Regional Grid or the system any of the other constituents
of the Southern Regional Grid.
1.11 Availability Based Tariff
and other Commercial Aspects:
In para 1.8 of the Indian Electricity Grid Code
the rate to be charged for reactive energy exchange is stipulated. Complementary
Commercial Mechanisms are also provided in the IEGC. These tariff rates
and procedures apply to APTRANSCO only for the drawals from ISGS. For
the drawals/injections from/ to other States the tariff as agreed mutually
will apply. Similarly for the active and reactive energy transfers between
Users and APTRANSCO within A. P. State the tariffs approved by APERC
will apply.
1.12 Information in the first
Version of APCTI
Some paras are included for information to facilitate
smooth implementation of the APCTI in the post-unbundling scenario.
They may be deleted in subsequent revisions. Under para 4.6.2 tables
4.1, 4.2 and 4.3 can be deleted in subsequent revisions because maintenance
of updated Regional lines and ISGS entitlements is the internal matter
of APTRANSCO.